CHANCERY DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
GLENMERE PLC |
Claimant |
|
- and - |
||
F. STOKES & SONS LIMITED |
Defendant |
____________________
Mr Wayne Clark (instructed by Memery Crystal LLP) for the Claimant
Mr Benedict Sefi (instructed by Close Goff Humphreys) for the Defendant
Hearing date : 14-16 January 2008
____________________
Crown Copyright ©
Mr Stuart Isaacs QC:
Introduction
The Project Coordination Agreement
"Building: an office building consisting of not less than 12,000 square feet of net lettable floor area …."
"Building Contractor: such reputable contractor as may be appointed by the Developer"
"Development: the construction of the Building on part of the Property by the carrying out of the Works pursuant to the Planning Permission"
"Office Site: the part of the Property shown edged in red on the plan annexed hereto subject to such adjustment of the boundaries as may be required to comply with the requirements of the Planning Permission"
"Planning Permission: planning permission for the construction of the Building on the Office Site and a residential development consisting of not less than 16,000 square feet of gross internal floor area and not less than 24 units on the Residential Site"
"Property: the freehold property known as Heatherside House, Park Street, Camberley, Surrey and registered at HM Land Registry with title absolute under title numbers SY432900 and SY609313"
"Residential Site: the part of the Property shown edged in blue on the Plan annexed hereto subject to such adjustment of the boundaries as may be required to comply with the requirements of the Planning Permission"
"Works: the works described in the Building Contract and the Planning Permission for the construction of the Building".
The Issues
(a) Are various conditions attached to the planning permission dated 27 September 2005 "Requisite Consents" as defined in clause 1.1 of the PCA?
(b) If so, is the fulfilment of the planning conditions "necessary for the commencement of the construction of the Development" within the meaning of clause 6.5 of the PCA?
(a) Is the requirement to obtain the approval of Network Rail (as successor to the British Railways Board) to plans for the carrying out of works under a restrictive covenant contained in a conveyance dated 31 December 1970 between the Board and Frimley and Camberley UDC as purchaser a "Requisite Consent" as defined in clause 1.1 of the PCA?
(b) If so, is the obtaining of it "necessary for the commencement of the construction of the Development" within the meaning of clause 6.5 of the PCA?
Issue 1: Planning conditions
Issue 1(a): Are the various conditions attached to the planning permission dated 27 September 2005 "Requisite Consents" as defined in clause 1.1 of the PCA?
" planning permission, building regulation consents, by-law approvals, and other consents, licences and authorisations required from any competent authority, statutory undertaker, or person either for the carrying out of the Development or its intended use."
" As I understand the effect of the authorities to which I am about to refer, it is only necessary to ask a single question: are the operations (in other situations the question would refer to the development) permitted by the planning permission read together with its conditions? The permission is controlled by and subject to the conditions. If the operations contravene the conditions they cannot be properly described as commencing the development authorised by the permission. If they do not comply with the permission they constitute a breach of planning control and for planning purposes will be unauthorised and thus unlawful. This is the principle which has now been clearly established by the authorities."
" The Developer will use all reasonable endeavours pursuant to its obligation under clause 14 of this Agreement to procure that the Development is carried out:
…(b) in accordance with this agreement, the Planning Permission and the Requisite Consents;(c) in accordance with all statutory or other legal requirements and the recommendations or requirements of the local authority or statutory undertakings;…"
(1) it would render the satisfaction of clause 2.1 of the PCA nugatory;
(2) the two year period given to the Developer under clause 2 to obtain a planning permission satisfactory to him would effectively be truncated since he would, within that period, have not only to obtain the grant of planning permission but would also have to satisfy the planning conditions; and there is nothing to stop the Developer making successive planning applications;
(3) it would mean that the Professional Team contemplated by clause 5.2 of the PCA had to be appointed only after their fulfilment, despite the fact that the appointment of the Professional Team was necessary in order for those conditions to be fulfilled;
(4) similarly, the building contract provided for in clause 4.2 could not be entered into until after their fulfilment;
(5) substantial work would have been undertaken which would not be covered by the Collateral Warranty in the Defendant's favour which the Developer was required to procure under clause 5.3 of the PCA – a matter of some importance in the event that the Developer were to become insolvent;
(6) if a condition related to both the Residential Site and the Development, all aspects of it would have to be satisfied in order to avoid rescission under clause 6.5.
Conclusion
Issue1(b): Is the fulfilment of the planning conditions "necessary for the commencement of the construction of the Development" within the meaning of clause 6.5 of the PCA?
" If all Requisite Consents necessary for the commencement of the construction of the Development have not been obtained by two years from the date of this Agreement or such longer period as may be provided for by Recital (D) of this Agreement, then either party may rescind the Agreement by service of notice in writing to that effect upon the other whereupon this Agreement will cease and determine but without prejudice to the rights of any party in relation to any antecedent claim or breach of covenant."
(It is common ground that the reference to recital (D) is erroneous and should refer to clause 2.3 of the PCA).
Conclusion
Issue 2 : Network Rail approval
" FOR the benefit and protection of such part of the adjoining or neighbouring property of the Board as is capable of being benefited or protected and with intent to bind so far as legally may be itself and its successors in title owners for the time being of the property or any part thereof in whosesoever hands the same may come the Purchase covenants with the Board as follows:-
(1) Not at any time -
(a) without previously submitting detailed plans and sections thereof to the Board and obtaining their approval thereto and
(b) without complying with such reasonable conditions as to foundations or otherwise as the Board shall deem it necessary to impose
to erect or add to any building or structure or to execute any works on any part of the property adjacent to the railway of the Board."
Issue 2(a): Is the requirement to obtain the approval of Network Rail to plans for the carrying out of works under the restrictive covenant a "Requisite Consent" as defined in clause 1.1 of the PCA?
" If any third party has the benefit of any easement, covenant, right or interest in or over the Property that may:
(a) prevent or hinder the progress of the Development, or(b) adversely affect the use or enjoyment of the Property as contemplated by the terms of the Planning Permission,then the Developer will negotiate with the third party for its release. The Owner at the cost of the Developer will enter into any requisite deed or agreement with the relevant third party subject to the Owner approving its terms such approval not to be unreasonably withheld or delayed."
" If it is desirable or necessary to obtain the grant of any easement or right for the benefit of the Property from any third party:
(a) for the carrying out of the Development, or(b) for the use or enjoyment of the Property as contemplated by the terms of the Planning Permission,the Developer will negotiate with the third party for its grant. The Owner will at the cost of the Developer enter into any requisite deed or agreement with the relevant third party subject to the Owner approving its terms such approval not to be unreasonably withheld or delayed."
Conclusion
Issue 2(b): Is the obtaining of Network Rail's approval "necessary for the commencement of the construction of the Development" within the meaning of clause 6.5 of the PCA?
Conclusion
Conclusion