KING'S BENCH DIVISION
ADMINISTRATIVE COURT
BIRMINGHAM DISTRICT REGISTRY
Priory Courts, 33 Bull Street, Birmingham, B4 6DS |
||
B e f o r e :
____________________
THE KING On the application of BIRMINGHAM CITY COUNCIL |
Claimant |
|
- and – |
||
SECRETARY OF STATE FOR TRANSPORT |
Defendant |
____________________
SARAH HANNAFORD KC, EWAN WEST KC and WILL PERRY (instructed by Government Legal Department) for the Defendant
Hearing dates: 21st and 22nd March 2024
____________________
Crown Copyright ©
Mr Justice Mould :
The subject matter of these proceedings
"I am writing to inform you that the Government has now made a decision on the Outline Business Case setting out Birmingham City Council's proposals for the revised Highway Maintenance PFI arrangement (the "Project"). I recognise the delay in reaching this decision has been challenging and am grateful for your patience while the Government considers this important decision. The Government has decided not to support the revised deal outlined in the Outline Business Case.
The revised deal cannot be recorded "off balance sheet" in accordance with the relevant ESA 10 accounting rules because: (i) the proportion of capital work to be undertaken relative to the value of the asset on completion of the Project is insufficient; and (ii) there is insufficient risk transfer to the private sector. The revised deal would therefore need to be accounted for as "on balance sheet", which requires an up-front CDEL charge in the region of £200m to £250m. The Government has therefore rejected the Outline Business Case on the basis that this cost is unaffordable.
In rejecting the revised deal, the Government is instead proposing to maintain provision of Highways Maintenance funding for BCC at the current level (£50m p.a.) until the end of the current Spending Review period (2024/25). This is expected to be delivered through an uplift to the West Midland Combined Authority (WMCA) CRSTS settlement.
I appreciate this decision will be disappointing and I want to reassure you of the Government's commitment to supporting authorities to fulfil this critical function in the best way it can. My officials stand ready to work with your team and WMCA to ensure a smooth transition to the new arrangements, and the continuity of Highways Maintenance in Birmingham".
The grounds of challenge in summary
Factual background
PFI Agreements
"A Private Finance Initiative (PFI) is a long-term contract between a private party and a government entity where the private sector designs, builds, finances and operates a public asset and related services. In a PFI contract the private party bears the risks associated with construction and maintenance and management responsibility, and remuneration is linked to performance.
….
PFIs transfer delivery, cost and performance risk to the private sector – this protects the public sector from delays, cost overruns and poor performance".
The Project Agreement
The Local Government PFI Project Support Guide (2009-10)
"Notification that grant will be paid, the conditions and the level of capital investment which will be supported are set out by issuing a "PFI credit" in the form of a letter from the sponsoring department".
"This guide provides advice to those local authorities seeking central government support for PFI or LIFT projects. Those authorities who wish to formally submit a grant claim should consult the Local Authority PFI Annuity Grant Determination (No 1) 2009 [No 31/1352]….".
"More detailed guidance on possible re-assessment of support resulting from termination or major variations".
"…each letter will be tailored to meet the specific needs of each sector and project….This letter will include standard and specific conditions, and set the endorsement date which is used to determine a number of rates used in grant and PFI credit calculations. Some conditions may need to be met before the project is taken to the market. A project with such conditions is nonetheless considered endorsed at the date of the relevant PRG meeting".
"Promissory note. A promissory note does not need to be sent at any particular stage if the authority does not require it, but may be requested to provide assurances about the continued support in principle of the department if that is requested/needed. If that is requested prior to the [Full Business Case (FBC)] being agreed a template for use is at Section B2. More usually the promissory note is requested shortly before contract signature and the FBC will have been approved – a template for use in these circumstances is at Section B3 (note that the comments about the endorsement template at para. 2.2 also apply to these letters).
"PFI credit letter. The authority should send written notification of the date financial close is reached. A PFI credit letter (template at Section B4 – note that the comments about the endorsement template at para. 2.2 above also apply to this letter) will always be sent by the sponsoring department when the project reaches financial close. This letter is the formal date at which a PFI credit is issued, and is the record of all factors used in calculating PFI grant".
"Major post contract signature variations. Any major variation which is being considered must be reported to the sponsoring department before it is agreed, including any contract extension (whether PFI credit is being sought for that extension or not). Where there is a change protocol which defines major variations that should be used. Where that does not exist, there is no simple definition of whether any variation is major or not. However, the standard change protocols can be used as a guide, and if in doubt the sponsoring department should be consulted. A department may wish to look at the [Value for Money (VfM)] or legal aspects of any such variation.
The possible impact of such changes on the level of support is covered in Section G".
Section G of the Guide: Post Contract Signature Changes
"Changes to the contract, including possibly termination, may occur after it has reached financial close and the PFI credit has been issued. Any major variation must be reported to the sponsoring department who will consider whether there are PFI support implications".
"If a sponsoring department wishes to support such an increase, it will be treated for grant purposes as if it were a separate contract. The PFI credit calculation will use the discount rate in force when the variation is agreed, not that used for the original project, and a separate PFI credit letter will be issued. The same approach will be used in the grant calculation, i.e. the interest rate and scaling factor used will be those in force when the variation is agreed".
"Exceptional circumstances. Government reserves the right to stop support in exceptional circumstances. Such circumstances could be where continuation of support would unduly enrich or reward an authority, for example where a contract was terminated by the authority despite that approach not being the best value for money. As a first step, sponsoring departments will therefore consider the circumstances of any major variation in this light.
Even in such exceptional cases, steps would be taken to ensure that the local authority was not thereby prevented from meeting in full the resulting liabilities to the PFI contractor and its funders for capital assets already delivered".
"(2.2) Reductions in assets delivered. Termination or variation of the contract (including as a result of planning permission difficulties) could result in a reduction in PFI credits and therefore grant. If substantially all of the assets have been delivered there will not be any change to the PFI credits or grant. However, if the change results in significantly reduced capital investment by the contractor, it will lead to a reduction in support.
The interpretation of whether a reduction is significant or not is a matter for the sponsoring department, and should always be considered on a scheme-by-scheme basis after taking into account all the relevant circumstances. Where there is one or a limited number of large assets, it will be easier to reach a decision since the non-delivery of any would clearly be a significant change. Where there are a larger number of smaller assets involved, a decision will be more subjective, but a department needs to decide whether substantially all of the planned assets have been delivered or not.
(2.3) Changes in assets delivered. In some cases the nature of the assets may change, e.g. a change in the number or location, but the overall capital value remain about the same. In such circumstances an authority should notify the sponsoring department who will consider whether the alternative proposals are acceptable to them. If they are, support will continue without interruption.
….
(2.8) Changes to services or financing costs. A variation may be agreed which reduces the local authority's costs because of changes in the service element or financing costs. Neither of these would result in any reduction in support. It is established policy that in the case of refinancing the benefits will be shared between the contractor and the local authority, and not by central government".
The PFI Credits in this case
"This is to confirm that we have now received Project Review Group (PRG) approval for the Birmingham Highways Maintenance PFI Project. This follows the final version of the Final Business Case for the project which your Authority submitted to this Department on 23 November 2009 and the addendum submitted on 10 February 2010.
This note confirms that if the transaction is entered into on the terms set out in that Business Case this Department will issue your authority with a PFI credit letter for an estimated £637 million. This amount is based on your own assumption of a 4.70% swap rate. The final amount will be determined at financial close based on the actual swap rate achieved up to a maximum of £650 million. We expect a transparent process to close with the actual amount of credits necessary re-confirmed after contract signature and this amount will form the basis of the PFI credit letter.
We also expect the Authority to supply the Department with a full set of documentation and a financial model after close and subsequently to help with lessons learnt and to give reasonable support to other authorities for the benefit of the ongoing highway maintenance PFI programme.
You should continue to seek prior approval if, between now and contract signature, different terms are negotiated which affect either the nature of the scheme or the potential amount of the PFI credit, or if those terms differ from those in the relevant PFI standardisation documents. Any departure from these terms could affect your authority's entitlement to PFI credits, and will in any case risk delay to the project if PRG decides to have the proposed departures reviewed. Should we wish to support the revised project we would issue a further letter".
"In addition to the Promissory Note, there are a number of other conditions for your Authority with regards to the scheme which we wish to receive confirmation that your Authority accepts before financial close and which will also feature in the Department's final PFI credit letter".
The Covering Letter then set out certain specific and general conditions with which DfT expected the Claimant to adhere, including reserving Ministers' right to reconsider their decision on the funding if there are any significant changes to the project.
"I trust that this letter provides appropriate confirmation and commentary upon the issues identified within your Covering Letter and that we can move towards the issue of the Final PFI Credit letter, which in turn would allow the Authority to make the necessary grant claim. As identified above the contract with Amey commenced on the 7th June 2010 and the first payment under the contract took place on Friday 25th June 2010".
"We have now received confirmation that financial close was reached on the above transaction on 6 May 2010 and that the contract was agreed on the terms set out in your Final Business Case (FBC). This Department is therefore now formally issuing PFI credits for the project for an amount of £625,214, 302.
You should publish your FBC (barring any sensitive information) on your website as soon as possible.
Revenue support will be paid once a valid claim form has been received, as set out in the Local Government PFI Annuity Grant Determination for the financial year in which grant is first claimed. The interest rate which will be applied in calculating grant for your project will be 6.3%, and the scaling factor 1. Your authority will need to ensure that funds are available to cover that part of the payments to the contractor which will not be met by central Government…..
Revenue support is not intended to match or correlate directly to the payments that arise under a PFI contract. However, the Government is committed to supporting good PFI projects and to assisting the development of PFI in the local authority sector. Its policy therefore to maintain revenue for PFI projects in the long term, consistent with the long-term nature of PFI contracts, even though formally such support cannot be guaranteed.
Termination or variation of a PFI contract could in some circumstances (as set out in the Local Government PFI Project Support Guide) lead the Government to reassess the level of revenue support based on the extent to which the anticipated capital investment is delivered. Any plans for a major variation (including extension) to the contract must therefore be reported to this Department before it is agreed".
Accounting Rules
"This letter seeks your agreement to an increase in the PFI credits to the Birmingham Highway Maintenance PFI from £608m to £637m (with provision to increase this to a maximum of £650m), as the scheme exceeds the Department's spending delegation. This increase is within the Departmental PFI credit allocation budget. My officials have undertaken a value for money assessment at the higher cost and I can confirm the scheme falls into the medium/high value for money category.
…
As part of the Final Business Case the authority provided an opinion (ESA95) from the financial advisers to the project that the project is considered to be off the Department's Balance Sheet. We are seeking confirmation from your officials that the project will be deemed to be off the Department's Balance Sheet. You will appreciate that the project could not proceed if there was any doubt on this matter, since it is completely outside our budget planning".
"I also understand that discussions are ongoing with the ONS concerning the classification of the scheme for balance sheet purposes. In line with the advice given on 13 December 2007 (attached), we will ensure that Departments are no better, and no worse off, following the accounting changes. Therefore, if the scheme is deemed to be on balance sheet, your Department's budget will be increased as necessary to reflect this new pressure".
"For a project involving the refurbishment, renovation or upgrade of an existing asset to be considered a PPP, the amount of capital expenditure by the Partner under the contract must represent at least 50% of the value of the asset after completion of the works….If the Partner's capital expenditure does not meet the 50% threshold, the project is not considered to be a PPP and it will be on balance sheet for government".
"I should make clear that this outcome follows from the Capex Threshold irrespective of any assessment of the balance of allocation of risk effected by the Project Agreement. If the Capex Threshold is not satisfied then the Project could not be considered a PPP and the project would be required to be accounted for by DfT "on balance sheet" irrespective of the risk allocation that is given effect by the terms of the Project Agreement".
The Amey Settlement
"1.2 This report provides an update regarding discussions to reach a commercial settlement with Amey Birmingham Highways Limited in relation to a number of matters within the Highway Maintenance and Management PFI contract and bring to an end legal action undertaken.
…
5.7 Under the conditions of the PFI grant the Council is required to report any proposed major variation to the contract to DfT for prior approval, in their capacity as the sponsoring government department. The changes proposed constitute a major variation and DfT require a full business case, which, if supported, will then be submitted for consideration at the HM Treasury Board Investment Commercial Committee (BICC). In addition the Council is advised that the proposal may require ministerial approval.
5.8 The review by government will involve two key elements:
5.8.1 Consideration of the funding for the project against the original outcomes, to ensure that the proposed outcomes remain comparable with those when the PFI grant was originally awarded. For example, if there were to be a significant reduction in the capital investment made under the project (which is not being proposed), this could result in the grant being reduced.
5.8.2 Consideration of the impact on the accounting treatment within the Whole of Government Accounts, to ascertain whether the proposed changes result in the recognition of a liability on the public sector Balance Sheet or not. This will require an assessment of each of the proposed changes to the contract against the existing accounting requirements. It should be noted that the existing requirements have been updated since the original assessment at contract commencement".
The Department's May 2019 Letter
"The Department has been closely involved with the Birmingham City Council PFI as the options have developed, and supports the idea of a consensual exit for Amey that you and the partners to the PFI, including Amey, have been working to deliver. We are keen to see this result in a sufficiently funded and feasible project for Birmingham City Council, and we stand by the terms of our existing PFI agreement.
We support the two-stage approach that has now been agreed and which will involve further discussions between the Council, the lenders, the SPV, and the equity investors over the next 24 months. We recognise that this may result in an interim provider followed by a procurement exercise to secure a new sub-contractor to cover the remaining 15 years of the agreement.
The Department's view is that the Council, through its local accountability to members and residents, will not wish to accept wholesale changes to the contract that would result in poorer quality specifications or services. It is in all our interests to minimise substantive changes to the project agreement, although some change may be needed in order to secure a satisfactory replacement sub-contractor.
We believe that the Council should also review the contract management arrangements to make the project sufficiently attractive to bidders, and deal with any misconceptions in the market. If this is not done then it is likely that bidders will add a substantial risk premium, which the project may not be able to afford. The Department will need to see a substantive piece on the overall management case, including contract management arrangements, with BCC working with the SPV and involving some external challenge. We would be grateful for your early thoughts on how this might be done.
Our intention is to continue paying PFI grant at the current rate, subject to value for money. We understand that the Council may also be considering changes to the contract, and it is of course at liberty to submit other proposals for support from new and existing funding streams from Government. DfT will consider such changes on their merits, provided always that the business case demonstrates continued value for money.
This will be greatly assisted by close and open working between the Council and DfT officials, and by putting in place suitable governance arrangements to oversee the second stage, as described earlier. But we must emphasise that the principals here are the SPV and BCC. The parties should avoid a sequential approach, in which the SPV propose changes in the light of market soundings, BCC review and agree them, and then at the end come to DfT for review. With that in mind I would be grateful if you could continue to liaise closely with Tony Boucher and Mohammed Aziz in the Department for Transport.
The renegotiation phase in coming months will be difficult, and I can confirm that the Infrastructure and Projects Authority will continue to support the project, for example by drawing on past experience and/or facilitating discussions with existing investors, and potentially with new ones (both debt and equity)".
Updating the business case 2021/2023
"1.1.6 Following analysis, all Project stakeholders concur that the original outcomes from the Project are not now achievable, so the Authority has given consideration to delivering the optimum level of investment within the available resources.
1.1.7 This business case sets out the scenarios currently under consideration by the Authority, and reports on the analysis undertaken to date.
1.1.8 By submission of this business case, the Authority seeks approval from Government to proceed with the recommended approach, as described in this business case and recognising (i) the ongoing negotiations with stakeholders; and (ii) the planned market engagement and procurement exercises. The Authority also seeks confirmation from Government that the PFI credits / grant will continue to apply for the remainder of the Project term.
…
Solution
1.2.14 In further of its public law duties and in pursuit of best value, the Authority has therefore explored an alternative approach that could deliver the same or better asset condition outputs in a more efficient and flexible manner. A key consideration is whether market risk pricing and other overheads could be actively managed in a more effective way to achieve the best value for money possible with the available finding.
1.2.15 The Authority therefore has three potential scenarios -
Scenario 1: the default scenario in which no agreement is reached with Senior Creditors prior to the expiry of the Restructuring Period, such that the Project Agreement terminates;
Scenario 2: reduction in Project standards to a level allowing BHL to procure a long-term Replacement Subcontractor; and
Scenario 3: the Authority's alternative approach, which would see BHL acquired by the Authority, implementation of active management by BHL and procurement of a suite of subcontracts intended to optimise project delivery".
"Our previous letter…dated 16 May 2019, set out the Department's expectations for the future contract. In that response, the Department committed to consider carefully any proposed changes to the contract to ensure they aligned with these expectations, including that any substantive changes to the project specification should be minimised, undertaking a review to the contract management arrangements to make the project commercially attractive, and that the business case demonstrated the proposals offered value for money.
Following your submission of a business case in March 2021 along with additional supporting documents, the Department has now considered the two proposals you have put forward, each of which the Department understands you to consider offers a feasible alternative solution for the contract. We have concluded, following scrutiny of the material you submitted through Departmental governance processes, that we cannot support the Council's preferred proposal, put forward as Scenario 3….
Although the Department cannot support your preferred proposed approach for the reasons given above, the Department remains content to continue paying the PFI credits if a workable proposal can be identified and can be delivered quickly, which meets our ongoing requirements and addresses the concerns set out above. It should align much more closely with the original policy aims of the project and provide clear evidence and assurance of a robust approach that offers value for money, does not expose HMG to additional financial costs, and is both deliverable and commercially viable".
"As discussed this morning … can you/DfT please respond to the following additional queries:
- Recognising that neither BHL nor BCC can undertake the national balance sheet classification analysis for DfT/Treasury, can DfT confirm what specific information is required from BHL/BCC to assist DfT/Treasury in undertaking the analysis?
- In addition, can DfT confirm how national balance sheet assessment/classification will impact decision making at each business case stage, e.g. at what point will DfT approach ONS for a formal assessment of the contract's classification?
- Also, is an 'off balance sheet' classification a 'red line' requirement for DfT to approve Option 2?"
"Balance sheet classification is one of the considerations likely to be assessed when the business case is evaluated as a whole. It is likely to be considered at each stage of review – SOBC and OBC level as well as the full business case".
"1.1.2 As part of its preparation, BCC and BHL have been cognisant of the unique circumstances presented by this Project and have sought to address the main areas of concern set out in the DfT Letter to BCC dated 14 June 2021. Appendix 1 sets out where each specific requirement of the DfT Letter has been considered within the SOBC.
…
1.2.4 This option, referred to as Scenario 2, would secure a scale of investment in highways infrastructure and support a long term proactive investment strategy which would significantly contribute towards achieving BCC's original Project objectives, arrest the current deterioration in the network condition, facilitate economic growth and deliver demonstrable value for money. It is aligned to BCC's current strategic outcomes and also supports the DfT's priority outcomes as set by the most recent Government Spending Review.
1.2.5 This proposed solution has been tested against the counterfactual, referred to as Scenario 1. This Scenario would see the PFI contract terminated and future funding of BCC's highway network be subject to short term local highways maintenance funding allocations. Under such an outcome, BCC would only be capable of delivering the minimum requirements to fulfil its statutory obligations in respect to maintaining safety and usability of the highways and there would be very limited scope to enhance the highways network via capital investment".
"1.4.4 The case goes on to consider the accounting classification implications of Scenario 2, from the perspective of both BCC and the National Accounts. It outlines that the changes to the contract anticipated as part of the re-procurement of a new subcontractor may trigger a National Accounts classification review, with the Project's balance sheet treatment being reassessed under the current ESA 2010 rules.
1.4.5 It explains that BCC and BHL intend to seek reassurances from DfT that should this result in an 'on balance sheet' classification in the National Accounts, this is not considered to be an insurmountable obstacle to receive approval to continue the PFI project and proceed with the subcontractor re-procurement exercise.
…
4.9.14 We understand that DfT will undertake its own assessment of the statistical treatment impact of the proposals under Scenario 2 based on the information that is made available as part of this SOBC. Given the possibility that the Project would no longer meet the requirements to remain off government balance sheet under ESA 2010 rules, BCC and BHL intend to seek reassurances from DfT that this is not considered to be an insurmountable obstacle before commencing the development of the OBC".
"5.12.1 Should Scenario 2 not be pursued, BCC would revert to Scenario 1. As outlined in the Economic Case it is assumed that PFI Credits would be withdrawn and replaced by capital block funding. This would create a significant level of funding uncertainty in the medium to long term which would directly affect the ability of BCC to adopt a long-term asset management approach to the re-procurement of highway network investment".
"The next stage is for BCC, working with Birmingham Highways Ltd (BHL), to submit an Outline Business Case (OBC) and final procurement documents by 6 December 2021 which demonstrate that BCC has developed a credible proposition that will be acceptable to the market and which meets DfT requirements, including Value for Money for the PFI project in its remaining years. As the team have discussed with you, to be approved the OBC will need to meet the following requirements agreed by IPDC and Ministers…".
One of those requirements was that the Claimant should continue to address the balance sheet and accounting treatment questions and work with DfT and Treasury ["HMT"] to agree a final position.
"Through the Steering Group we have discussed the requirement to submit "final procurement documents" along with the Outline Business Case (OBC) on 6 December 2021 and have sought further clarification of what this means in practice. Specifically the following points have been accepted, noting that …. you will need to understand the risk transfer and pricing as part of the Economic Case…
…
We will continue to support DfT in its consideration of the balance sheet treatment questions, but you will appreciate that this is ultimately for DfT and HM Treasury to confirm. We will be grateful if this can be progressed as a matter of urgency."
"This framework establishes the requirements BCC must meet in order for DfT to continue paying PFI credits. It sets out the withdrawal process if BCC fail to meet these requirements. The document will be kept under regular review and revised where necessary".
This framework document appears not to have been discussed and was never signed by either DfT or the Claimant. Mr Shelswell says that the Claimant's position was that the PFI Credits continued to be governed by the terms on which they had been issued in 2010.
"3.6.10 Under Scenario 2, agreement is reached by BCC, BHL, DfT and Senior Creditors on the scope and terms of the revised Project Agreement and the future investment in highways infrastructure will be secured.
3.6.11 The PFI structure will remain in place and BHL will procure a Replacement Subcontractor. This will support a long-term proactive investment strategy that will significantly contribute towards BCC's Project objectives, arrest the current deterioration in the network condition, secure the legacy network condition and deliver demonstrable value for money.
3.6.12 The anticipated risk allocation is set out in more detail in the Commercial Case, but in summary is represented below. Those items marked in red represent areas where there has been an increased transfer of risk back to BCC relative to the existing contract".
Table 6 of the OBC showed certain assets for which the Claimant would take back risk (either on a sole or shared basis) under the proposed arrangements for Scenario 2. Paragraphs 3.6.13 to 3.6.21 briefly explained the position.
"1.2.5 …Scenario 2 … is aligned to BCC's current strategic outcomes and supports the DfT's priority outcomes as set by the most recent Government Spending Review.
1.2.6 This proposed solution has been tested against the counterfactual, referred to as Scenario 1. This Scenario would see the PFI contract terminated, and future capital funding of BCC's highway network be subject to short term local highways maintenance funding allocations. Under such an outcome, BCC would only be capable of delivering the minimum requirements to fulfil its statutory obligations in respect of maintaining safety and usability of the highways and there would be very limited scope to enhance the highways network via capital investment".
"HMT stated that DfT should be no better or no worse off following any classification changes (in reference to the letters exchanged between HMT and DfT in 2010).
The classification change….would be prospective, so it would apply from the date the new Contract is let.
DfT will need to manage the budget arising from the project coming on-balance, almost certain to do when a new Contract is let.
HMT confirmed it would be one hit on Capital Departmental Expenditure Limits ["CDEL"] in one financial year. This is because National Accounts treat it as the purchase of an asset, calculated as the present value of the future PFI grant payments. It is not retrospective, so grant payments already made are not taken into account in the calculation".
"4. …The OBC continues to present BCC's preferred option of a project restructuring that maintains the PFI structure and full credit allocation but with a new subcontractor procured to deliver the highways services set out in a modified contract – in comparison to the counterfactual.
5. On 24 January, IPDC considered the OBC and the three options DfT could take: allowing BCC to straightforwardly continue to FBC; withdrawing support now; or allowing BCC to continue on the route to FBC but with additional checkpoints and requirements.
6. IPDC agreed that the project was too high risk to proceed straight to FBC but also noted that at this stage there are no material breaches of our requirements, instead many uncrystallised risks that BCC will not meet those requirements. Therefore, there are several risks associated with withdrawing support now …
7. On balance, IPDC agreed to support the option recommended by the policy team – allow BCC to continue on the route to [Final Business Case], but with additional checkpoints and robust requirements – including a specific requirement on the Department's role in assessing VfM and strategic priorities … The Board agreed that this option strikes the right balance between giving BCC the chance to secure arrangements that will give longer term and higher levels of investment into Birmingham's roads and minimise risk to taxpayer interests if the project does not proceed…
8. Allowing BCC to continue does not mean that we are committed to funding this project, we can still choose to withdraw support at a later checkpoint if BCC fail to meet our requirements. One of our requirements is for BCC to work with us and the West Midlands Combined Authority (WMCA) to agree contingency plans, which will make the transition much smoother if we do eventually withdraw PFI funding.
…
12. HMT officials have advised that, given the fiscal impacts of the options, HMT Ministers will also need to agree to the above recommendations".
"However, given the risks that remain with the project the Department requests an additional checkpoint to review an updated OBC in line with the requirements detailed in the annex to this letter.
I appreciate the hard work from all parties that has gone into the OBC and recognise that you have come a long way in delivering a revised contract that you can take to market. We are committed to working in collaboration with you and I know that the team has already sought both BCC's and BHL's view on the content of this letter.
I can confirm that a formal checkpoint will take place later this year, following the second round of dialogue with bidders. BCC will be required to complete a formal submission with an updated OBC that demonstrates progress against the requirements below. The deadline for this submission is Monday 12 September 2022, to be considered at committee shortly thereafter. IPDC will review this submission before making recommendation to DfT Ministers and I hope it will prove sufficient to assuage the board of any concerns ahead of the FBC. In addition, HM Treasury (HMT) will review your submission. While we do not expect you to pause re-procurement while you wait for IPDC and HMT's views, if the submission fails to provide adequate assurance that you are meeting our requirements, then DfT may withdraw support at this stage. The continuation of PFI grant funding is not guaranteed".
"I emphasise again that the council's primary aim is to achieve a successful project restructuring and business case approval to continue the PFI until 2035. However, as Highway Authority we also require robust contingency arrangements to deliver our statutory responsibilities should it not be possible to do so via the PFI structure.
Since your 31 March 2022 letter the council has worked with your officers to ensure that they understand the implications of the project's 2019 restructuring agreement ending. We have explained that there are a number of triggers that could set in chain a sequence of events that lead to the Restructuring Agreement, Project Agreement and PFI grant being sequentially terminated. While there are a number of potential routes, the most likely event to cause this to happen is Government (whether the Department or HM Treasury) not approving the council's business case at any point".
"Thank you for your letter to Stephen Fidler of 8 July, and our subsequent discussion, regarding post-PFI funding should the Outline Business Case (OBC) or Final Business Case (FBC) submissions be unsuccessful, or in the event that the PFI project ends for some other reason. I thought it would be helpful to follow up on some of the key issues in writing.
In particular, I wanted to reiterate our desire to continue to work collaboratively with you and that our support is behind developing the case for a successful re-procurement of the PFI. However, we have agreed that we should work together to develop possible alternative arrangements in the event that the government decides that the case for continuing to provide PFI funding has not been made and that funding should come to an end. For the avoidance of doubt, nothing referred to in this letter prejudices Birmingham City Council's (BCC) position in that regard or pre-empts the government's decision-making process in any way. The possible alternative arrangements set out below, including any estimated figures referred to, are for illustrative purposes only to assist with contingency planning".
The letter then went on to provide information about possible alternative arrangements in the event that PFI credits funding was withdrawn.
"The council remains clear that its priority and preference is to work with Birmingham Highway Ltd (BHL) to deliver a successful procurement of the long-term replacement subcontractor for the PFI contract. Nonetheless, given our statutory duties as Highway Authority it is appropriate that if that is unsuccessful (for any reason) we have in place contingency arrangements that minimise the transitional period to a new long-term model. This aligns with the Department's requirement for the council to work with you on this in its 31 March 2022 letter.
To support achieving this mutual objective, we will need to work together to understand one another's positions and drivers and then develop the answers to a number of key questions".
The letter went on to raise detailed questions about the operation of transitional and alternative funding arrangements, were PFI Credit funding to be withdrawn.
"Under Scenario 2, the changes to the contract anticipated as part of the re-procurement of a new subcontractor, may trigger a classification review such that the Project will need to be reassessed under the current ESA 2010 rules. The latest rules generally consist of stricter interpretations than ESA 1995 and therefore there is a possibility that, even without significant changes to the contract, the Project could be determined to not meet these requirements and instead be brought on government balance sheet and impact DfT CDEL.
We understand that DfT will undertake its own assessment of the statistical treatment impact of the proposals under Scenario 2 based on the information that is made available as part of this OBC. However, we believe there is a strong probability that the Project would no longer meet the requirements to remain off government balance sheet under ESA 2010 rules".
Part 5 of the OBC stated the commercial case for Scenario 2. Section 5.2 included Table 20, which updated the risk allocation proposals in comparison to the existing Project Agreement. Paragraph 5.2.2 of the OBC then summarised the key changes in the proposed risk allocation.
"The Committee approved the OBC and the decision to proceed to FBC stage subject to getting DfT Ministers' agreement and subject to HMT assurances of continued financial support. Senior engagement from HMT was needed. The Permanent Secretary also offered to have a discussion with the Chief Executive at BCC. It would be important to be frank about how finely balanced this decision was and the implications either way".
"I am writing to seek your approval to allow Birmingham City Council to proceed to Full Business Case for the re-procurement of a long-term replacement contractor for the 2010 Highways Maintenance Private Finance Initiative, through to the original planned end date in 2035.
Birmingham City Council have submitted a well-developed Enhanced Outline Business Case (OBC) which I believe meets previous conditions we have set and provides a good value for money case for their proposal to undertake the re-procurement based on receiving the same total funding currently received under existing PFI arrangements (£50.3m p.a.).
The strategic case for the continued investment in Birmingham's roads is strong, as it was in 2010 when the PFI began. Furthermore, continuing with a long-term approach of the PFI will provide more planned, preventative maintenance, which involves resurfacing at regular intervals, and which is the most cost-effective method of keeping the road surface in good repair. The consequence of delaying essential work on roads is often to increase the bill for fixing the problem in the future.
My approval of the OBC would also be subject to Birmingham City Council meeting certain conditions at the FBC stage. These include:
to demonstrate in the FBC that they are equipped and capable of managing the PFI to ensure that it delivers the outputs and outcomes the contract
to ensure that the Value for Money (VfM) position in the FBC does not deteriorate and seek opportunities to improve commercial arrangements
to ensure that competitive tension is retained through the procurement and that there is sufficient incentive for shareholders to remain dedicated to delivering the agreed outputs and outcomes through to hand-back
to ensure that there is sufficient incentive for shareholders to remain dedicated to delivering the agreed outputs and outcomes through to hand-back.
I am conscious that owing to changes to ESA10 accounting guidance, that occurred after the original PFI was signed, a re-procured contract will likely no longer meet the rules for National Accounts that must be followed at any major change to a PFI. Therefore, the project will no longer be classified as a PFI for National Accounts purposes.
The result of this is that the DfT would need up front CDEL budget cover for the discounted cumulative value of the Department's future grants towards capital components of the contract. I am therefore also asking for your agreement for HMT to provide the budgetary cover required to cover these costs if the project is also approved at the FBC stage. I would also like confirmation that HMT will honour the existing funding (£50.3m per year), which is part of our SR settlement, to pay the ongoing costs associated with the PFI if approved at FBC.
This change in PFI classification is outside of DfT's control and I don't believe it should impact on the decision to continue to support this vital project.
I understand your officials will also be reviewing the Enhanced Outline Business Case and be providing you with advice and I hope we are able to move quickly to provide Birmingham City Council with the approvals they need to develop their FBC, ahead of the planned Summer submission".
"Thank you for your time earlier and sorry it was not the happiest of conversations. We discussed contingency planning and the potential risk that HMT officials are currently not minded to recommend the re-procurement to their Ministers. I had pushed back on many of the points they raised, in particular the fact it feels like the 2010 decision is being revisited, and Mo and I were clear on the challenges that you had faced with Amey.
As discussed on our call, I said I would summarise the areas in which HMT had outlined concerns which are below:
- showing the real benefits / better outcomes that Birmingham have achieved in the last 13 years through the uplift in funding (when compared to formula funding for the rest of the country);
- the value for money argument, particularly given difficulties with affordability; and
- if the PFI continues, what will the £50m per annum buy / what will there be to show for it.
Whilst I believe the business case answers the above, it might be useful for us to put forward some tangible / real world examples of where the money has been sent and a short summary on the last bullet too".
"1.2 …the Council considers it important to remind Government of the ramifications of a decision not to proceed with the project ahead of the imminent submission of the Full Business Case (FBC). Appropriate background and context is also shown in Appendix 1.
1.3 It is important to note that the Council has been:
i. working closely with Government on the restructuring of the contract since 2019 on the basis agreed by all parties;
ii. providing all the information and analysis requested to a significant range of changing officials; and
iii. (based upon methodologies discussed and agreed with those officials) produced a number of business case versions.
Throughout this process Government has re-confirmed its ongoing support for the project.
1.4 In the context of this collaborative process, the Council continues to work with BHL on the re-procurement of the long-term services subcontractor. This has now almost concluded, with two tenders having been received on 4 July 2023. An FBC based on the final preferred bid is due to be submitted to Government on 11 August.
1.5 The Council has worked on the assumption that, provided the re-procurement of the sub-contract was successful within the boundaries agreed by all parties in 2019, the restructuring of the project would be completed. The Council has invested heavily to allow a successful re-procurement in a way that delivers value for money, to enable the continuation of the funding that HMT committed in 2010".
"If Government withdraws its support now, it will require the Council to terminate the 25-year PFI contract… This would have grave consequences for the Council, including significant financial exposure that the Council neither considers itself directly responsible for nor has the financial means to manage".
Paragraphs 3.3 and 3.4 then gave further information about the feared financial consequences of "terminating the PFI contract at this late stage in the re-procurement process".
"The FBC builds on the confirmation of ministerial approval to proceed with the restructuring and re-procurement of the PFI Contract on 31 March 2022 in response to the Outline Business Case (OBC) and its subsequent update in September 2022 (UOBC). As you are aware, the project has continued to proceed, with the Department involved in the all-party steering group. The FBC has been developed in line with all the Department's and HM Treasury's additional requirements as communicated to us. This collaboration has been important in developing a successful restructuring of the PFI Contract and re-procurement of the operating sub-contract, following the settlement with Amey in 2019.
Importantly, the FBC demonstrates how the value for money (VfM) proposition for the Project has improved substantively since the preparation of the OBC. The competitive procurement process has resulted in a preferred bidder whose submission significantly exceeds investment outcomes anticipated at the OBC stage. We believe we have now satisfied all of the Department's and HM Treasury's requirements as communicated to us through correspondence.
…
We have now reached a position where the restructuring agreed to by all parties in 2019 can be successfully completed. Our expectation and assumption is that the restructuring of the project will be completed following ministerial approval of the FBC. This is in line with the assurances we have received to date from the Department that the project will be supported as long as VfM continues to be demonstrated..".
"BCC and BHL have been cognisant of the unique circumstances of this Project. We have also sought to address feedback received at previous business case stages. Since the submission of the Updated Outline Business Case (UOBC) we now have a Preferred Bidder, whose bid will deliver a quantitative value for money benefit of [sum]. This is significantly in excess of the [sum] envisaged at UOBC stage.
We consider that this FBC presents a compelling, value for money approach to maintaining the city's highway network to 2035".
Paragraph 3.3.12 of the FBC summarised the case in relation to risk allocation under Scenario 2 -
"The anticipated risk allocation (and mitigation against those risks, where applicable) is set out in more detail in the Commercial Case, but in summary is represented below in Table 6. The revised PFI contract is structured such that the majority of risk remains with the private sector in order to meet PFI principles (SOPC4), refined so as not to present a specific barrier for market acceptability. Those items marked in bold represent areas where there has been an increased transfer of risk back to BCC relative to the original PFI contract".
"reject the revised PFI proposal because it involves substantially less risk transfer to the private sector compared with the original arrangement and is unaffordable to DfT due to the upfront CDEL charge associated with the accounting treatment of the revised deal. HMT propose to continue the current level of Highways Maintenance funding (£50m pa – the same level as the PFI deal) for BCC until the end of the SR period (24-25), via WMCA's CRSTS settlement".
"On 19th September HMT officials confirmed that CST will reject the revised PFI proposal. The revised deal cannot be recorded "off balance sheet" in accordance with the relevant ESA 2010 accounting rules (as would be expected with any PFI/PPP and as was the case for the 2010 PFI) because: (i) the proportion of capital work to be undertaken relative to the value of the asset on completion of the Project is insufficient; and (ii) there is insufficient risk transferred to the private sector. The revised deal must therefore be accounted for as 'on balance sheet', which requires an up-front CDEL charge in the region of £200m to £250m. HMT have therefore rejected the OBC on the basis that DfT would need to cover this cost and it is unaffordable".
Paragraphs 7 and 8 advised –
"We have been reviewing the rationale behind HMT's decision, looking carefully at DfT's financial position including the implications of the PM's announcement on the reallocation of HS2 funding to Network North.
The accounting treatment of the revised deal has been understood for some time. In your letter to the CST requesting approval of the OBC, the department asked HMT to cover the up-front CDEL charge in line with our interpretation of HMT guidance covering charges arising from a change in accounting treatment. In taking a decision on the OBC, HMT have indicated that they expect the department to cover this. We were made aware of HMT's position just prior to the announcement on Network North, which allocates £8.3bn of additional funding to Highways Maintenance over 10 years. However, only £150m of this will be available nationally on both 2023/24 and 2024/25. The CDEL charge would fall in one of these two years and we therefore consider that the Network North funding does not change the affordability position. Consequently, the revised deal continues to be unaffordable to DfT".
"Although affordability, in view of the balance sheet treatment has been the main rationale for rejecting the proposed deal, HMT have raised wider concerns that mean they would be unlikely to approve the OBC if the affordability of the up-front CDEL cost were resolved".
"Thank you for your letter of 23 April seeking approval to allow Birmingham City Council to proceed to Full Business Case stage for the re-procurement of a long-term replacement contractor for the 2010 Highways Maintenance Private Finance Initiative (the "Project"). Thanks to your officials for the close work with my department on this proposal over the last few months.
I agree with you on the importance of investing in local roads maintenance, including in Birmingham. This is an important part of ensuring we maintain a safe and secure network for road users and businesses. Given spending pressures across DfT and wider Government, we will need to consider how we balance these requirements with the need to put the public finances on a sustainable path in the medium term.
I understand that the Project cannot be recorded "off balance sheet" in accordance with the relevant ESA 10 accounting rules, as would be expected for any PFI/PPP and as was that case for the 2010 PFI. That is because (i) the proportion of capital work to be undertaken relative to the value of the asset on completion of the Project is insufficient, and (ii) insufficient risk is transferred to the private sector. Therefore, in accordance with ESA 10 accounting rules, DfT would be required to record a CDEL expense (equivalent to the discounted value of the lifetime grant element of capital works within the contract) in order to demonstrate the transfer of risk to your department. Your department has estimated this at £200-£250m, which as your department's Investment, Portfolio and Delivery Committee report states, would require significant CDEL budget cover, making this unaffordable for DfT. With this in mind, and the need to effectively control public spending in the current fiscal climate, I am therefore not content to approve of the re-procurement of a long-term replacement contractor.
However, I am conscious of the points you make in your letter on the importance of investing in cost-effective local roads maintenance. Noting your department has already been allocated c.£50m p.a. over SR21 for Birmingham local roads maintenance, I am content for this existing SR21 funding to be incorporated in to the CRSTS settlement for West Midlands Combined Authority (WMCA) through to the end of the SR21 period. Our officials should work together on this, including any required budget exchanges necessary to deliver this change, with any budgetary decisions to be signed-off by my officials.
We should then determine the future arrangements for funding local roads maintenance in the West Midlands in the round at the next SR, as part of the forthcoming Single Settlement for WMCA".
Legal framework
Statutory arrangements
"Legal basis of payments. Grant for all projects other than those which involve HRA housing will be paid under section 31 of the Local Government Act 2003 to receiving authorities listed in Local Government PFI Grant Determinations".
"31(1) A Minister of the Crown may pay a grant to a local authority in England towards expenditure incurred or to be incurred by it".
"(3) The amount of a grant under this section and the manner of its payment are to be such as the person paying it may determine.
(4) A grant under this section may be paid on such conditions as the person paying it may determine.
(5) Conditions under subsection (4) may, in particular, include—
(a) provision as to the use of the grant;
(b) provision as to circumstances in which the whole or part of the grant must be repaid.
(6) In the case of a grant to a local authority in England, the powers under this section are exercisable with the consent of the Treasury".
Legitimate expectation – principles and approach
"62. From these authorities it can be deduced that where a clear and unambiguous undertaking has been made, the authority giving the undertaking will not be allowed to depart from it unless it is shown that it is fair to do so. The court is the arbiter of fairness in this context. And a matter sounding on the question of fairness is whether the alteration in policy frustrates any reliance which the person or group has placed on it".
"Legitimate expectation of either kind may (not must) arise in circumstances where a public decision-maker changes, or proposes to change, an existing policy or practice. The doctrine will apply in circumstances where the change or proposed change of policy or practice is held to be unfair or an abuse of power: see for example Ex parte Coughlan paragraphs 67 ff, Ex p Begbie [2000] 1 WLR 1115, 1129F – H. The court is generally the first, not the last, judge of what is unfair or abusive; its role is not confined to a back-stop review of the primary decision-maker's stance or perception…".
"The initial burden lies on an applicant to prove the legitimacy of his expectation. This means that in a claim based on a promise, the applicant must prove the promise and that it was clear and unambiguous and devoid of relevant qualification. If he wishes to reinforce his case by saying that he relied on the promise to his detriment, then obviously he must prove that too."
"…the theme that is current through the legitimate expectation cases. It may be expressed thus. Where a public authority has issued a promise or adopted a practice which represents how it proposes to act in a given area, the law will require the promise or practice to be honoured unless there is good reason not to do so. What is the principle behind this proposition? It is not far to seek. It is said to be grounded in fairness, and no doubt in general terms that is so. I would prefer to express it rather more broadly as a requirement of good administration, by which public bodies ought to deal straightforwardly and consistently with the public. … Accordingly a public body's promise or practice as to future conduct may only be denied, and thus the standard I have expressed may only be departed from, in circumstances where to do so is the public body's legal duty, or is otherwise, to use a now familiar vocabulary, a proportionate response (of which the court is the judge, or the last judge) having regard to a legitimate aim pursued by the public body in the public interest. The principle that good administration requires public authorities to be held to their promises would be undermined if the law did not insist that any failure or refusal to comply is objectively justified as a proportionate measure in the circumstances".
(1) To what has the public authority committed itself, whether by promise or practice?
(2) Has the public authority acted (or does it propose to act) unlawfully in relation to its commitment?
(3) What should the court do?
"20. The answer to the first is a question of analysing the evidence - it poses no jurisprudential problems.
21. Sometimes, as in the first category of outcome analysed in Ex parte Coughlan [2000] 2 WLR 622 (para. 57) the answer to this first question is dispositive of the case. It seems to us that the present authorities in that group of cases (in particular In re Findlay [1985] AC 318, 338) make it generally appropriate to allocate the issue of legitimacy to this initial question. In other words, if the public body has done nothing and said nothing which can legitimately have generated the expectation that is advanced to the court, the case ends there. It seems likely that a representation made without lawful power will be in this class. In the present case the answer to the first question is not in dispute and is in favour of the applicants".
"22. Two problems face a court in answering these questions. The first is to find one or more measuring rods by which it can be objectively determined whether a certain action or inaction is an abuse of power. The second is what order to make once an abuse of power has been discerned – can the court come to a substantive decision itself or should it send the matter back to the decision taker to decide afresh according to law?
23. To a degree the answer to the second depends on the approach one takes to the first. As Laws L.J. pointed out in R v Secretary of State for Education and Employment ex parte Begbie [2000] 1 WLR 1115 at page 1131C 'The more the decision challenged lies in what may inelegantly be called the macro-political field, the less intrusive will be the court's supervision. More than this: in that field, true abuse of power is less likely to be found, since within it changes of policy, fuelled by broad conceptions of the public interest, may more readily be accepted as taking precedence over the interests of groups which enjoyed expectations generated by an earlier policy.'"
"[41] …a public authority will not often be held bound by the law to maintain in being a policy which on reasonable grounds it has chosen to alter or abandon. Nor will the law often require such a body to involve a section of the public in its decision-making process by notice or consultation if there has been no promise or practice to that effect. There is an underlying reason for this. Public authorities typically, and central government par excellence, enjoy wide discretions which it is their duty to exercise in the public interest. They have to decide the content and the pace of change. Often they must balance different, indeed opposing, interests across a wide spectrum. Generally they must be the masters of procedure as well as substance; and as such are generally entitled to keep their own counsel. All this is involved in….the entitlement of central government to formulate and re-formulate policy. This entitlement - in truth, a duty – is ordinarily repugnant to any requirement to bow to another's will, albeit in the name of a substantive legitimate expectation. It is repugnant also to an enforced obligation, in the name of a procedural legitimate expectation, to take into account and respond to the views of particular persons whom the decision-maker has not chosen to consult."
[42] But the Court will (subject to the overriding public interest) insist on such a requirement, and enforce such an obligation, where the decision-maker's proposed action would otherwise be so unfair as to amount to an abuse of power, by reason of the way in which it had earlier conducted itself. In the paradigm case of procedural expectations it will generally be unfair and abusive for the decision-maker to break its express promise or established practice of notice or consultation. In such a case the decision-maker's right and duty to formulate and re-formulate policy for itself and by its chosen procedures is not affronted, for it must itself have concluded that interest is consistent with its proffered promise or practice. In other situations – the two kinds of legitimate expectation we are now considering – something no less concrete must be found. ….what is fair or unfair is of course notoriously sensitive to factual nuance….".
"77. Furthermore, at paras. 80-81, Holman J accepted submissions made by counsel for the Secretary of State in that case. In particular he accepted the submission that governments may change at general elections, and even if there is an expectation that a given government will carry through its policies and assurances, there can be no legitimate expectation that a later and politically different one will do so, absent the kind of binding commitment that a promissory note contains. He also accepted the submission that:
"It was plainly implicit that the delivery of a project of such a scale, duration and ambition [as BSF] would always be conditional upon the availability of the requisite finance and the policy decisions of the government of the time. Had it been otherwise the present government's predecessor would have been guilty of unlawfully fettering a successor government."
78. There are similar views expressed by Laws LJ in the Bhatt Murphy case, at para. 41, which I have already cited. It seems to me that such views reflect important constitutional principles as to the proper role of the courts in our democratic society and have particular resonance in the context of public finances, in which the Crown is responsible to the House of Commons in particular".
Ground 1 – Substantive legitimate expectation
Submissions
"Termination or variation of a PFI contract could in some circumstances (as set out in the Local Government PFI Project Support Guide) lead the Government to reassess the level of revenue support based on the extent to which the anticipated capital investment is delivered…"
The relevant section of the Guide was Section G. Paragraph 2.1 of Section G of the Guide provided that the Government reserved the right to stop support "in exceptional circumstances". Mr Oldham KC characterised the terms of the PFI Credit Letter and the Guide as "the Conditions". It was submitted that the Conditions provided that the PFI Credits could be terminated or reduced by the Defendant only on the basis of a decision, lawfully made, that there were exceptional circumstances to justify doing so.
Discussion
(1) The Government had a policy of support for good PFI projects.
(2) In recognition of the long-term nature of PFI contracts, the Government's policy was to maintain revenue support for PFI projects in the long term.
(3) However, that support was not guaranteed.
(4) Where an existing PFI contract was either terminated or subject to major variation (including extension), the Government would wish to review the new arrangements or changed circumstances before deciding whether it would continue to provide the revenue support for the PFI project at its committed level.
(5) In the case of termination or major variation of a PFI contract, the local authority must therefore report the proposed arrangements for termination or variation to the relevant department of government before proceeding with it.
"Changes to the contract, including possibly termination, may occur after it has reached financial close and the PFI credit has been issued. Any major variation must be reported to the sponsoring department who will consider whether there are PFI support implications".
The advice given in the following, numbered paragraphs of Section G in relation to "Increases" and "Decreases" was intended to inform local authorities of the likely "PFI support implications" in the circumstances of the scenarios therein considered.
"(2.1) Government reserves the right to stop support in exceptional circumstances . Such circumstances could be where…"
"(2.2) Termination or variation of the contract… could result…The interpretation of whether a reduction is significant or not is a matter for the sponsoring department, and should always be considered on a scheme-by-scheme basis after taking into account all the relevant circumstances".
"(2.3) In some cases the nature of the assets may change…In such circumstances an authority should notify the sponsoring department who will consider whether the alternative proposals are acceptable to them".
(my emphases).
"As a first step, sponsoring departments will therefore consider the circumstances of any major variation in this light."
(my emphasis)
The words which I have emphasised are important. They make clear that in any given case, the sponsoring government department will initially consider whether termination or variation of the contract justifies the immediate or early withdrawal of support. Such a peremptory response is, however, likely to be appropriate only in exceptional circumstances of the kind illustrated by the example given in that paragraph. Even then, the local authority would not be left in a position in which it was unable to meet its accrued liabilities.
"Under the conditions of the PFI grant the Council is required to report any proposed major variation to the contract to DfT for prior approval, in their capacity as the sponsoring government department. The changes proposed constitute a major variation and DfT require a full business case, which, if supported, will then be submitted for consideration (etc)…".
(my emphasis)
"Our intention is to continue paying PFI grant at the current rate, subject to value for money. We understand that the Council may also be considering changes to the contract, and it is of course at liberty to submit other proposals for support from new and existing funding streams from Government. DfT will consider such changes on their merits, provided always that the business case demonstrates continued value for money".
Conclusions
Ground 2 – failure to have regard to the Claimant's substantive legitimate expectation
Ground 3 – The Decision does not establish exceptional circumstances
Ground 4 – Procedural legitimate expectation/ fairness
The issue
Submissions
"But the Court will (subject to the overriding public interest) insist on such a requirement, and enforce such an obligation, where the decision-maker's proposed action would otherwise be so unfair as to amount to an abuse of power, by reason of the way in which it had earlier conducted itself… What is fair or unfair is of course notoriously sensitive to factual nuance….[t]he categories of unfairness are not closed, and precedent should act as a guide not a cage".
"…for this secondary case of procedural expectation to run, the impact of the authority's past conduct on potentially affected persons must, again, be pressing and focused. One would expect at least to find an individual or group who in reason have substantial grounds to expect that the substance of the relevant policy will continue to enure for their particular benefit: not necessarily for ever, but at least for a reasonable period, to provide a cushion against the change. In such a case the change cannot lawfully be made, certainly not made abruptly, unless the authority notify and consult".
"93. …. I have rejected the argument that the claimants can have had a legitimate expectation that all or any of their stopped projects would necessarily continue; but that does not diminish that the five claimants all had their recent OBC approval letters and were continuing not only to act and spend in reliance upon them, but actively to engage in continuing dialogue with the department or PfS about them. It is, in my view, relevant also that the sums involved were very large: a hundred or more millions of pounds for most of these claimants. While the scale of the proposed expenditure may have added to the imperative to make substantial savings, it did also, in my view, fortify the duty to consult.
94. In my view the impact of the department's past conduct on the five claimants was indeed "pressing and focussed" and change could not lawfully be made abruptly without some prior consultation".
"…although the source or origin of that decision is a change of policy by a public authority, it is not the change of policy itself that the claimant is entitled to complain about but its application to a particular claimant who has a legitimate expectation that a benefit or advantage will continue but which is now being withdrawn. This is because there is an element of retrospectivity in such a case. If a public authority simply changed its policy for the future, it is doubtful that anyone could complain about lack of consultation. However, if a particular person or small class of identifiable persons have enjoyed a benefit or advantage under the previous policy, they may, depending on the circumstances, have a claim to procedural fairness before the decision is made to apply the new policy to them and so to withdraw or discontinue that benefit or advantage".
Conclusions
"The FBC has been developed in line with all the Department's and HM Treasury's additional requirements as communicated to us. This collaboration has been important in developing a successful restructuring of the PFI Contract and re-procurement of the operating sub-contract, following the settlement with Amey".
(my emphasis)
Ground 5 – Failure to have regard to relevant considerations and irrationality
Ground 6 - Reasons
Delay
Disposal and Relief