QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT AT MANCHESTER
1 Bridge Street West, Manchester M60 9DJ. |
||
B e f o r e :
____________________
Daniel Johns Manchester Limited |
Claimant |
|
- and - |
||
Manchester City Council |
Defendant |
____________________
Paul Greatorex (instructed by City Solicitor, Manchester) for the Defendant
Hearing dates: 20 February 2018
Draft judgment circulated: 22 February 2018
____________________
HTML VERSION OF JUDGMENT
Crown Copyright ©
His Honour Judge Stephen Davies
His Honour Judge Stephen Davies sitting as a High Court Judge:
Introduction
The facts
"The existing permission for redevelopment of the site is a product of the past and as discussed yesterday I think our preference would be to see a more comprehensive approach to development including the adjacent site. However, we could not prevent the existing scheme from being implemented. On this basis it would be worth meeting with these potential owners to understand how serious their intentions are for building out any scheme."
"The heads of terms are, as you will appreciate "subject to contract". As previously discussed, the council has concerns about the scale and density of the proposed scheme and whilst these concerns stand we will not be pursuing any agreement to transfer the freehold of its leasehold interest in the site on completion of the scheme."
(1) The fact that the email was composed and sent in some haste indicates that this was not the only reason. He did however also submit, and I accept, that this was a summary of what was the most important reason.(2) The subsequent statement by the city council's solicitor in his letter dated 7 December 2016 that the reasons were: "(a) concerns about the proposed scheme; (b) insufficient information as to who the scheme was intended for; (c) concerns about whether it could be delivered and effectively managed by Cityscape" indicates that: (i) there were other reasons, although: (ii) reason (c) was clearly mistaken in referring to Cityscape, when it should have referred to the claimant. He also submitted, and I accept, that reason (a) was clearly the most important reason and that it also clearly referred back to the one reason stated in the email of 28 November 2016. No real attention has been paid to reason (b) either in the grounds or the evidence or in submissions.
(a) The claimant was clearly intending to develop the Rosedale building site only, rather than the proposed extended site, including the Yikman site.(b) The city council did not consider such a development to be viable.
(c) The city council did not consider the claimant to have sufficient experience or ability to deliver the development.
The law
"55. Having considered these authorities my conclusions are as follows:(1) In a case such as the present, involving a challenge to a decision of a public body in relation to a contract, it is necessary to consider:
(a) by reference to the contract in question, to the relevant statutory power, to the statutory framework (if relevant), and to all other relevant matters, whether or not, and if so to what extent, the defendant is exercising a public function in making the decision complained of;(b) whether, and if so to what extent, the grounds of challenge involve genuine and substantial public law challenges to the decision complained of, or whether, and if so to what extent, they are in reality private law challenges to decisions made under and by reference to the terms of the relevant contract.
(2) In a case involving a challenge to a decision of a public body acting under a statutory power but in relation to a contract and in the absence of a substantial public function element, a claimant will nonetheless normally be entitled to raise genuine and substantial challenges based on fraud, corruption, bad faith, and improper motive (in the sense identified by De Smith of the knowing pursuit of an improper purpose).
(3) The extent to which a claimant will be entitled to raise genuine and substantial public law challenges beyond those limited classes will depend on a careful analysis of all of the relevant circumstances so as to see whether or not there is a relevant and sufficient nexus between the decision in relation to the contract which is challenged and the grounds complained of."
Ground 1
(a) All that Ms Hodgett said in that internal email was that if a new application was made the fact that there was an existing consent which had been implemented would be a material consideration and that if the new application was of the same nature as the existing permission the principle of development would be acceptable unless there were material changes in circumstances.(b) However what I concluded in paragraph 40 was that the city council had a genuinely held view, held on rational grounds, that if the claimant had applied for the same planning permission from scratch in 2016 it would not have obtained it. I was not considering and was not invited to address the entirely separate question as to whether or not if the claimant, already having the benefit of the 2011 permission, had decided to make a further application for precisely the same scheme in 2016 the city council would have been obliged to grant it on the basis that there were no or insufficient material changes in circumstances to justify refusal.
(c) The evidence that this was the city council's view, that it was genuine and that it was held on grounds which are not evidently irrational emanates from what Mr Jones said at the meeting of 25 May 2016 as was recorded by Ms Boyle at section 3.3 and as further stated by her in paragraph 44 of her witness statement at bullet point 2.
Ground 2
(1) For the reasons already given, I am satisfied that the claimant is not entitled to challenge this decision other than on the grounds of fraud, corruption, bad faith or improper motive as the knowing pursuit of an improper purpose.(2) Even if that was wrong, I am also satisfied that the city council was entitled to have regard to its concerns about the claimant's ability to deliver and manage the scheme. Those concerns related not just to the claimant's willingness to undertake the development in accordance with the existing permission, and the consequences if the city council became embroiled in a planning dispute as a result of the claimant seeking to amend the permission during the course of development but also, as Ms Boyle said, to the wider impact upon the city council's regeneration strategy if the claimant could not or would not do so.
Ground 3
Standing and delay
Conclusion
Consequential matters permission to appeal and costs
(1) The city council had failed to provide from the outset a full and proper account of its reasons for not proceeding with the transfer of the freehold from the outset, since its position had shifted dramatically from the sole reason stated by Ms Boyle on 28 November 2016 (paragraph 21 above) as clarified and amplified in the city council's solicitor's letter of 7 December 2016 (paragraph 22(2) above) to the more wide-ranging reasons and concerns subsequently given by the city council in Ms Boyle's witness statement as relied upon in the Detailed Grounds of Defence at paragraph 15.(2) If the city council had said in November 2016 what it said in Ms Boyle's witness statement at paragraph 60, which was that "the door remains open to the claimant to try and address the Council's concerns as set out above" then the claimant would have attempted to address those concerns in a constructive manner before resorting to proceedings so that there was at least a real prospect that these proceedings might have been unnecessary.
(1) Permission be granted.(2) The claim be dismissed.
(3) Permission to appeal be refused.
(4) The Claimant do pay the Defendant's costs of the claim to be assessed on the standard basis if not agreed.
(5) If, 21 days after the amount of costs has been agreed or assessed, the Claimant has not paid them to the Defendant as required by paragraph (4), the Defendant do have liberty to apply to vary this order and to seek a non-party costs order against Daniel Johns Ltd and/or Mr Khalid Iqbal Bhatti.
Note 1 In fact the reference was to the claimants parent company, but nothing turns on that. [Back]