QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
33 Bull St, Birmingham, B4 6DS |
||
B e f o r e :
____________________
ESMOND JENKINS |
Claimant |
|
- and - |
||
GLOUCESTERSHIRE COUNTY COUNCIL |
Defendant |
|
- and - |
||
MORETON C CULLIMORE (GRAVELS) LIMITED COTSWOLD WATER PARK SOCIETY ENVIRONMENT AGENCY |
Interested Parties |
____________________
Paul Cairnes (instructed by Nigel Roberts, Director of Law and Administration Gloucestershire County Council) for the Defendant
Hugh Richards (instructed by Willans LLP Cheltenham) for the First Interested Party
Gwion Lewis (instructed by Jonathan R Taylor, Legal Services (Midlands), Environment Agency) for the Third Interested Party
The Second Interested Party did not appear and was not represented
Hearing dates: 24 - 25 January 2012
____________________
Crown Copyright ©
Mr Justice Bean:
"the progressive extraction and processing of sand and gravel with restoration using imported inert fill to a mix of wetland, grassland and recreational use, together with replacement visitor parking and access to the Keynes Country Park"
on land to the East of Spratsgate Lane, Shorncote, Gloucestershire ("the Quarry Site").
The permission under challenge
The Gloucestershire Minerals Local Plan
This application for judicial review
(1) Mineral working outside a Preferred Area: Misinterpretation or misapplication of Policy A4 of the GMLP;
(2) Noise: Misrepresentation of the views of the Environmental Health Officer; failure to take relevant Supplementary Planning Guidance into account;
(3) Flooding: Failure to comply with the publicity requirements of the Town and Country Planning (Environmental Impact Assessment) Regulations 1999 ("the EIA Regulations"); deferment to conditions of a flooding issue which should have been resolved prior to any decision to grant permission; and failure to give reasons for permission being granted notwithstanding that issue;
(4) Dust: Misleading the Committee by inaccurate statements in the Officer's Report; and irrationality, namely failure to take into account a material consideration.
It will be convenient to take grounds 3 and 4 in reverse order.
Ground 1: Policy A4 of the Gloucestershire Minerals Local Plan
"Proposed aggregate mineral working outside the Preferred Areas defined in this Plan will only be permitted where they are in accordance with and will secure the effective implementation of the objectives and other policies of the Plan by providing for either
A. The provision of aggregates not found in the Preferred Areas defined in this Plan where it can be demonstrated that the mineral is of a specification, or will meet a forecast shortfall, which is required to maintain the County's appropriate contribution to local, regional and national need, and where it is demonstrated that such provision would be significantly more acceptable overall than a site or sites in a Preferred Area.
or,
B. [not applicable]"
"Proposals for aggregates mineral development outside of the Preferred Areas will not be permitted unless exceptional circumstances prevail…. It is possible that on the basis of new information becoming available about mineral resources outside areas identified in the Plan that an operator could bring forward an application site which might be significantly more acceptable overall than a site identified in the Plan. Although in practise these circumstances should be rare, any such applications should be determined in light of development control and other relevant policies of the Plan …. Following the appraisal undertaken by the MPA … it is unlikely that any such sites outside the Preferred Areas would be significantly more acceptable overall."
"Bullet 2 – the acceptability of the proposal overall compared to the Preferred Areas
This will relate to any material considerations raised in the consultation of the proposal. A key issue will be those matters raised in 10.8 of the Inspector's Report (Dec 2001) and the MPA consideration of the Inspector's Report (Sept 2002) pages 97-99. What is central here is that the reasons for the Inspector recommending that the site not be included in the MLP are considered and potentially overcome in the current proposals. If the landbank issue is considered as outlined above, the main issue is that any potential harmful impacts to the amenity of the users of the Country Park can be mitigated. The Inspector particularly highlighted windblown dust and noise. It needs to be established that these issues can be satisfactorily mitigated and that the pollution control agencies, such as the CDC Environmental Health Officer, have no concerns [about] this proposal."
Ground 2: Noise
Noise: the SPG for the Water Park
"the proximity of existing settlements requires that control be exercised over the type of use in order to protect nearby residents."
"should not cause excessive noise, attract large numbers of people or generate high traffic volumes. Sites in low intensity zones may attract between 5 and 10 cars or 15 and 30 people per hectare at peak use."
Ground 4: Dust
"for the stabling of 4 horses, and storage of tractors and implements used exclusively to maintain 8.5 acres of pasture. All the horses kept on the property are owned by my family and consequently the proposed structure is intended solely to support my family's own smallholding/equestrian activities."
"an objection on the grounds of dust affecting the land adjacent to the north of the application site has not been raised. This is because these fields, although used for purposes ancillary to the enjoyment of the residential property known as 'Old Manor Barn', are considered by Officers to have an agricultural, rather than a domestic or equestrian use."
"It is my opinion that the submitted DMP will provide sufficient mitigation to limit the dust created at the site and that the measures outlined will prevent windblown dust leaving the site. The EHO is satisfied that the DMP meets best practice guidance and that the scheme will mitigate dust levels at the site…………….
The CDC EHO stated in a response dated 17th February 2010 that the DMP reflected good industry practice and subsequently CDC withdrew their objection regarding dust.
The EHO acts as the MPA's advisor on matters such as dust and noise and is consulted through the local authority (CDC) on environmental matters relating to planning applications. In this case the EHO has accepted that the DMP reflects good practice and that if there was to be a problem with dust CDC could take action as a statutory nuisance and that dust issues raised by the objectors can be dealt with through the implementation and operation of a DMP that have been approved by the MPA. If consent is granted for the proposal the DMP will be enforced via planning condition."
Dust: failure to take material consideration into account
Ground 3: Flooding
"A full hydrological and hydrogeological assessment of the proposal will be required to determine baseline conditions at the site, and outline the potential impact of the operation and proposed restoration on water resources and water dependant features."
"details of storage available within local ditches and lakes proposed to receive drained groundwater and any changes needed to accommodate additional water."
"We recognise that there are flooding problems in the locality and that residents are understandably concerned about this. The MPA may wish to seek a view on this from the Local Authority or County Council as the lead on land drainage matters. However we do not consider the proposed development will exacerbate these flooding issues, from either a ground or surface water perspective. Again, the conditions we have recommended allow for control of this matter."
"To address this the applicant will be required via condition to ensure that any submitted scheme to deal with surface water flows shall be designed to prevent any surface water being directed towards the County Ditches."
Breach of the obligation to advertise
"(a) that includes such of the information referred to in Part I of Schedule 4 as is reasonably required to assess the environmental effects of the development and which the applicant can, having regard in particular to current knowledge and methods of assessment, reasonably be expected to compile, but
(b) that includes at least the information referred to in Part II of Schedule 4."
"a description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects" (para 2); and
"the data required to identify and assess the main effects which the development is likely to have on the environment" (para. 3).
"19. – (1) Where the relevant planning authority, the Secretary of State or an inspector is dealing with an application or appeal in relation to which the applicant or appellant has submitted a statement which he refers to as an environmental statement for the purposes of these Regulations, and is of the opinion that the statement should contain additional information in order to be an environmental statement, they or he shall notify the applicant or appellant in writing accordingly, and the applicant or appellant shall provide that additional information; and such information provided by the applicant or appellant is referred to in these Regulations as "further information".
(2) Paragraphs (3) to (9) shall apply in relation to further information and any other information except so far as the further information and any other information is provided for the purposes of an inquiry or hearing held under the Act and the request for the further information made pursuant to paragraph (1) stated that it was to be provided for such purposes.
(3) The recipient of further information pursuant to paragraph (1) [or any other information] shall publish in a local newspaper circulating in the locality in which the land is situated a notice stating - …….
(d) that further information [or any other information] is available in relation to an environmental statement which has already been provided;
(e) that a copy of the further information [or any other information] [and of any statement referred to as an environmental statement for the purposes of these Regulations which relates to any planning permission or subsequent application] may be inspected by members of the public at all reasonable hours.
(f) an address in the locality in which land is situated at which the further information [or any other information] may be inspected and the latest date on which it will be available for inspection (being a date not less than 21 days later than the date on which the notice is published);
(g) an address (whether or not the same as that given pursuant to sub-paragraph (f) in the locality in which the land is situated at which copies of the further information [or any other information] may be obtained;"
"any other substantive information relating to the environmental statement and provided by the applicant or the appellant as the case may be."
"The Directive requires not merely that the planning authority should have the necessary information, but that it should have been obtained by means of a particular procedure, namely that of an EIA. And an essential element in this procedure is that what the Regulations call the "environmental statement" by the developer should have been "made available to the public" and that the public should have been "given the opportunity to express an opinion" in accordance with Article 6(2) of the Directive. ……………
The directly enforceable right of the citizen which is accorded by the Directive is not merely a right to a fully informed decision on the substantive issue. It must have been adopted on an appropriate basis and that requires the inclusive and democratic procedure prescribed by the Directive in which the public, however misguided or wrongheaded its views may be, is given an opportunity to express its opinion on the environmental issues. …………..
A court is therefore not entitled retrospectively to dispense with the requirement of an EIA on the ground that the outcome would have been the same or that the local planning authority or Secretary of State had all the information necessary to enable them to reach a proper decision on the environmental issues."
"A letter was sent out to all contributors on the 6th July 2010 (including the Claimant) informing them that the Officer's Committee Report was publicly available to be viewed from the 14th July 2010, i.e. 7 days before the determination of the application."
Mr Betty goes on to state that:
"All details on the ditch design and hydrology were put on public access before the 16th July 2010. A copy was sent to the Parish Council on the 20th July and a copy to the Claimant on the 19th July 2011. It is therefore incorrect to infer that the interested parties only saw them on the 20th July."
Deferment to a condition
"Third, the planning authority or the Inspector will have failed to comply with article 4(2) [of the Directive] if they attempt to leave over questions which relate to the significance of the impact on the environment, and the effectiveness of any mitigation. This is so because the scheme of the regulations giving effect to the Directive is to allow the public to have an opportunity to debate the environmental issues, and because it is for those considering whether consent to the development should be given to consider the impact and mitigation after that opportunity has been given. As Harrison J put it in [R v Cornwall County Council ex p Hardy [2001] Env LR 26]:-
"Mr Straker laid emphasis upon the fact that the local planning authority felt that, in imposing conditions, it had ensured that adequate powers would be available to it at the reserved matters stage. That, in my view, is no answer. At the reserved matters stage there are not the same statutory requirements for publicity and consultation. The environmental statement does not stand alone. Representations made by consultees are an important part of the environmental information which must be considered by the local planning authority before granting planning permission. Moreover, it is clear from the comprehensive list of likely significant effects in paragraph 2(c) of Schedule 3, and the reference to mitigation measures in paragraph 2(d), that it is intended that in accordance with the objectives of the Directive, the information contained in the environmental statement should be both comprehensive and systematic, so that a decision to grant planning permission is taken "in full knowledge" of the project's likely significant effects on the environment. If consideration of some of the environmental impacts and mitigation measures is effectively postponed until the reserved matters stage, the decision to grant planning permission would have been taken with only a partial rather than a "full knowledge" of the likely significant effects of the project. That is not to suggest that full knowledge requires an environmental information statement to contain every conceivable scrap of environmental information about a particular project. The Directive and the Assessment Regulations require likely significant effects to be assessed. It will be for the local planning authority to decide whether a particular effect is significant, but a decision to defer a description of a likely significant adverse effect and any measures to avoid, reduce or remedy it to a later stage would not be in accordance with the terms in Schedule 3, would conflict with the public's right to make an input into the environmental information and would therefore conflict with the underlying purpose of the Directive".
Fourth, (and here as it seems to me one reaches the most difficult area) it is certainly possible, consistent with the above principles, to leave the final details of for example a landscaping scheme to be clarified either in the context of a reserved matter where outline planning consent has been granted, or by virtue of a condition where full planning consent is being given as in the instant case."
"24. Smith was concerned with outline planning consent, but the same principles clearly apply to the grant of planning permission itself.
25. The authorities make it clear, therefore, that if the planning authority consider that a process or activity will have significant environmental effects then the ES needs to include the detailed information identified in schedule 4 to the regulations. It cannot leave the matter to be covered by conditions at a later stage. Even if that might otherwise be a satisfactory way of dealing with the problem, it frustrates the democratic purpose of the consultation process.
26. However, as the observations of Harrison J in the Hardy case make clear, it is a matter for the authority itself whether or not the development will have significant effects, and its decision on the point can only be challenged on traditional public law grounds. There is a screening system whereby the authority may give a decision whether an ES is required or not, and the regulations set out the material information which the developer has to provide if it seeks such an opinion (see regs 4, 5 and 7). In this case no screening opinion was required since the developer voluntarily provided the ES. But if the information is defective because it fails to deal with all significant environmental effects, even if it deals with some of them, then the ES will be inadequate and the consultation process will not reach to its full extent. "
"The Secretary of State has to make a practical judgment as to whether the project would be likely to have significant effects on the environment by virtue of factors such as its nature, size or location. The extent to which remedial measures are required to avoid significant effects on the environment, and the nature and complexity of such measures, will vary enormously but the Secretary of State is not as a matter of law required to ignore proposals for remedial measures included in the proposals before him when making his screening decision. In some cases the remedial measures will be modest in scope, or so plainly and easily achievable, that the Secretary of State can properly hold that the development project would not be likely to have significant effects on the environment even though, in the absence of the proposed remedial measures, it would be likely to have such effects. His decision is not in my judgment pre-determined either by the complexity of the project or by whether remedial measures are controversial though, in making the decision, the complexity of the project and of the proposed remedial measures may be important factors for consideration".
"1. The decision whether a process or activity has significant environmental effects is a matter for the judgment of the planning authority. In making that judgment it must have sufficient details of the nature of the development, of its impact on the environment and of any mitigating measures.
2. Equally, it is for the planning authority to decide whether it has sufficient information to enable it to make the relevant judgment. It need not have all available material provided it is satisfied that it has sufficient to enable a clear decision to be reached.
3. In making that determination, the planning authority can have regard to the mitigating measures provided that they are sufficiently specific, they are available and there is no real doubt about their effectiveness. However, the more sophisticated the mitigating measures and the more controversy there is about their efficacy, the more difficult it will be for the authority to reach a decision that the effects are not likely to be significant.
4. If the authority is left uncertain as to the effects, so that it is not sure whether they may be significant or not, it should either seek further information from the developer before reaching a conclusion, or if an ES has already been provided it should require a supplement to the ES which provides the necessary data and information. It cannot seek to regulate any future potential difficulties merely by the imposition of conditions.
5. The authority cannot dispense with the need for further information on the basis that it is not sure whether or not there are significant environmental effects, but that even if there are, other enforcement agencies will ensure that steps are taken to prevent improper pollution. However, it should assume that other agencies will act competently and it should not therefore anticipate problems or difficulties on the basis that those agencies may not do so."
(1) the EA only withdrew its objection on the basis that it considered that concerns relating to surface and groundwater flooding could be dealt with by the mitigation measures proposed, namely discharge inter alia into the County Ditch;(2) however, the EA was not responsible for the County Ditch, and explicitly advised GCC to consult on their suitability to received discharge. Specifically, the EA advised GCC to satisfy itself that a condition requiring mitigation measures which involved discharge into the County Ditch was acceptable;
(3) when GCC consulted the Senior Drainage Engineer, he made it absolutely clear that discharge into the County Ditch was not acceptable, and that the Interested Parties should look for "other ways of dealing" with the problem;
(4) In circumstances where the Senior Drainage Engineer had specifically ruled out an important component of the proposed mitigation scheme, GCC could not lawfully grant permission unless it was satisfied that some other form of mitigation was available and acceptable. At the very least, GCC should have reconsulted the EA in order to ascertain whether, in those circumstances, the EA's consultation response would remain the same. More appropriately, GCC should have sought further information from the Interested Parties as to what "other ways" of dealing with the problem were available. Once received, that information should have been the subject of proper public consultation. What GCC could not do was to leave the matter over to be dealt with under Condition 30.
(1) GCC was required to consult with the EA as to the likely significant effects of the proposal in the context of flood risks.(2) The EA properly considered the environmental information before issuing its consultation response.
(3) The EA was clear that it had sufficient environmental information (including proposed mitigation measures) on which to reach its conclusions.
(4) It was then a matter of planning judgment for GCC to consider the environmental information (and the EA assessment thereof) before reaching its decision.
(5) The EA's firm conclusion following its comprehensive assessment of the technical evidence and issues was that there was no justifiable basis for refusing the application on grounds of flood risk.
(6) GCC were required to consider, and entitled to rely upon, the EA conclusions and recommendations before making its determination.
(7) To have departed from the EA advice in their consultation response could have represented an unjustified reaction to the reasoned response of its statutory consultee in respect of flooding issues.
Failure to give reasons
"Where an EIA application is determined by a local planning authority, the authority shall—
(a) …
(c) make available for public inspection at the place where the appropriate register (or relevant section of that register) is kept a statement containing—
(i) the content of the decision and any conditions attached thereto;
(ii) the main reasons and considerations on which the decision is based [including, if relevant, information about the participation of the public]; and
(iii) a description, where necessary, of the main measures to avoid, reduce and, if possible, offset the major adverse effects of the development…"
"In considering the adequacy of reasons for the grant of permission there are a number of factors which seem to me to be relevant. The first is the difference in the language of the statutory requirement relating to reasons for the grant of planning permission compared to that relating to the reasons for refusal of planning permission. In the case of a refusal, the notice has to state clearly and precisely the full reasons for the refusal, whereas in the case of a grant the notice only has to include a summary of the reasons for the grant. The difference is stark and significant. It is for that reason that I reject the claimants' contention that the standard of reasons for a grant of permission should be the same as the standard of reasons for the refusal of permission.
Secondly, the statutory language requires a summary of the reasons for the grant of permission. It does not require a summary of the reasons for rejecting objections to the grant of permission.
Thirdly, a summary of reasons does not require a summary of reasons for reasons. In other words, it can be shortly stated in appropriate cases.
Fourthly, the adequacy of reasons for the grant of permission will depend on the circumstances of each case. The officer's report to committee will be a relevant consideration. If the officer's report recommended refusal and the members decided to grant permission, a fuller summary of reasons would be appropriate than would be the case where members had simply followed the officer's recommendation. In the latter case, a short summary may well be appropriate."
Conclusion