KING'S BENCH DIVISION
PLANNING COURT
SITTING IN LEEDS
B e f o r e :
____________________
(1) LIONEL WATERHOUSE (2) PATRICIA WATERHOUSE |
Appellants |
|
- and - |
||
(1) SECRETARY OF STATE FOR HOUSING, COMMUNITIES AND LOCAL GOVERNMENT (2) NORTHUMBERLAND COUNTY COUNCIL |
Respondents |
____________________
Riccardo Calzavara (instructed by GLD) for the First Respondent
Piers Riley-Smith (instructed by Northumberland CC) for the Second Respondent
Hearing date: 17.10.24
____________________
Crown Copyright ©
FORDHAM J:
Introduction
The Need for Evidence
The 2017 Photo
The "To Whom It May Concern" Emails
The Inspector's Decision
Unfairness
Unlawfulness
Unreasonableness
Reasons
Extension of Time
Please note the Planning Inspectorate is not the administering body for High Court challenges. If you would like more information on the strictly enforced deadlines for challenging, or a copy of the forms for lodging a challenge, please contact the Administrative Court on 020 7947 6655.
Costs
[Later]
Order
17.10.24