QUEEN'S BENCH DIVISION
PLANNING COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
R (on the application of CITY OF WESTMINSTER) |
Claimant |
|
- and - |
||
TRANSPORT FOR LONDON - and - (1) CS11 LONDON LIMITED (2) LONDON BOROUGH OF CAMDEN (3) CROWN ESTATE PAVING COMMISSION (4) THE ROYAL PARKS |
Defendant Interested Parties |
____________________
Timothy Straker QC & Thomas Francis (instructed by Transport for London) for the Defendant
Andrew Parkinson (instructed by LCS Practice Ltd) for the First Interested Party
Hearing date: 6 September 2018
____________________
Crown Copyright ©
Sir Ross Cranston:
INTRODUCTION
BACKGROUND
The Mayor's strategy and CS11
TfL's consultation, its response and discussions with Westminster
"Further and more detailed traffic modelling needs to be carried out to demonstrate that the forecast traffic reassignments can be accommodated at key junctions as expected. If the network is not capable of accommodating the reassigned flows, TfL should advise to what degree further traffic reduction is required, or how this might affect network wide journey times... TfL should show the changes in traffic flows along roads forming the sections of the CS11 route being consulted upon, within broad band widths, which is considered reasonable and allows for inevitable modelling inaccuracies. This data has not been presented as part of the consultation material… The City Council therefore objects to the proposals being implemented on behalf of its residents and businesses who have requested detailed information on the traffic modelling work undertaken on several occasions."
"[W]e intend to proceed to the next stage, namely full engineering design ('detailed design') of the majority of the proposals… However, we will be doing further work on the proposals for The Regent's Park before deciding on a way forward for this section of the route."
"We consulted on two options for Portland Place. Having considered the consultation responses, we will be taking forward Option B – segregated cycle lanes on Portland Place. We will now carry out detailed traffic modelling on this option and the design will be reviewed in the light of the outcomes of this modelling."
"Therefore journey time data for traffic and buses, degree of saturation and queue data, and traffic reassignment plots will be key outputs for assessing the acceptability of both sets of proposals."
TfL's 15 March 2018 documents and the 15 March Decision
"Decision required. The Healthy Streets Portfolio Board is asked to note the paper and: (a) endorse additional Programme and Project Authority of [redacted] for CS11 to enable: I. Construction of Swiss Cottage II. Completion of The Regent's Park Outer Circle section through design and construction with delegated authority to Cycling Programme Board." [There was no (b)]
"Royal Parks and affected London boroughs (Camden, Westminster) being slow to grant approvals, respond to ongoing issues, and to sign-off design and construction works as they proceed, resulting in delays and increased costs."
Judicial review and the Additional Reasons
(e) "In any event, as part of its decision-making TfL did consider the (unlikely, in TfL's view) scenario that it may not have all consents in place to proceed with the phased programme of construction. As TfL will explain in its evidence, Ben Plowden was appraised of the possible implications for the delivery of the scheme in the event that any of the required consents were not obtained. Based on all of the information available, TfL was satisfied that it was appropriate to proceed."
"having considered this alongside the other information presented to the meeting and discussed with the other [Board] members I was satisfied that it was appropriate and reasonable to proceed with the Decision to approve the start of the delivery of CS11. The approach taken to the Decision, and to CS11 overall, is not unusual. It reflects the practical realities association with the delivery of a scheme such as CS11 that involves several decision-making authorities and requires numerous stages of approval over months and years…The evidence available to me when I took the Decision pointed clearly to an ongoing relationship with all parties working together on CS11…"
LEGAL FRAMEWORK
"(2) A decision falls within this paragraph if it would otherwise have been taken by the relevant local government body, or a committee, sub-committee of that body or a joint committee in which that body participates, but it has been delegated to an officer of that body either—
(a) under a specific express authorisation; or
(b) under a general authorisation to officers to take such decisions and, the effect of the decision is to—
(i) grant a permission or licence;
(ii) affect the rights of an individual; or
(iii) award a contract or incur expenditure which, in either case, materially affects that relevant local government body's financial position."
THE LEGAL ISSUES
The Additional Reasons
"[34] In my judgment, the following propositions appear from the above authorities:
(i) Where there is a statutory duty to give reasons as part of the notification of the decision, so that (as Law J put it in Northamptonshire County Council ex p D) "the adequacy of the reasons is itself made a condition of the legality of the decision", only in exceptional circumstances if at all will the Court accept subsequent evidence of the reasons.
(ii) In other cases, the Court will be cautious about accepting late reasons. The relevant considerations include the following, which to a significant degree overlap:
(a) Whether the new reasons are consistent with the original reasons.
(b) Whether it is clear that the new reasons are indeed the original reasons of the whole committee.
(c) Whether there is a real risk that the later reasons have been composed subsequently in order to support the tribunal's decision, or are a retrospective justification of the original decision. This consideration is really an aspect of (b).
(d) The delay before the later reasons were put forward.
(e) The circumstances in which the later reasons were put forward. In particular, reasons put forward after the commencement of proceedings must be treated especially carefully. Conversely, reasons put forward during correspondence in which the parties are seeking to elucidate the decision should be approached more tolerantly."
"30. The second additional and perhaps over-arching factor is whether it would be just in all the circumstances to refuse to admit the subsequent reasons of the decision-maker. So if there was no need for a decision to contain reasons, it might be strange if on the facts of a particular case, later reasons could not be adduced to meet a challenge on grounds of, say, a misdirection, unfairness or inconsistency. If this were not so, there might in some cases be unfairness between the parties as the decision-maker could not defend himself. Obviously the application of principles of fairness would also enable the court to reach a decision on the cogency of and weight to be given to the new reasons."
Reasons for the Decision
Openness of Local Government Bodies Regulations
CONCLUSION