KING'S BENCH DIVISION
PLANNING COURT
B e f o r e :
____________________
TELFORD AND WREKIN COUNCIL | Claimant | |
- and - | ||
(1) SECRETARY OF STATE | ||
FOR LEVELLING UP, HOUSING AND COMMUNITIES | ||
(2) GREENTECH INVEST UK (1) LTD | Defendants |
____________________
Riccardo Calzavara (instructed by Government Legal Department) for the First Defendant.
The Second Defendant did not appear and was not represented.
____________________
Crown Copyright ©
MR JUSTICE EYRE:
Introduction.
The Chronology.
"If so advised, an application for an extension of time for service of the claim without prejudice to the primary submission that the claim was served in time."
The Applications and the Contentions in Summary.
The Applicable Provisions.
"extend or shorten the time for compliance with any rule, practice direction or court order (even if an application for extension is made after the time for compliance has expired)."
"(1) The Claimant may apply for an order extending the period for compliance with rule 7.5", and then at (3):
"If the Claimant applies for an order to extend the time for compliance after the end of the period specified by rule 7.5 or by an order made
under this rule, the court may make such an order only if –
(a) the court has failed to serve the claim form; or
(b) the Claimant has taken all reasonable steps to comply with rule 7.5 but has been unable to do so; and
(c) in either case, the Claimant has acted promptly in making the application."
"As for extensions of time for service of a judicial review claim form, whilst CPR 7.6 does not directly apply, its principles are to be followed on an application to extend under CPR 3.1(2)(a). Thus, unless a Claimant has taken all reasonable steps to comply with CPR 54.7 but has been unable to do so, time for service should not be extended."
". . . as I have already said, there is no logical basis for treating statutory review cases any differently from judicial review cases on this point, and since Corus is not authority to the contrary, it would not be proper for me not to apply the approach in Good Law to the current case and I do so."
". . . that any delay measured in a day or more in serving a claim for statutory review such as this cannot be other than serious and significant. That is because of the importance attached to service of the claim form within the period required by the statute. . ."
"was plainly an unnecessary risk to take since it needed the co-operation of the court to obtain a service copy of the sealed claim form. . ."
"These rules and their Practice Direction shall apply to Planning Court claims unless this section or a Practice Direction provides otherwise."
"A Part 8 claim form must be used and must be filed at the Administrative Court within the time limited by the statutory provisions set out in paragraph 1.2."
That being section 288 of course.
"The claim form must be served on the appropriate Minister or government department and, where different, on the person indicated in the following table . . ."
And then provides for the persons on whom there must be service.
"The claim form must be served within the time limited by the relevant enactment for making a claim for planning statutory review set out in paragraph 1.2."
Was the Application served in Time?
Should an Extension be granted?
Conclusion.