QUEEN'S BENCH DIVISION
PLANNING COURT IN WALES
2 Park Street Cardiff CF10 1ET |
||
B e f o r e :
____________________
THE QUEEN on the application of MYNYDD Y GWYNT LIMITED |
Claimant |
|
- and - |
||
THE SECRETARY OF STATE FOR BUSINESS, ENERGY AND INDUSTRIAL STRATEGY |
Defendant |
____________________
Richard Moules (instructed by the Government Legal Department) for the Defendant
Hearing date: 11 October 2016
____________________
Crown Copyright ©
Mr Justice Hickinbottom :
Introduction
The Factual Background
"For each species of particular interest, the population dynamics data on the species indicate that it is maintaining itself on a long-term basis as a viable component of its natural habitats…"
This is taken directly from the definition of "favourable conservation status" in article 1 of EC Council Directive 92/43/EEC on the conservation of natural habitats and wild fauna and flora ("the Habitats Directive") (see paragraph 14 below).
"The SPA area will continue to support at least 15 pairs of breeding red kites, or 0.5% of the British population";
and, with regard to "Specified Limits", as a "Performance Indicator", it is said:
"Upper limit: None.
Lower limit: At least 15 pairs of kites nest regularly within the SPA, or within 2km of the boundary."
The Core Management Plan makes clear that such indicators are merely part of the objective, and projects "must be based on the entire conservation objective, not just the performance indicators".
The Law
"… population dynamics data on the species concerned indicate that it is maintaining itself on a long-term basis as a viable component of its natural habitats."
"Any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. In the light of the conclusion of the assessment of the implications of the site…, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned…".
"The site" in this context is, of course, a reference to any European Site. Whilst the article refers to plans and projects, we are dealing here with a project; and, unless the context requires otherwise, I shall not refer further to plans.
"(1) A competent authority before deciding to undertake, or give consent, permission or other authorisation for, a… project which… is likely to have a significant effect on a European [S]ite… (either alone or in combination with other plans or projects)… must make an appropriate assessment of the implications for that site in view of that site's conservation objectives.
(2) A person applying for any such consent, permission or other authorisation must provide such information as the competent authority reasonably require for the purposes of the assessment or to enable them to determine whether an appropriate assessment is required.
(3) The competent authority must for the purposes of the assessment consult the appropriate nature conservation body and have regard to any representations made by the body….
…
(5) In the light of the conclusions of the assessment, and subject to regulation 62 (considerations of overriding public interest), the competent authority may agree to the… project only after having ascertained that it will not adversely affect the integrity of the European [S]ite…
(6) In considering whether a… project will adversely affect the integrity of the site, the authority must have regard to the manner in which it is proposed to be carried out or to any conditions or restrictions subject to which they propose that the consent… should be given."
Therefore, by virtue of regulation 61(5), the competent authority is proscribed from consenting to the project proceeding unless it will not adversely affect the integrity of the European Site.
"… [T]he applicant should… provide the (Secretary of State] with such information as [he or she] may reasonably require to determine whether an Appropriate Assessment is required. In the event that an Appropriate Assessment is required, the applicant must provide the [Secretary of State] with such information as may reasonably be required to enable [he or she] to conduct the appropriate assessment. This should include information on any mitigation measures that are proposed to minimise or avoid likely effects."
i) Exactly how the article 6(3) obligations are satisfied in a particular case is a matter for the competent authority.
ii) Article 6(3) does not provide for or require any formal screening (Champion at [37] and following); but most decision-makers understandably adopt a two stage process. First, the competent authority considers whether the project "is likely to have a significant effect on a European [S]ite…", because, unless it does, an "appropriate assessment" is not required. If the authority considers that the project is likely to have that effect, then it moves to the second stage; and carries out the appropriate assessment itself.
iii) In respect of the first stage, as Advocate General Sharpston pithily put it in her opinion in Sweetman (at [50]), the question to be addressed by the competent authority is "Should we bother to check?". To add some flesh to that, the precautionary approach applies; and "likely" to have a significant effect is a reference to "likely" in a European sense, i.e. not a level of chance exceeding the balance of probabilities, but merely a real risk (see, e.g., Hart District Council at [78]). The burden of proof effectively lies on the applicant, as I have explained. Therefore, where there is any real doubt as to the absence of significant effects of the proposed project on a protected area, then the competent authority must proceed to make an appropriate assessment. Thus, a competent authority will be required to perform an appropriate assessment unless there is no credible evidence of a real (rather than hypothetical) risk that the project will cause a significant effect to a European Site (see Boggis at [37], and Bateman at [17]).
iv) In respect of the second stage – the appropriate assessment itself – the competent authority can only grant consent for a project if, applying the precautionary principle, it is "convinced" that the project will not adversely affect the integrity of the protected site concerned (Waddenzee at [48] and [56]-[59]). A project not directly connected to the management of a European Site (such as this) will adversely affect its integrity if, applying the precautionary principle, it is liable to prevent (i.e. it poses a real risk to) the lasting preservation of the constitutive characteristics of the European Site that are connected to the presence of a priority natural habitat whose conservation was the objective justifying the designation of the European Site in accordance with the Habitats Directive. Thus, as was said by the Grand Chamber in Waddenzee (at [59]):
"… [T]he competent national authorities, taking account of the conclusions of the appropriate assessment of the implications of mechanical cockle fishing for the site concerned, in the light of the site's conservation objectives, are to authorise such activity only if they have made certain that it will not adversely affect the integrity of the site. That is the case where no reasonable scientific doubt remains as to the absence of such effects…". (see also the opinion of Advocate General Sharpston in Sweetman at [51] to similar effect).
"Certain", here, also has a particular meaning. For a competent authority to "have made certain that [the project] will not adversely affect the integrity of the [European] site", it must be satisfied that there is no real (as opposed to merely hypothetical) risk to the integrity of the site.
v) This assessment exercise requires consideration of the potential effects of the project on the protected species, and whether those effects pose a real risk to the maintenance of the favourable conservation status in respect of that species as reflected in the conservation objectives for that species (see the opinion of Advocate General Sharpston in Sweetman at [50]). Advocate General Kokott helpfully considered the nature of the competent authority's task in relation to this second stage in her opinion in Waddenzee (at [97]-[98]):
"The assessment must, of necessity, compare all the adverse effects arising from the… project with the [European] site's conservation objectives. To that end, both the adverse effects and the conservation objectives must be identified. The conservation objectives can be deduced from the numbers within the site. However, it will often be difficult to encompass all adverse effects in an exhaustive manner. In many areas there is considerable scientific uncertainty as to cause and effect. If no certainty can be established even having exhausted all scientific means and sources, it will consequently be necessary also to work with probabilities and estimates. They must be identified and reasoned."
Therefore, it may be appropriate or necessary for assumptions, probabilities and estimates to be used, but they cannot be mere guesses: they must be "identified and reasoned".
vi) In respect of the appropriate assessment, "a high standard of investigation" is required. No particular procedure being prescribed, the issue ultimately rests on the judgment of the competent authority (Champion at [41]), taking into account any secured mitigation (Hart District Council at 76]). As Sales LJ recently put it in Smyth (at [78]):
"… Although the legal test under each limb of article 6(3) is a demanding one, requiring a strict precautionary approach to be followed, it also clearly requires evaluative judgments to be made, having regard to many varied factors and considerations. As Advocate General Kokott explained in her opinion in [Waddenzee] at [107], the conclusion to be reached under an 'appropriate assessment' under the second limb of article 6(3) cannot realistically require ascertainment of absolute certainty that there will be no adverse effects; the assessment required 'is, of necessity' subjective in nature'".
vii) In exercising that judgment, the competent authority must give "considerable weight" to the advice of "the appropriate nature conservation body", and give cogent and compelling reasons for departing from it (Hart DC at [49]: see also Akester at [112] and DLA Delivery at [32] to similar effect).
viii) The burden of proof again lies on the applicant. In effect, the burden upon him is to ensure that the competent authority is provided with sufficient information to convince the authority, taking into account all material considerations and exercising an evaluative judgment in respect of them, that the project poses no real risk in respect of the integrity of the European Site as considered through the prism of the conservation objectives. "Information" is a broad concept, stretching beyond relevant raw material: it includes appropriate analysis. Where the authority is unconvinced by the information lodged at any particular time in the process, it may request further information from the applicant under regulation 61(2) of the 2010 Regulations (see paragraph 16 above). The authority must necessarily have a wide discretion in the requests for information it considers appropriate to make. Once the applicant has been given a proper opportunity to submit the information upon which it relies and all of the information is in, if that information does not convince the competent authority, then the authority may – indeed, must – refuse to make a DCO, irrespective of the cause of that deficiency.
ix) The decision of the competent authority cannot be construed as a statute or deed; it must be construed in a flexible and common sense way, bearing in mind that the applicant and other interested parties will know the issues with which he was required to grapple (Bloor at [19](1)). The reasons for the decision must enable an informed reader to understand why the decision was reached as it was, and what conclusion were reached on the "principal important controversial issues" (ibid at [19](2)).
x) Consistency in decision-making is important; but cases are usually fact-specific. In any event, it is not a principle of law that like cases must always be decided alike. The relevant decision-maker must exercise his own judgment on this question, if it arises (Bloor at [19](6)).
xi) Once made by the competent authority, the assessment is only judicially reviewable on conventional grounds, the standard of review being the Wednesbury rationality standard (see, e.g., Smyth at [78]-[81]).
The Examination
"On the basis that there are no nests within the maximum foraging range of red kite as identified in the SNH Guidance, it is considered that there is no connectivity with the SPA.
Therefore Objective 1 would not be affected by the scheme as the scheme would not affect the population within the SPA."
That case, made at the outset of the application, was maintained throughout (see, e.g., paragraph 7 of its Deadline VII representations dated 16 April 2015).
i) Using data from red kite surveys, the Claimant predicted the collision risk mortality of red kite at the Application Site to be less than one pair per annum. However, because of the lack of connectivity, it submitted that in any event there was no real risk that these birds would be from the SPA.
ii) There would be steps taken to mitigate the loss of red kite as a result of collision with turbine blades, e.g. steps to reduce the amount of carrion available in the immediate area, and thus reduce the attraction of the Application Site as a foraging ground for red kite.
iii) There would be no in-combination effect because the other wind farms are further away from the SPA than the Application Site.
i) reliability of the survey data;
ii) whether any red kite observed on the Application Site may originate from the SPA;
iii) quantification or efficacy of mitigation effects; and
iv) in combination effects with other wind farms.
However, (ii) was potentially determinative in this sense: if the Secretary of State was satisfied that there was no real risk that red kite observed on the Application Site came from the SPA, there could be no real risk of the project adversely affecting the integrity of the Site.
i) NRW disagreed with the Claimant's interpretation of the conservation objective, namely that that objective was met if the current red kite population of the SPA was above 15 pairs. The last monitoring report, in 2011, recorded 18 pairs of red kite within the SPA (compared with 15 pairs recorded in 1997), and 66 pairs within 2km (compared with 41 pairs in 1997). In NRW's view, the effect of the project on the SPA population had to be considered against the current SPA population, as the conservation objective was to maintain or increase that population.
ii) In respect of the Application Site alone, in terms of the foraging range, NRW considered that the non-breeding season should also be considered, because red kite remain in the area outside the breeding season. As I have indicated, the Pendlebury review underlying the SNH guidance shows that red kite can regularly forage up to 10km from roosting locations during the non-breeding season.
iii) The Claimant had no data to demonstrate the origin of red kite using the Application Site during the breeding and non-breeding season; and it therefore could not be assumed that they do not originate from the SPA. Given the precautionary principle, the winter foraging ranges in the Pendlebury review and the absence of any demonstrative evidence from the Claimant, NRW said that it should be assumed that red kite at the Application Site come from the SPA.
iv) NRW considered that the Claimant's red kite survey data – which were used to demonstrate the collision risk mortality rate for red kite – were older than good practice guidance suggested as suitable to inform an assessment, and the surveys did not always conform to best practice (e.g. because they did not include surveys of nest locations). The survey data were therefore not as reliable as they might have been.
v) NRW said that the proposed mitigation may reduce red kite numbers around the Application Site, but there was no quantification of the reduction (if any) in likely collision numbers.
vi) However, prior to the closure of the examination (as recorded in the Examination Report at paragraph 5.2.30), "in its final comments before the close of the examination, NRW [did] not specifically conclude that there would be any [likely significant effects] on the red kite qualifying feature of the SPA as a result of the proposal alone". Nor did it conclude that there would be no such risks. Rather, in paragraph 25 of its Deadline VII response dated 16 April 2015 towards the end of the examination process, NRW said this:
"21. … [T]here is no certainty regarding the origin of red kites using the [Application Site] in the breeding season and their connectivity to the SPA as no data has been collected by the [Claimant] to demonstrate this….
…
25. NRW's stance remains that, given the difficulty of demonstrating that no birds originate from the SPA, it should be assumed they may be connected to the SPA. This is [in] line with the precautionary principle inherent within the Habitats Regulations assessment process. The assessment should then assess whether the likely mortality rates alone or in-combination with other projects including the grid line and other proposed wind farms are likely to affect the population of red kites for which the SPA is designated. The assessment could be undertaken using a number of assumptions regarding the proportion of birds using the site likely to originate from the SPA."
vii) NRW considered that the in-combination assessment should cover the other five wind farms within 10km of the SPA (which included Bryn Blaen, which is about 6km from the SPA). In NRW's view, the Claimant had provided insufficient information to enable NRW to advise on whether there would be an adverse effect on the integrity of the red kite feature of the SPA in combination with other projects. Thus, in its response dated 20 May 2015 to the Claimant's Deadline X material, it said:
"In NRW's previous submissions (e.g. NRW submissions for Deadline VII 16 April 2015) we advised that the assessment for the Elenydd Mallean SPA collated the collision data for all of the wind farms included in the in-combination assessment. This would have allowed for an assessment of whether the in-combination mortality rate had the potential to effect the red kite population given the current increasing population numbers. If this had been provided, despite the uncertainty regarding the origins of the birds on the site, it may have demonstrated that the combined mortality levels were such that it could be concluded that there would be no effect on the population of red kite within the SPA.
This is important and relevant because NRW has insufficient information to advise the ExA on whether there would be an adverse effect in-combination on the integrity of the Elenydd Mallean SPA" (emphasis in the original).
"NRW's position during the Examination was that there can be no certainty about the origin of red kite using the Application Site in the absence of survey data…. Given the [Claimant's] up-to-date survey data compiled from visits in March and April 2015 (albeit this covered the early breeding season), I consider this provides a reasonable degree of certainty that red kite do not originate from the SPA or its buffer close to the Application Site";
and, consequently, the proposal would not result in a likely significant effect, looked at alone.
"NRW's position at the end of the Examination was that it considered it had insufficient information to advise on whether there would be an adverse in-combination effect on the integrity of the SPA in respect of the red kite feature…. However, I consider that, on the basis of the evidence presented: there [is] a reasonable certainty that red kite observed within the Application Site do not originate from the SPA; that the proposal would not have a [likely significant effect] on this feature; and this must feed through to the in-combination effect. As such, irrespective of any shortfall in data about other proposed or existing wind farms close to the SPA, I am satisfied that the proposal would not contribute to any adverse effect on the integrity of the [SPA] in respect of this feature."
"8. There is insufficient information for NRW to advise on the maximum level of collision mortality and displacement for there to be no adverse effect on site integrity. There is currently no information on the population dynamics of the [SPA] features. Therefore, although it may be possible to conclude that low mortality levels may be unlikely to affect the population in the long term, we cannot advise with certainty as to threshold for there to be no adverse impacts on integrity."
i) In respect of connectivity, she agreed with NRW that the Claimant had not shown beyond "reasonable scientific doubt" that the red kite using the Site do not come from the SPA. She referred specifically (in paragraph 6.12 of the Record) to the view of NRW that the Claimant had not provided any data to demonstrate the origin of the red kite using the Application Site, and it could not be said with any certainty that they do not come from the SPA. The Secretary of State therefore proceeded on the basis that they may (ibid).
ii) The conclusions of the Secretary of State's assessment in relation to the project alone are set out in paragraphs 6.19-6.22 of the Record, as follows:
"6.19 In [its HRASR]…. the Applicant states that there will be no LSE [i.e. likely significant effect] on the red kite population of the SPA, as the birds using the Site are not from the SPA. In the view of the SoS [i.e. the Secretary of State], the Applicant does not give evidence to support this statement.
6.20 The ExA concluded that on the basis of the evidence presented, there is a reasonable certainty that red kite observed on the Project Site do not originate from the SPA, and therefore the Project will not have a LSE alone on the SPA….
6.21 At the end of the examination NRW advised that it should be assumed that the red kite that use the application site may be connected to the SPA, and that the HRA should assess whether the possible mortality rates are likely to affect the SPA red kite population…. They do not agree that it has been demonstrated that adverse effects on the red kite feature of the site as a result of collisions can be ruled out alone….
6.22 The SoS, having considered the information provided during and after the examination, agrees with NRW, as the statutory nature conservation body and concludes that there is not enough information to ascertain that there will be no adverse effect on the integrity of the red kite feature of the Elenydd Mallean SPA from the Project alone. The SoS is of opinion that:
- It has not been proven beyond reasonable scientific doubt that the red kite using the project site do not come from the SPA, and accepts NRW's advise on this matter.
- Mitigation proposed by the Applicant to address the issue of collision risk through aiming to avoid making the area under and around turbines attractive to red kite may reduce red kite numbers, there is no certainty that this will be the result, and there has been no quantification of the reduction in the likely collision numbers. It is also unclear whether these activities actually already currently occur.
- The Secretary of State shares the concerns of NRW as to the age and methodology of the surveys that informed the Applicant's assessment, as they did not conform to recommended good practice guidance."
iii) In relation to the in-combination effects, the Secretary of State noted that there were five wind farms within 10km of the Application Site; and, although the Claimant had concluded there would be no connectivity with the Application Site from these proposals because of distance and the SNH guidance, NRW had advised that these ought to be included for consideration of in-combination effects; and that there should be an assessment of whether the likely mortality rates alone or in combination with other projects posed a risk to the relevant red kite population. The Claimant had not provided any such information; and, therefore, the Secretary of State concluded that "the [Claimant] has not demonstrated sufficiently that there is unlikely to be a significant in-combination effect on red kite, as the red kite collision figures for the other developments have not been provided and considered by the [Claimant]" (paragraph 6.34).
iv) In other words, the Secretary of State was not convinced by the information before her that the project, alone or in combination, posed no real risk to the conservation objective in respect of the red kite population of the SPA. The Claimant (as applicant) had failed to satisfy the burden upon it by providing sufficient information to convince the Secretary of State that there was no such risk.
v) Finally, the Secretary of State considered that, in the absence of sufficient information about the possible environmental effects of the proposed development, it was not possible to consider whether the public interest might override those effects for the purposes of paragraph 62 of the 2010 Regulations (paragraph 28 of her decision letter).
The Grounds of Challenge
Ground 1: The Secretary of State failed to perform a proper appropriate assessment.
Ground 2: The Secretary of State failed to apply guidance on foraging distances in this case consistently with other cases where the same issue arose.
Ground 3: The Secretary of State failed properly to consider the derogation in article 6(4) of the Habitats Directive and regulation 61(3) of the 2010 Regulations; and, in particular, failed to give any proper reasons why she found there were no imperative reasons of overriding interest for granting consent, despite a negative conclusion on the appropriate assessment.
Ground 1: The Appropriate Assessment
i) Using data from red kite surveys performed in the period 2005-11, the Claimant predicted the collision risk mortality of red kite to be less than one pair per annum.
ii) There would be steps taken to mitigate the loss of red kite as a result of collision with turbine blade on the Application Site, e.g. steps to reduce the amount of carrion available in the immediate area,
iii) There would be no in-combination effect because the other wind farms are further away from the SPA than the Application Site.
i) NRW had been unimpressed with the survey data. In the third bullet point of paragraph 6.22 of the Record, the Secretary of State indicated that she shared those concerns. Although she did not expressly refer to the Claimant's response to those criticisms, there is nothing to suggest that she did not take those into account in concluding that there was some force in NRW's opinion. In any event, because of the lack of connectivity, the Claimant merely submitted that, whatever the risk from the project to red kite in general, there was no real risk to red kite from the SPA, because they would not be on the Application Site, a proposition which the Secretary of State had already dealt with. As NRW had indicated, the Claimant had failed to provide any further data or information to remedy this identified defect.
ii) With regard to the proposed mitigation, the Secretary of State dealt with that in the second bullet point of paragraph 6.22. Although as a matter of principle removing carrion from the Application Site would in theory reduce its attraction for foraging – and, in practice, it might – there was nothing in the information provided as to how successful, if at all, that mitigation might be in practice.
iii) In relation to in-combination effects, the Claimant's case relied solely upon the proposition that there is no real risk of red kites foraging more than 4km from their roosts. The Secretary of State had already dealt with that. In the circumstances of this case, she did not accept it. In paragraph 6.34 of the Record, she noted that NRW had advised that there should be an assessment of mortality rates in respect of red kite from these other project sites – and the Claimant had provided no such information.
i) The burden of proof lay on the Claimant as applicant, in the sense that it was up to the Claimant to provide sufficient information to convince the Secretary of State that there was no real risk of adverse effects as to the integrity of the red kite feature of the SPA. That obligation extended to any appropriate analysis of (or assumptions or estimates drawn from) raw material, upon which the Claimant relied.
ii) Although the ExA agreed with the Claimant's contention that there was no real risk that red kite at the Application Site would be from the SPA, the NRW's opinion was that there was such a risk. During the latter stages of the examination, NRW made that view very clear (see, e.g., paragraphs 30-1 above). The ExA recognised that that was NRW's opinion (see paragraph 34 above). It was also NRW's opinion that there was a parallel risk for the red kite on any other wind farm within 10km of the Application Site, relevant to the assessment of in-combination risk. It was for the Claimant to lodge any information it wished to be taken into account for the purposes of the appropriate assessment, in the event that the Secretary of State agreed with the advice of NRW, found there were such real risks and proceeded to perform an appropriate assessment involving an exercise evaluating the various material considerations.
iii) The Claimant had at least reasonable opportunities to do so. Given NRW's advice on this issue, despite the ExA's conclusion on it, the Secretary of State was still overtly concerned; indeed, as I have indicated, if she had had sufficient information to be convinced of the Claimant's case, she would not have had to make the request for information she did make post-examination, on 14 September 2015. That request was, at the very least, a clear marker that, to be convinced, she required further information.
iv) As Lord Carnwath JSC emphasised in Champion (see paragraph 20(vi) above), there is no set procedure for determining an appropriate assessment. In the evaluative exercise she had to perform, the Secretary of State had a wide discretion; including a wide discretion as to the information she requires to make an assessment that there is no risk, risk being rebuttably presumed as the default position.
v) The September 2015 request of the Claimant was specifically in respect of in-combination effects. Mr Kimblin submits that data on mortality rates was not available from all of the other wind farms – they had not been collected – but, even to the extent that that is true, the Secretary of State was right to focus on the data and analysis that had been provided, and whether that was sufficient to convince her that there was no risk to the integrity of the SPA from the proposed project in combination with other relevant projects.
vi) Of course, the Claimant's firm contention was that the real risk from the project to red kite on the SPA would be nil, because the real risk of red kite from the SPA flying there to forage was nil. Although no alternative analysis was put forward in the event that the Secretary of State did not agree with that proposition, it is clear that the Claimant considers that, if risk there be, it is small or very small. But that is not sufficient to answer the question posed by the appropriate assessment.
vii) The cases confirm that certainty with regard to the elements that go to the risk of adverse effect on integrity is not required and may well be impossible; and, as NRW accepted during the course of the examination, it may be necessary to make assumptions and estimates as to the level of particular risks.
viii) However, such assumptions and estimates must be identified and reasoned (see paragraph 20(v) above). The Secretary of State had no assistance on that score here. Neither the Claimant nor the ExA identified any assumptions or estimates upon which the Secretary of State's task should be based, let alone provide any analysis or reasoning for any assumptions and estimates proposed. NRW noted in particular that the Claimant had provided no information on the population dynamics of the SPA features (see paragraph 39 above), of some moment in the light of article 1 of the Habitats Directive and paragraph 1 of the conservation objectives for the Application Site (see paragraphs 10 and 14 above).
ix) In other circumstances, even in this absence of this information, I accept that the Secretary of State might have been able to say that, whatever the absent information might reasonably have said, she was convinced that, in practice, the project would not result in any adverse effect to the integrity of the SPA. I accept that it is possible that, on other facts, she would err in law if she did not draw that conclusion on the information available.
x) However, in this case, there were a substantial number of important "unknowns", including:
a) the proportion of red kite on the Application Site that came from the SPA;
b) the risk posed by the turbines to red kite on the Application Site (it being open to the Secretary of State to find, as NRW advised, that the data upon which one pair per year was based were unreliable);
c) the level of mortality that the SPA red kite population could sustain before the conservation objective would be undermined; and
d) the risk posed by the other five wind farms which (NRW advised) needed to be considered in an in combination assessment.
xi) Given the uncertainties so far as these relevant matters were concerned, on the information that was available, (a) NRW did not consider that it could be concluded that the risk to the integrity of the red kite feature of the SPA could be excluded on an alone basis, without making assumptions and estimates; and, in any event, (b) NRW did not consider that that risk could be excluded on an in-combination basis. The Secretary of State was bound to give considerable weight to that advice, unless there was good reason not to do so. Given her wide discretion in the matter, she was clearly entitled to follow that advice, even if others (e.g. the ExA) disagreed.
xii) In my judgment, in the circumstances of this case, in which relevant probabilities, estimates and assumptions were required for any positive appropriate assessment to be made, the Secretary of State did not err by refusing to go beyond the probabilities, estimates, assumptions and analysis before her in the form of the ExA's Report and supplementary documents. Insisting that probabilities, estimates and assumptions that are or might be relied upon by an applicant are identified and reasoned is not the same thing as requiring "absolute certainty" or "a search for certain proof demonstrated numerically" or even "an obsession with quantification", as Mr Kimblin at various times suggested.
xiii) It is not easy to see how the Secretary of State could – or why, after a six-month examination, she should – have made the necessary assumptions etc herself; but, in any event, if she had proceeded on the basis of any such further information, she would have had to disclose it to the parties for their comments, and the procedure does not require – and, certainly by the post-examination stage, is fair set against – such an iterative process. She was entitled to perform the evaluative balancing exercise on the (very limited) information that she did have available, as she did.
xiv) Although Mr Kimblin complains that the Secretary of State used boilerplate clauses in the decision letter, that letter correctly set out the law, in paragraphs 11-12. There is nothing to suggest that she did not have that well in mind when performing the assessment. As it had to do, the decision dealt with the issued raised by the claimant and case as put by the Claimant – by rejecting it – and, in doing so, she dealt with the information that was available in respect of the second stage assessment.
xv) Mr Kimblin complains that the Secretary of State wrongly proceeded on the basis that all of the red kite killed by turbines on the Application Site would come from the SPA. However, the Secretary of State was bound to deal with the conclusion of the ExA (agreeing with the Claimant's case) that there was no real risk of red kite from the SPA using the Application Site – because that was potentially determinative of the assessment. She dealt with that finding in the first bullet point in paragraph 22 of her decision letter. Although Mr Moules accepted that she did proceed on the basis that all red kite on the Application Site would be from the SPA, the decision makes no express finding to that effect. It simply says that, in the absence of compelling evidence to the contrary, they may; and, thereafter, the Secretary of State did not rely upon any estimate or assumption of that risk, because none had been provided by the ExA (or the Claimant), and she did not presume to make such an estimation or assumption herself. For the reasons I have given, she was right (or, at least, entitled) not to do so. Similarly, for the other unknowns.
xvi) The Secretary of State therefore had no assumptions, estimates or probabilities to fall back upon. Mr Kimblin says that, in those circumstances, she fell back upon using the worst hypothetical case in respect of each element. However, although I accept that that may have been the effect, the way the decision puts it, when read fairly and as a whole, is as follows. The Claimant had failed to provide information reasonably required to determine the appropriate assessment. The Secretary of State had, however, done the best she could on the available information. In line with advice from NRW, she had concluded that there was some risk of red kite on the Application Site originating from the SPA. Again in accordance advice from NRW, she was not convinced that the project in combination with other wind farms would not pose a risk to the red kite population of the SPA in terms of the conservation objectives, and thus was not convinced that it would not result in adverse effects that would impact on the integrity of the SPA. Given the absence of reasoned estimates and probabilities, she was also not convinced that there would be no risk looking at the effects of the project alone.
xvii) In my view, that approach cannot be said to have been wrong in law. The Secretary of State was entitled to conclude that, without further information in respect of the matters referred to in (x) above, she was not convinced as to the absence of risk that I have described.
"In simple terms, a project may account for a mortality of X birds a year alone, and a total mortality of Y birds per year combined with the impact of other projects. The mortality threshold Z represents the mortality rate that the SPA population can sustain without affecting its integrity. Provided that both X and Y are less than Z then the [Secretary of State] can conclude that the project would have no adverse effect on integrity. In this case fundamental pieces of information were missing. The Claimant only provided s figure for X, and did not provide a figure for Y. NRW advised that the surveys used by the Claimant to calculate X were flawed and in the September consultation neither the Claimant nor NRW provided a figure for Z to test X against. In those circumstances the [Secretary of State] was unable to determine the impact on integrity on a precautionary basis using the other data/surveys because there was no other data/figures that could be used on a precautionary basis as a substitute for accurate modelling data."
In my respectful view, that encapsulates the reasons why the Claimant's core submission fails.
Ground 2: Inconsistency
i) At Clocaenog, there was no evidence of the relevant raptor (peregrine falcon) breeding in the vicinity of the project site, and none had been observed using that site in either the breeding or non-breeding season. The RIES in that case concluded that there was no functional link between the relevant European Site (the Berwyn Special Protection Area) and the project site. The circumstances of that case were therefore materially different.
ii) The Bryn Blaen decision was made by the Welsh Ministers on appeal from the planning authority under section 288 of the 1990 Act, but only after the Secretary of State's decision in this case. In this circumstances, Mr Kimblin accepts that it is not more than an indicator that, had the Secretary of State approached this matter lawfully, she would have come to the same conclusion as the Welsh Ministers in that case. It thus goes only to relief, if the Secretary of State is found to have acted unlawfully.
Ground 3: Imperative Reasons of Overriding Public Interest ("IROPI")
i) The Claimant never contended or suggested that the project might be granted consent by reason of IROPI, in the event of a negative appropriate assessment. It is too late to raise the argument now.
ii) The Secretary of State did, in any event, expressly consider regulation 62, and concluded that she was unable to consider IROPI "in the absence of sufficient information to consider the possible environmental effects of the development". As Mr Moules submitted, it was logically impossible for her to have been satisfied that the (undetermined and, on the evidence, undeterminable) adverse impact was justified in the public interest under regulation 62. For the same reason, without knowing the extent of the adverse impacts, the Secretary of State could not properly determine appropriate compensatory measures under regulation 61(6), that she would have had to consider if she had had found IRPOI to have existed.
Conclusion