CHANCERY DIVISION
MANCHESTER DISTRICT REGISTRY
1 Bridge Street West, Manchester, M60 9DJ |
||
B e f o r e :
Sitting as a Judge of the High Court
____________________
MR CHRISTOPHER SHAW | ||
MRS GABRIELE SHAW | Appellants | |
- and - | ||
MFP FOUNDATIONS & PILING LIMITED | Respondent |
____________________
Mr Richard Bradley (instructed by CE Law, Solicitors, Birkenhead) for the Respondent
Date of hearing: 10 December 2009
____________________
Crown Copyright ©
His Honour Judge Stephen Davies:
Introduction
'The District Judge was wrong in law on the facts as he found them when he decided that although he was bound by the decision in George Parke v. The Fenton Gretton Partnership (which was a case admitted by the District Judge as being 'on all fours' with the present case) he would nevertheless exercise his discretion in the Respondent's favour.'
'1. A statutory demand should not be set aside on the grounds of a counter-claim, set-off or cross demand equalling or exceeding the amount of the debt specified in the statutory demand where the debt or debts in the statutory demand are based upon a judgement enforcing an adjudication award and bankruptcy proceedings are not being used in order to stifle a genuine counterclaim, set-off or cross demand.2. The Appeal Court is not bound by the decision in George Parke v. The Fenton Gretton Partnership.'
Relevant facts
'On 11 February 2008 the Referring Party accepted your repudiation of the contract.On 23 June 2008 the Referring Party submitted as its claim for damages arising from the Responding Party's breach of contract its assessment of the value of the works it had completed at the date of your repudiation of the contract in the sum of £189,134.69 and indicating that it was due a further payment of £86,730.24.
You have failed to respond to the Referring Party's assessment of the value of the works it has completed and have not made any payment in respect of the same. In the circumstances a dispute exists between the Referring Party and you as to the sums to be paid in respect of the work the Referring Party has undertaken at your instruction.
The Referring Party seeks an award of damages for your breach of contract and an adjudicator will be asked to determine what further sums if any are to be paid as damages to the Referring Party in respect of the works it carried out at the property and will be asked to make an award that:
1. That the Responding Party pay the Referring Party damages of £86,713.24 or such sum as the adjudicator shall decide being the unpaid value of the works, pleaded by the Referring Party at the date of the Responding Party's breach of contract.2. …'
The hearing of 30 June 2009 and the judgment of the District Judge
'30. It therefore seems to me that there is no real issue of bankruptcy of Mr and Mrs Shaw. There is no real issue of the right to pursue the arbitration being lost because of a supervening bankruptcy. It seems to me that this is simply a decision for Mr and Mrs Shaw as to whether they choose to pay the amounts due or not. To set aside the statutory demand simply to require the respondent to pursue enforcement by other means of a sum that (it is quite clear both from the facts of the case and all the authorities I have referred to) is undoubtedly due, is a step which, in my judgment, on the facts of this case [is] not one which the court should take. I do have a discretion. For those reasons, I exercise my discretion and decline to set aside the statutory demands.'
The first arbitral award & the subsequent conduct of the arbitration
Relevant principles applicable to this appeal
'Before the Court can interfere it must be shown that the Judge has either erred in principle in his approach or has left out of account or has taken into account some feature that he should, or should not, have considered, or that his decision was totally wrong because the court is forced to the conclusion that he has not balance the various factors fairly in the scale.'
The appellants' appeal
44. Subparagraph (a) provides that, if one of the conditions specified in the subparagraph is met, then the court may set aside the demand. I accept that the court retains a discretion not to do so even if one of the conditions is satisfied. But it seems to me that, if one of the conditions is satisfied, then the demand will usually be set aside. That is because it will usually be unjust to require the principal debtor to face the consequences of bankruptcy if he appears to have a counterclaim, set off or cross demand. There may be circumstances where the principal debtor's ability to pay is a relevant factor. But as Nicholls LJ said [in Re A Debtor [1989] 1 WLR 271, 276D], the theme running through rule 6.5(4) is that a statutory demand will be set aside where it is just to do so. In my judgement, it is difficult to see how it can be just not to set aside a demand where the principal debtor satisfies one of the conditions in subparagraph (a) merely because he can afford to pay the debt.
45. It has not been suggested (rightly in my view) that, even where the principal debtor appears to have a bona fide arguable counterclaim, set off or cross demand, an application to set aside a statutory demand under subparagraph (a) should be dismissed because he has the means to pay the debt that he owes to the creditor. Were the position to be otherwise, it could always be said of a principal debtor who has the means to pay the debt that he has the ability to avoid the consequences of a bankruptcy and that his application to set aside the statutory demand should be dismissed for that reason. Ability to pay would always be a trump card in the hands of the creditor in answer to such an application. I would add that, if ability to pay were fatal to an application to set aside a statutory demand, one would have expected that to be spelt out in the rules.'
'I would not rule out the possibility that ability to pay may be a relevant factor in certain circumstances. But for the reasons that I have given, I find it difficult to conceive of circumstances where ability to pay can be the sole or principal reason for refusing to set aside a statutory demand. No such circumstances have been identified in the present case.'
The respondent's cross-appeal
'11.5.1 Where the court is faced by an application to set aside a statutory demand issued in support of a judgement based upon an adjudication award it has a discretion as to whether or not to set aside that statutory demand. In exercising that discretion the court should give great weight to the policy of the 1996 Act, namely that adjudicator's awards are to be paid and execution of judgments based upon adjudicator's awards should not be delayed pending final determination of the dispute whether by litigation or arbitration. However, in exercising the discretion the court should be alive to the possibility that bankruptcy proceedings could be used to stifle genuine litigation to finally resolve the dispute provisionally determined by adjudication. Therefore, if the evidence suggests that bankruptcy proceedings are being used to prevent a party pursuing a genuine dispute the statutory demand should be set aside. If however the position is that the court has refused a stay of execution based upon the inability of the claimants to repay an award (as it has in this case) and, if it is clear that the debtor has the funds to pay the judgment sum (as is the case in this matter) then, the discretion should be exercised against the setting aside of the statutory demand.
11.5.2 A late issue of a statutory demand shortly before the final determination of the dispute by arbitration or litigation would also lead to the exercise of the discretion to set aside the demand on the grounds that it was being used oppressively.'
Discussion
The court may grant the application if –
(a) the debtor appears to have a counterclaim, set-off or cross demand which equals or exceeds the amount of the debt or debts specified in the statutory demand; or(b) the debt is disputed on grounds which appear to the court to be substantial; or(c) it appears that the creditor holds some security in respect of the debt claimed by the demand, and either Rule s6.1(5) is not complied with in respect of it, or the court is satisfied that the value of the security equals or exceeds the full amount of the debt; or(d) the court is satisfied, on other grounds, that the demand order to be set aside.'
'The authorities are illustrations of the well established practice of the Companies Court that, if a company has a genuine and serious cross claim, which is likely to exceed the petition debt, the court will normally exercise its discretion by dismissing the winding up petition and allowing the company the opportunity to establish its cross claim in ordinary civil proceedings. A company should not be prevented from raising a cross claim in winding up proceedings simply because it could have raised or litigated the claim before the presentation of the petition or it has delayed bringing proceedings on the cross claim. The failure to litigate the cross claim is not necessarily fatal to a genuine and serious cross claim defeating a winding up petition. However, in deciding whether it is satisfied that the cross claim is genuine and serious, the court is entitled to take into account all the relevant circumstances, such as the fact that a company has not even attempted to litigate the cross claim, or that there are reasons why it has not done so.'
15. The law in this area is clear and can be condensed into a few simple propositions:
(a) Absent a want of jurisdiction or a failure to comply with the rules of natural justice, the court will enforce the decision of an adjudicator. The position was summarised by Chadwick LJ in Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2005] EWCA Civ 1358 in these terms:
'85. the objective which underlines the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator …
86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points on which to present the challenge under the labels 'excess of jurisdiction' or 'breach of natural justice' … The task of the adjudicator is to find an interim solution which meets the needs of the case. Parliament may be taken to have recognised that, in the absence of an interim solution, the contractor or sub-contractor or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash flow requirements of contractors and their sub-contractors. The need to have a right answer has been subordinated to the need to have an answer quickly.
87. In short, in the overwhelming majority of cases the proper course of the party who is unsuccessful in an adjudication under this scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision is correct (whether on the facts or the law) he can take legal or arbitration proceedings in order to establish the true position …'
(b) The paying party can, as Chadwick LJ indicated, issue a claim form or an arbitration notice in order to obtain a substantive decision on the merits, and that may lead to some or all of the money, originally ordered to be paid by the adjudicator, being repaid to the paying party. But that does not affect the temporary finality of the adjudicator's decision, or the directive that that decision must be complied with and, if necessary, enforced by the court.
(c) The fact that the paying party has commenced substantive arbitration proceedings is usually irrelevant to the successful parties right to enforcement (and indeed execution) of any judgment: see Harlow and Milner v. Teasdale (No 2) [2006] EWHC 535 (TCC).
(d) The only authority of which I am aware in which the existence of ongoing arbitration proceedings affected the mechanics of enforcement is my decision in Kier Regional Ltd v City & General (Holborn) Ltd [2008] EWHC 2454 (TCC). But that was a case where the enforcement of an adjudicator's decision had in fact been ordered by the court in 2006. The difficulty was that the claimants had done nothing to execute that judgement and only sought charging orders and the like at a time when the substantive arbitration was only a few weeks away. In those wholly exceptional circumstances I granted a stay of execution.'
'In my judgment it cannot be right that an employer or main contractor can be made bankrupt when it is known that he has proper proceedings on foot which, if successful, will result in a payment to him. I do not accept that the scheme of the 1996 Act is that an adjudication can be pursued to bankruptcy no matter the underlying state of account. The court would be required to close its eyes to the overall position, which in the context of bankruptcy is in my judgment wrong in principle.'
Exercise of the discretion
'Where the statutory demand is based on a judgment or order, the court will not at this stage go behind the judgment or order and enquire into the validity of the debt nor, as a general rule, will it adjourn the application to await the result of an application to set aside the judgment or order.'
Impact of the first arbitral award