QUEEN'S BENCH DIVISION
PLANNING COURT IN BIRMINGHAM
Priory Courts, 33 Bull Street Birmingham |
||
B e f o r e :
____________________
THE QUEEN on the application of ROBERT HITCHINS LIMITED |
Claimant |
|
- and - |
||
WORCESTERSHIRE COUNTY COUNCIL |
Defendant |
|
- and - WORCESTER CITY COUNCIL |
I IInterested Party |
____________________
John Hobson QC (instructed by Simon Mallinson, Head of Legal and Democratic Services, Worcestershire County Council) for the Defendant
The Interested Party not appearing or being represented
Hearing date: 4 November 2014
Further written submissions: 7-10 November 2014
____________________
Crown Copyright ©
Mr Justice Hickinbottom:
Introduction
The Law
"203. Local planning authorities should consider whether otherwise unacceptable development could be made acceptable through the use of… planning obligations….
204. Planning obligations should only be sought where they meet all the following tests:
- necessary to make the development acceptable in planning terms;
- directly related to the development; and
- fairly and reasonably related in scale and in kind to the development."
"A planning obligation may only constitute a reason for granting planning permission if the obligation is:
(a) necessary to make the development acceptable in planning terms;
(b) directly related to the development; and
(c) fairly and reasonably related in scale and in kind to the development."
"Planning obligation" is defined in terms of a section 106 obligation (regulation 122(3)).
The Factual Background
"Development should only be prevented or refused on transport grounds where the residual cumulative impacts are severe."
"I hope you see that we have come a very long way towards the County [Council's] position in the spirit of seeking to negotiate an agreement and I would be grateful for a response today." "
"To pay the County Council the Worcester Strategy Transport Contribution… in three equal instalments, the first instalment to be paid on or before the Commencement Date the second instalment to be paid on or before the occupation of no more than 50% of the Dwellings on the Development and the third instalment to be paid on or before the occupation of no more than 75% of the Dwellings on the Development…".
"Dwellings" was defined in clause 1 as "dwellings… to be constructed within the Development…", "the Development" being defined as the development described in the Claimant's First Planning Application (clause 2.5). In line with the earlier agreement struck in correspondence, "the Worcester Strategy Transport Contribution" was defined in clause 1 as the sum equivalent to £4,530 in respect of each dwelling on the development (or such other sum on future review under clause 4.7), to be applied to the particular purposes of "the Worcester Transport Strategy", which was itself defined as meaning "a package of transport infrastructure and service enhancements across all modes of transport identified as being required to support the planned growth set out in the Draft South Worcestershire Development Plan". For 181 dwellings, the contribution was £819,930.
"4.5 Nothing in this Deed shall be construed as prohibiting or limiting any right to develop any part of the [Site] in accordance with a planning permission (other than the Planning Permission) granted by the City Council or the County Council or by the First Secretary of State on Appeal or by reference to him after the date of this Deed.
…
4.16 No person shall be liable for breach of a covenant contained in this Deed occurring after he shall have transferred to a third party all interest in the [Site] or the part of which such breach occurs but without prejudice to liability for any subsisting breach of covenant prior to parting with such interest."
i) The Claimant agreed, "for so long as the same is enforceable", to observe and perform the obligation to make the transport contribution under the First Section 106 Agreement, and to indemnify BDW against any breach or non-performance of that obligation (clause 15.2).ii) BDW agreed to the Claimant submitting a duplicate planning application for the Site, in identical terms to that granted in the First Planning Permission except without the obligation to pay the transport contribution ("the Second Planning Application") (clause 15.3).
iii) If the Second Planning Application were successful, BDW agreed that it would make an application for approval of reserved matters under the Second Planning Permission and:
"… in such circumstances [BDW] shall either only implement the [Second] Planning Permission, or if the [First] Planning Permission… has already been implemented, [BDW] shall ensure that once the aforementioned approval of reserved matters has been granted, any further development at the [Site] is carried out under the [Second] Planning Permission" (clause 15.5).The Contract also made provision for circumstances in which the Second Planning Application was partially successful, in that it resulted in a transport contribution but less onerous than the First Planning Permission.
i) The Inspector identified that the main issue before him was whether a planning obligation to provide contributions to the transport infrastructure would meet the tripartite test of regulation 122 of the CIL Regulations (paragraph 4 of his decision letter).ii) He acknowledged that the development proposal would result in additional traffic on the highway network which, with traffic from other future development, would add to traffic congestion in the area (paragraph 19).
iii) However, focusing on the impact on transport of the development itself rather than the cumulative impact of the development with other future developments (see, e.g., paragraph 14), he concluded that the net impact would not be severe (paragraph 19).
iv) He noted that extant Policy TR24 did not apply to residential development, and did not support the requirement for a transport contribution for the development proposal (paragraph 22); and that, in his view, neither did the emerging South Worcestershire Development Plan (paragraph 23). He also noted that the emerging policy referred to the production of a Developer Contribution Supplementary Planning Document, to be used in conjunction with a Community Infrastructure Levy Charging Schedule prepared under section 211 of the Planning Act 2008 which would be capable of requiring a transport contribution on the basis of pooled contributions towards the aggregated burden of development proposed in the development plan on the transport infrastructure and services – but that neither of those documents had been prepared in this case (paragraph 23).
v) He found that the evidence did not demonstrate that the contribution would be fairly and reasonably related in scale and kind to the development (paragraph 25); and a planning obligation to secure a contribution towards the Worcester Transport Strategy would not meet the requirements of regulation 122 of the CIL Regulations (paragraph 26).
Ground 1: The County Council erred in asserting that the First Planning Permission and First Agreement would continue to govern the development of the Site, on the ground that, two planning permissions existing for the Site, a developer might choose the permission upon which to rely.Ground 2: The County Council erred in refusing to consider varying the planning obligation in respect of the transport obligation under section 106A, on the ground that, whilst an authority has a discretion to modify or discharge a section 106 obligation, that discretion must be exercised for planning purposes. In this case, in considering whether the transport contribution could possibly have any continuing valid planning purpose, the County Council simply failed to grapple with the findings in the Inspector's recent decision or attempt to justify not following his conclusions.
Ground 3: The transport contribution obligation in the First Section 106 Agreement should be set aside because it was entered into by the Claimant under duress and/or as a result of the County Council's unconscionable conduct.
i) Patterson J refused the County Council's section 288 application, thereby upholding the Inspector's decision to grant the Second Planning Permission in the terms of the Second Application, i.e. without an obligation to make any transport contribution.ii) She set aside Judge Cooke's order granting permission to proceed in the Claimant's judicial review. She refused permission to proceed on Grounds 2 and 3, but gave permission to proceed on Ground 1. Under Ground 1, the Claimant sought the following declaration:
"The Claimant and any subsequent owners of the [Site] [can]not lawfully be required to pay further instalments of the [transport contribution] under the [First Section 106] Agreement if, upon grant of reserved matters for [the Second Planning Permission], they should choose to carry out development pursuant to [the Second Planning Permission] rather than [the First Planning Permission]."Patterson J appears to have considered it at least arguable that the position with regard to the enforceability of the obligation to make a transport contribution under the First Section 106 Agreement was potentially affected by the progress of the Second Planning Permission in respect of which (at the time of the hearing before her) outline permission had been granted but reserved matters had not been approved. She expressly granted permission to proceed "because of that uncertainty".iii) She directed that the Defendant's costs in relation to Ground 3 be paid by the Claimant in any event. She reserved the costs of Grounds 1 and 2.
"[BDW] intends to implement the Second Planning Permission and the Reserved Matters Approval. [BDW] enters into this Undertaking in order to dispense with the implementation of the First Planning Permission and to dispense with the discharge of the obligations under the First Section 106 Agreement and to implement the Second Planning Permission and the reserved Matters Approval and comply with the terms of the Second Section 106 Agreement."
Accordingly, by clause 4.1, BDW undertook to comply with the obligations set out in Schedule 1, and, under paragraph 1 of Schedule 1, it was provided:
"… [BDW] hereby covenants with the… Council and the County Council from the Commencement Date:
1.1 to discharge the obligations under the Second Section 106 Agreement in relation to the [Site];
1.2 to dispense with the implementation of the First Planning Permission; and
1.3 to dispense with the discharge of the obligations under the First Section 106 Agreement in relation to the [Site]…"
"This Undertaking will come to an end if… the Second Planning Permission expires before the Commencement Date without having been implemented."
The Parties' Respective Cases
"The Claimant and any subsequent owners of the Site cannot lawfully be required to pay further instalments of the Worcester Transport Strategy contribution under the First Section 106 Agreement having, upon the grant of reserved matters for the Second Planning Permission, elected to carry out development pursuant to the Second Planning Permission rather than the First Planning Permission".
The Issues
i) Whether, after the reserved matters approval perfected the Second Planning Permission and as a matter of law, the developer was able to elect to continue and complete the development under the Second Planning Permission rather than the First Planning Permission.ii) If so, whether the developer, on the evidence available, in fact elected to continue and complete the development under the Second Planning Permission.
iii) If so, what relief, if any, is appropriate.
The First Issue
"An application under section 73 is an application for planning permission: see section 73(1)…
Whilst section 73 applications are commonly referred to as applications to 'amend' the conditions attached to a planning permission, a decision under section 73(2) leaves the original planning permission intact and unamended. That is so whether the decision is to grant planning permission unconditionally or subject to different conditions under paragraph (a), or to refuse the application under paragraph (b), because planning permission should be granted subject to the same conditions.
In the former case, the applicant may choose whether to implement the original planning permission or the new planning permission; in the latter case, he is still free to implement the original planning permission…" (emphasis added).
In R v Leicester City Council ex parte Powergen UK Limited [2000] 81 P&CR 5 at [27], the Court of Appeal expressly approved those comments. Although both cases concerned section 73 applications, there is no reason why the principles set out in Pye should not be of general application in all cases where there are multiple extant planning permissions for the same site.
i) Lord Widgery clearly accepted the general principle, set out later by Sullivan J in Pye, that, where there are two planning permissions in respect of one site, then a developer may chose which he implements.ii) However, he held that a developer cannot implement two planning permissions for inconsistent developments, such that both are pursued.
iii) Although in Pilkington the first planning permission was fully implemented – the bungalow etc was built – there is no reason why the principle should not apply where the first development is only begun but not completed.
iv) Pilkington has no application in this case; because, although the two planning permissions in this case were alternatives (in the sense that, if one were pursued, the other could not be pursued at the same time because it is conceptually impossible for a development to be both subject to, and at the same time not subject to, a particular requirement), they were not inconsistent in the sense that the development in each case was identical. Therefore, at whatever stage the development had reached, a change in authorisation from one planning permission to the other would not be impossible and indeed would not cause any difficulties, conceptually or in practice.
v) In their written representations of 7 November 2014, Mr Hobson and Mr Whale submitted that any development purportedly done under the Second Planning Permission would in any event be unlawful because:
"… [I]t is physically impossible to carry out the development authorised by the Second Planning Permission in the light of the full scope of that which has been done or can be done pursuant to the First Planning Permission which has been implemented. Put simply, two houses cannot occupy the same footprint on the self-same plot."But, here, we are not talking about two different developments – as I have explained, the development in the First and Second Planning Permissions is identical. We are not considering the equivalent of two houses – but rather the same house – occupying the same footprint on the self-same plot. Whatever part of the development has been completed, it would clearly be possible to carry out the development in accordance with the Second Planning Permission in the light of that which has been done pursuant to the First Planning Permission.
The Second Issue
The Third Issue
Disposal