QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
RWE Generation UK PLC |
Claimant |
|
- and - |
||
Gas and Electricity Markets Authority -and- (1) National Grid Electricity Transmission PLC (2) Scottish and Southern Energy PLC (3) Drax Power Limited |
Defendant Interested Parties |
____________________
Daniel Beard QC, Alan Bates, Owain Draper and Daisy Mackersie (instructed by Office of Gas and Electricity Markets) for the Defendant
Richard Gordon QC and Gerard Rothschild (instructed by Shakespeare Martineau LLP) for the Interested Party (1)
Michael Fordham QC and Fraser Campbell (instructed by Addleshaw Goddard LLP) for the Interested Party (2)
Hearing dates: 1 and 2 July 2015
____________________
Crown Copyright ©
Mr Justice Lewis:
INTRODUCTION
THE FACTUAL BACKGROUND
The Transmission System
The Current TNUoS Charging System
The Other Charges
The Criteria For Deciding to Incur Investment Costs
The Decision-Making Process
The Decision
The change under WACM 2
"WACM 2 would split the TNUoS tariff for generators into two parts: the Peak Security tariff and the Year Round tariff. Only conventional generators would be charged the former but all generators, including intermittent ones, would be subject to the latter. This aligns to the transmission planning standard and reflects the fact that intermittent generators are not assumed to contribute to meeting peak security. In its power flow model used to calculate tariffs, National Grid would split the circuits between the two tariffs using similar assumptions to those in the transmission planning standard.
There would also be two further adjustments to the Year Round tariff. The first of these is to split the tariff into two elements: 'shared' and 'non shared.' This refers to generators' ability to 'share' transmission capacity which depends on the concentration of types of generators in a particular area. It recognises that it is efficient to build more transmission capacity for areas with a high concentration of low carbon generation because this type of plant is likely to be generating at the same time (ie when the wind blows) and is expensive to constrain off. Once the proportion of a low carbon generation in an area exceeds 50%, then part of the Year Round tariff will be classed as 'non-shared.' The proportion of the Year Round tariff that is non-shared will increase as the percentage of low carbon generation increases."
"WACM 2 is a better proxy of the drivers of transmission investment than the status quo, or other options presented, because it is more closely aligned to the transmission investment decision making criteria. Tariffs are therefore more cost reflective and better reflect the impact a generator has on the transmission system than the status quo. We recognise that in reality the impact of individual generators may differ from that estimated by WACM 2. However, this is a feature of the investment cost related pricing methodology. This brings other benefits for example through smoothing the lumpy nature of transmission investment and making tariffs more stable and transparent. These are important aspects to reducing barriers to entry and facilitating effective competition."
and
"We also consider that WACM 2 better meets our wider duties and principle objective to protect the interests of existing and future consumers than the status quo and other options presented."
"reflect, as far as is reasonably practicable, the costs…..incurred by transmission licensees in their transmission business…"
"[I]t better reflects the impacts different users have on the costs incurred by the owners of the transmission network. This is because it is a closer approximation of the transmission investment decision-making process. Our reasons for reaching this decision are explained below, taking into account responses to both our consultations."
"2.6 For charges to be cost-reflective the calculation of the incremental impact that a generator has on the system used in the charging methodology should reflect the transmission investment decision-making process and the drivers of transmission investment. This is governed by the Security and Quality of Supply Standards (SQSS) which sets out the minimum criteria that the Transmission Owners (TOs) must comply with when determining the required capability of the transmission network (known as the Main Interconnector Transmission System (MITs)).
"2.7 The growth in intermittent generation connecting to the transmission system has changed the nature of investment planning. Traditionally, this has been driven by the need to ensure peak security in an environment dominated by conventional generators. However, intermittent generators cannot be relied upon to be operating at peak demand. In addition, increasing intermittent generation has given rise to investment planning now being driven to efficiently managing constraint costs. The SQSS was updated to reflect this shift in 2011 to include two sets of criteria setting out the assumptions to be used when assessing the required level of capacity. TOs must build transmission capacity determined by the following two conditions:
- Demand Security criterion – the minimum transmission capacity required to ensure that conventional generators can meet demand at times when intermittent generators cannot run (ie there is no wind).
- Economy criterion – the additional transmission capacity needed above that to meet peak demand to efficiently manage the system taking into account the need to manage constraint costs in an effective and economic manner.
"2.8 As well as these two criteria, the SQSS also recognises that in reality, a full cost benefit analysis (CBA) will be required as part of the decision-making process for major investments. This may drive a different level of investment from that resulting from either of the two criteria above.
"2.9 Currently there is a mismatch between the investment planning requirements which drive actual transmission investment costs and the charging methodology which only considers peak demand as the driver of investment costs. WACM 2 seeks to address this defect and more closely align charges for generators to the costs they impose on the system. It updates the charging methodology by splitting the locational tariff into two components:
- Peak Security tariff – only conventional generators will be charged this component. This is because, under the SQSS Demand Security criteria, it is assumed that intermittent generators do not contribute to peak security and therefore do not drive investment for this reason.
- Year Round tariff – all generators will receive the year round tariff adjusted for their output. This is designed as a proxy for the impact a generator has on investment to manage constraint costs in an economic way. The reasoning for the use of annual load factor (ALF) in this calculation is discussed in the next section.
"2.10 To determine how generators in different areas impact on investment in that area, NGET must determine which requirements would drive investment under the SQSS. They will do this by allocating the transmission circuit routes in the power flow model used to calculate the tariffs to either the Peak tariff or the Year Round tariff. This is based on which drives the maximum flows on that circuit using assumptions that are consistent with the two criteria in the SQSS.
"2.11 We therefore consider that, in principle, splitting the tariff into two components more closely aligns the charging methodology to the investment decision making process than the status quo. It is therefore more cost reflective. Our view is that the way NGET determines the allocation of circuits to each tariff is appropriate. It reflects that, under the SQSS, intermittent plant do not drive investment for the purposes of peak security. It also realises that managing constraints efficiently is becoming increasingly important in driving transmission investment. This is an improvement on the existing methodology which only considers one driver of investment with all plant contributing equally to this."
"effective competition in the generation and supply of electricity and (so far as is consistent therewith) … competition in the sale, distribution and purchase of electricity."
"In addition, our view is that the current methodology could be discriminatory. Discrimination can inhibit competition and can arise not just from treating like cases differently without objective justification, but also from unjustifiably treating different cases alike. Currently, all generators receive the same tariff in a zone but this does not reflect how different generators may drive transmission investment in that location according to the investment planning process. WACM 2 would reduce this discrimination as different generators would be treated differently according to the impact they have on the network. This is an objective justification to charging users differently and is therefore not in itself discriminatory, as suggested by some respondents to our consultation."
"We have concluded that WACM 2 better facilitates the relevant CUSC objectives than the status quo because it results in more cost reflective charges increases effective competition compared to the staus quo and better incorporates developments in the transmission licencees' transmission business. It also better facilitates the Authority's principle objective of protecting the interests of existing and future consumers. Of all the proposals put to us under CMP213, our view is that WACM 2 best meets these objectives. We have therefore decided to implement WACM 2."
THE LEGAL FRAMEWORK
The Relevant Provisions of European Union Law
"(32) Further measures should be taken in order to ensure transparent and non-discriminatory tariffs for access to networks. Those tariffs should be applicable to all system users on a non-discriminatory basis.
…..
(36) National regulatory authorities should be able to fix or approve tariffs, or the methodologies underlying the calculation of the tariffs, on the basis of a proposal by the transmission system operator or distribution system operator(s), or on the basis of a proposal agreed between those operators(s) and the users of the network. In carrying out those tasks, national regulatory authorities should ensure that transmission and distribution tariffs are non-discriminatory and cost-reflective, and should take account of the long-term, marginal avoided network costs from the distributed generation and demand-side management measures."
"Each transmission system operator shall be responsible for:
(a) ensuring the long-term ability of the system to meet reasonable demands for the transmission of electricity, operating, maintaining and developing under economic conditions secure, reliable and efficient transmission systems with due regard to the environment.
…..
(f) ensuring non-discrimination as between system users of classes of system users, particularly in favour of its related undertakings."
"(d) helping to achieve, in the most cost-effective way, the development of secure, reliable and efficient non-discriminatory systems that are consumer orientated, and promoting system adequacy and, in line with general energy policy objectives, energy efficiency as well as the integration of large and small-scale production of electricity from renewable energy sources and distributed generation in both transmission and distribution networks;
(e) facilitating access to the network for new generation capacity, in particular removing barriers that could prevent access for new market entrants and of electricity from renewable energy sources;
(f) ensuring that system operators and system users are granted appropriate incentives, in both the short and the long term, to increase efficiencies in system performance and foster market integration;
(g) ensuring that customers benefit through the efficient functioning of their national market, promoting effective competition and helping to ensure consumer protection."
"(a) fixing or approving, in accordance with transparent criteria, transmission or distribution tariffs or their methodologies".
The Act
"3A.— The principal objective and general duties of the Secretary of State and the Authority."(1) The principal objective of the Secretary of State and the Gas and Electricity Markets Authority (in this Act referred to as "the Authority") in carrying out their respective functions under this Part is to protect the interests of existing and future consumers in relation to electricity conveyed by distribution systems or transmission systems.
"(1A) Those interests of existing and future consumers are their interests taken as a whole, including—
(a) their interests in the reduction of electricity-supply emissions of targeted greenhouse gases;(b) their interests in the security of the supply of electricity to them; and(c) their interests in the fulfilment by the Authority, when carrying out its functions as designated regulatory authority for Great Britain, of the objectives set out in Article 36(a) to (h) of the Electricity Directive."(1B) The Secretary of State and the Authority shall carry out their respective functions under this Part in the manner which the Secretary of State or the Authority (as the case may be) considers is best calculated to further the principal objective, wherever appropriate by promoting effective competition between persons engaged in, or in commercial activities connected with, the generation, transmission, distribution or supply of electricity or the provision or use of electricity interconnectors.
…..
"(2) In performing the duties under subsections (1B) and (1C), the Secretary of State or the Authority shall have regard to–
(a) the need to secure that all reasonable demands for electricity are met;(b) the need to secure that licence holders are able to finance the activities which are the subject of obligations imposed by or under this Part; and(c) the need to contribute to the achievement of sustainable development.
…..
"(5) Subject to subsections (1B) and (2), and to section 132(2) of the Energy Act 2013 (duty to carry out functions in manner best calculated to further delivery of policy outcomes) the Secretary of State and the Authority shall carry out their respective functions under this Part in the manner which he or it considers is best calculated–(a) to promote efficiency and economy on the part of persons authorised by licences or exemptions to distribute, supply or participate in the transmission of electricity to participate in the operation of electricity interconnectors or to provide a smart meter communication service and the efficient use of electricity conveyed by distribution systems or transmission systems;(b) to protect the public from dangers arising from the generation, transmission, distribution or supply of electricity or the provision of a smart meter communication service;(c) to secure a diverse and viable long-term energy supply,and shall, in carrying out those functions, have regard to the effect on the environment of activities connected with the generation, transmission, distribution or supply of electricity or the provision of a smart meter communication service."(5A) In carrying out their respective functions under this Part in accordance with the preceding provisions of this section the Secretary of State and the Authority must each have regard to—
(a) the principles under which regulatory activities should be transparent, accountable, proportionate, consistent and targeted only at cases in which action is needed; and(b) any other principles appearing to him or, as the case may be, it to represent the best regulatory practice."
"In paragraphs 1 and 2 "the relevant objectives" shall mean the following objectives:
(a) that compliance with the use of system charging methodology facilitates effective competition in the generation and supply of electricity and (so far as is consistent therewith) facilitates competition in the sale, distribution and purchase of electricity;
(b) that compliance with the use of system charging methodology results in charges which reflect, as far as is reasonably practicable, the costs (excluding any payments between transmission licensees which are made under and in accordance with the STC) incurred by transmission licensees in their transmission businesses and which are compatible with standard condition C26 (Requirements of a connect and manage connection);
(c) that, so far as is consistent with sub-paragraphs (a) and (b), the use of
system charging methodology, as far as is reasonably practicable, properly takes account of the developments in transmission licensees' transmission businesses; and
(d) compliance with the Electricity Regulation and any relevant legally
binding decisions of the European Commission and/or the Agency."
THE ISSUES
(1) the list of matters that constitute objective justification for differential treatment of different classes of generators under the Directive is exhaustive and does not include differential treatment on the basis provided for in the decision, including, in particular, cost-reflectivity in the sense that that phrase is used in the decision;(2) the Authority has misinterpreted the term "cost-reflective" in the recitals to the Directive as that phrase only ensures that the charges levied by the transmission owners are not excessive and does not permit a system of charges intended to achieve cost reflectivity between different classes of generators in the way described in the decision;
(3) the Authority failed to have regard to a relevant element of the system of
transmission charges, namely the BSUoS charges, and acted in a way that amounted to discrimination by altering only those parts of the charging system reflected in the TNUoS charging system not the BSUoS charging system;
(4) the Authority assumed that intermittent generators were making no
contribution to meeting demand at peak times when in fact, and as known by the Authority, intermittent generators were contributing (and increasingly so) to meeting demand at peak times;
(5) the Authority wrongly elided the obligation to meet the policy aim of ensuring security of supply with the assumption that conventional generators can be more reliable in meeting demand at peak times and wrongly, and irrationally sought to allocate transmission costs as if they were caused by conventional generation.
THE FIRST AND SECOND GROUNDS – DISCRIMINATION AND RELEVANT CONSIDERATIONS
The First Issue – Unlawful Discrimination
The Second Issue – The Interpretation of the Directive
The Third Issue –The BSUoS Charges
The Fourth Issue – Contribution to Meeting Demand at Peak Times
The Fifth Issue – The Alignment of the TNUoS Charging System with the SQSS Criteria
THE THIRD GROUND – STATE AID
ANCILLARY MATTERS
CONCLUSION