CHANCERY DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AKZO NOBEL UK LIMITED |
Claimant |
|
- and - |
||
ARISTA TUBES LIMITED |
Defendant |
____________________
Jonathan Gaunt QC (instructed by Geldards LLP) for the Defendant
Hearing dates: 11 March 2009
____________________
Crown Copyright ©
Mr Justice Floyd :
Introduction
"The Seller and the Purchaser shall use all reasonable endeavours to procure the obtaining of the Property Consents as soon as reasonably practicable after the Completion Date…"
"If by the date of 12 months after the date hereof all Property Consents shall not have been obtained in respect of the Business Property then either the Seller or the Purchaser may, by 3 months' notice in writing to the other terminate on the date of expiry of that notice, the obligations of the parties thereto in respect of the Business Property, under this Schedule 7 (Properties) (but without prejudice to any antecedent breach) in which event the Purchaser shall vacate the Business Property by the end of such notice period."
"Those Agreements require us to give three months' notice to terminate and we accordingly therefore give notice to terminate our Licence Agreement on 31st January 2008, when all five units will be vacated."
"4 business days after … reasonable evidence is provided to the Purchaser's Solicitors that the Property Consent has been obtained"
"Our client has passed to us a copy of the letter … dated 30 October 2007, but not received by our client until 1 November 2007. We do not accept the validity of that letter as good notice to terminate your company's obligations in relation to these properties under the [BPA]."
"Having considered the [BPA] and, in particular, paragraph 11 of Part B Schedule [8], we can see no reason for which our client's Notice of 30th October should not be regarded as valid and accordingly therefore our client will not be proceeding to completion of the Underleases."
The rival arguments
Discussion