CO/11067/2007 |
QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
(SITTING AS A DEPUTY JUDGE OF THE QUEEN'S BENCH DIVISION)
____________________
RASTRUM LIMITED (1) MR R A BENGE (2) |
Claimants |
|
- and - |
||
SECRETARY OF STATE FOR COMMUNITIES AND LOCAL GOVERNMENT (1) ROTHER DISTRICT COUNCIL (2) |
Defendants |
____________________
Mr R A Benge, the Second Claimant, appeared in person
Paul Brown (instructed by The Treasury Solicitor) appeared for the First Defendant
Hearing dates: 24th and 25th November 2008
____________________
Crown Copyright ©
Sir George Newman :
Planning History
"1. The development hereby permitted must be begun either before the expiration of the period of five years beginning on the date hereof, or the expiration of two years beginning on the date of the notice of final approval of the reserved matters set out in condition 2 below or, in the case of approval on different dates, on the date of the notice of final approval of the last such matter to be approved, whichever is the later date.
2. An application for approval of detailed particulars of the following aspects of the development ("the reserved matters") shall be submitted to the District Council for determination by the County Council within the period of three years, beginning on the date of this outline permission and development must not be commenced until details have been approved:-
(a) Number, siting, design and materials of all buildings;
(b) Layout of the site including access, roads, footways, footpaths, parking for cars, boats, and commercial vehicles, and provision where practicable for separate circulation of private and heavy goods vehicles;
(c) Landscaping, including screening by fences, walls or other means, planting of trees, hedges and shrubs of appropriate species and grass, formation of banks, terraces, other earthworks and amenity features, paving;
(d) Foul and surface water drainage;"
These conditions and other conditions in connection with engineering and harbour works, finished ground levels and the amount of industrial floorspace were imposed to enable the County Planning Authority to regulate and control the proposed development.
The Commencement of Work and Events in the Ensuring Period to February 2004
"As you are aware the above mentioned planning permission expires on 31 January 1987.
As you are also aware our Client has already submitted an application to renew such permission on the same terms.
We now understand that the application will not be considered until the meeting on 26th February 1987, though we had been informed that it was to have gone before the meeting on 22nd January 1987. In these circumstances therefore and in order to comply with the requirement of the above mentioned consent, it has been decided to begin the development already approved. Our clients shall therefore, within the next 14 days commence to construct one or more of the road entrances into the site.
Unless we hear from you to the contrary, in our opinion (and we have so advised our Client) such work will, if commenced prior to 31st January 1987, preserve the validity of the above mentioned permission.
We have informed the East Sussex Council concerning the commencement of these road entrance works. Please let us know as a matter of urgency if you require any further information or other matters to be attended to."
That letter, as far as the court is aware, received no reply but there was ensuing correspondence.
1987
"It is noted that work has commenced to the industrial part of the above mentioned site.
In the recent past, considerable difficulty has been encountered with gipsies squatting on the land, also considerable dumping of rubbish. This was overcome by the erection of boundary fencing along the road frontage with a locked field gate at the access point.
Without prejudice to any future scheme of landscaping or fencing which the Council may require, I would suggest that, as a temporary measure, the site is adequately fenced and secured to prevent any recurrence of the above mentioned difficulties.
I should be pleased to receive your comments and indication of any action you are able to take."
"I refer to your letter of 8 December 1986 and various telephone conversations about this matter. In the event no application has been registered and the prospective applicants have ceased to seek to make an application. It is understood this follows from commencement of work upon the site prior to the expiry of the previous planning permission."
This prompted a letter dated 18th March 1987 from Needham & James:
"Would you please let us know whether or not you have accepted the works carried out as a specified operation pursuant to section 43 Town and Country Planning Act 1971."
To that letter the Planning Officer responded on 30th March 1987:
"I should point out that I have no delegated power to "accept" or to not accept the works on behalf of the Council as a specified operation pursuant to section 43 of the Town and Country Planning Act 1971. However, I am prepared to say that in my opinion the work undertaken appears to be an "operation in the course of laying out or constructing a road or part of a road" which is one of the specified operations."
"In the Rye edition of the Sussex Express dated 13 March 1987 allegations were made about Rother Council's handling of an application to renew a planning permission for a marina development at Rye Harbour Road, Rye Harbour, Icklesham.
The Council wishes to make it absolutely clear that there has been no attempt to prevent the renewal of the planning permission previously granted and strongly refutes the suggestion that there was any connection between the problems involving the making of a new application and the independent feasibility study.
The facts of the situation are:
(i) documents were submitted in an attempt to renew the permission;
(ii) these submissions were never registered as a valid planning application because of a series of technical and legal difficulties, none of which were the fault of the Council;
(iii) In the event the prospective applicants decided to implement the existing planning permission previously granted to the extent necessary to prevent it lapsing."
A copy was sent to the Chairman of the Planning Committee and the Chief Executive and Clerk of the Council.
"The restrictions on the sequence of the proposed development are contained in a legal agreement between Cornus Properties Limited (the original applicants) and the East Sussex County Council (which granted consent)".
Thereafter details were set out but the letter only purported to be a summary of part of a fairly complicated document. The letter concluded:
"Planning legislation does not require the Council to formally acknowledge or otherwise that a planning permission has been implemented. Therefore at this point the Council has not expressed a formal opinion. The site has been visited and photographs taken. It is my personal view that the work undertaken amounts to a "specified operation" for the purposes of section 43 of the Town and Country Planning Act 1971 (an operation marking the beginning of a development)".
"Since some work has been undertaken at the site pursuant to planning permission RR/84/0498, it is assumed that you do not now wish to proceed with your application dated 11th December 1986, and therefore in accordance with departmental practice I herewith return your forms and plans, whilst retaining one set for my records.
If however you do wish to have this application determined please return the documents together with your cheque for £5,300 in respect of the requisite fee, together with either a reiterated statement that you are the owners of the land together with some evidence thereof, or alternatively amended application forms advising that proper notice has been served".
This invitation to continue with an application for renewal was not taken up by the owner. In my judgment, the failure to take up the invitation presents well nigh insuperable difficulties in treating the District Council's conduct to this date as providing a basis for the creation of a legitimate expectation.
1989
"As a result of a determination by the County Council under previous legislation, valid planning permission exists for the development of the site with a marina, associated housing, industry and public facilities (Ref. RR/79/400(CM)). Legal agreements commit the developer of this proposal to provide a footway along Harbour Road and to phase the construction of the development. In particular it requires a substantial completion of the marina basin and associated engineering work before construction of housing commences. The permission was granted on the basis that the potential economic benefits of the scheme were likely to outweigh the identified environmental and ecological disadvantages."
The reference to legal agreements echoes the contents of the letter dated 6th April 1987 to the Director of Administration and Secretary to the Harbour of Rye Advisory Committee wherein a summary was given of a legal agreement between Cornus Properties Limited and the East Sussex County Council. The agreement or the agreements were not before the Inspector and are not before the court.
"Consideration of the 1987 proposal indicated that the decision, as to whether the proposal was acceptable was fairly balanced. Consideration of this similar marina scheme leads to the same conclusion. With the increased importance attached to ecological matters further outweighing any likely economic benefits arising from the proposed scheme, added to doubts about the quality and location, the balance has tipped the other way. However, it is not satisfactory to reject completely the use of the site for a marina in the absence of conclusions on potential sites in the area which may fulfil the strategic planning policies to provide a marina and/or moorings".
1990-1992
(i) RR/79/0400 – outline planning permission. Approved in 1981 with Section 52 Agreement covering (1) highway improvement, (2) phasing of development and (3) limits on industrial floorspace and various other obligations;(ii) RR/84/0498 (sometimes erroneously referred to as "… 0489) – approval of reserved matters;
(iii) RR/87/0749 – outline permission for houses/flats and other development. Delegated approval given subject to a legal agreement which was not completed;
(iv) RR/89/1392 – application not determined.
"Work commenced on the formation of a vehicular access to this site in order to "implement" the permission and keep it alive".
"There is a valid consent on the site for marina/housing and the industrial/warehousing and the current application seeks variation of the scheme….. In February 1988 you were prepared to agree to the increase of residential units …".
(1) Clause 10"On the 18 March 1981 the County Council granted outline planning permission in respect of the said application RR 79 0400 ("the 1981 permission") and on 31 January 1985 the District Council approved the matters reserved from the 1981 permission under reference RR 84 0498 ("the 1984 approval")";(2) Clause 11
"The 1981 permission and the 1984 approval were implemented to the extent only that works were carried out to an access which for the purposes of identification only …..".(3) The agreement, clause 3
"The District Council agrees to grant the application upon the execution of the Agreement by the other Parties hereto and this Agreement shall come into effect upon the grant of the application Provided that in the event that the Company does not implement the permission so granted by the carrying out of a material operation … nothing in this Agreement shall oblige the Company to carry out any works or (save as mentioned in clause 2) pay any monies to the County Council".Clause 2 obliged the Company to pay reasonable administrative costs.
(4) Clause 11
"The 1981 Agreement and the Section 278 Agreement are hereby revoked and shall be of no effect ….".(5) Clause 12
"The covenants obligations and other stipulations on the part of the Company shall be enforceable … against all persons deriving title to the land …".(6) Clause 15
"In the event of the District Council or the County Council resolving to make an order under section 97 of the 1990 Act revoking or notifying the 1981 permission and the 1984 approval the Company will not oppose the order and no claim whatsoever shall be made against the District Council or the County Council by the Company … and the Company hereby indemnifies the District Council and the County Council against all claims …".(7) Clause (h) of Schedule 2:
"Save for so much of the development as has been previously carried out [recital 11] no development whatsoever of the land shall be carried out in pursuance of the 1981 permission and the 1984 approval".
"The planning permission that had expired on that site for a marine and employment development was thought to have lapsed but the legal opinion appears to indicate that the permission is still valid …".
The Inspector's Decision Letter ("the DL")
"8. Area of disagreement. It is not agreed that the said access works did, as a matter of law, implement the planning permission".
This broad expression of the issue shed no light on the several issues of law which would be raised by the disagreement. Having adopted it as the correct formulation of the main issue, the Inspector added:
"… The onus is upon the appellants to demonstrate, on the balance of probabilities, that the access on to the highway was lawful at the time those works were carried out".
It has to be said that this was only part of the case. The application for a certificate of lawful use had not been made in relation to the access works carried out in 1987, but in relation to the proposed development of the site. Further, the issue as to whether the works were lawful at the time they were completed was not determinative of the appeal. Even if the works were unlawful when they were completed, if enforcement action in connection with the works was no longer possible, it was necessary to consider whether the works had to be regarded as lawful. Yet further, the application raised an issue as to whether Rastrum enjoyed the benefit of a substantive legitimate expectation that the proposed development had to be regarded as lawful and/or that for the District Council to act otherwise would amount to an abuse of power.
"I am of the opinion that on the narrow point before me, set out at paragraph 4 above, my reasoning does not need to go any further. However, much of the inquiry's time was spent on determining whether, based on the local planning authority's and other public bodies' actions and decisions over a long period after 31 January 1987, the appellants enjoyed a legitimate expectation that a lawful start had been made on the development, such that it could still be completed today without breaching planning control. This matter cannot be ignored and I address it below".
The Inspector concluded that he did not "need to go any further" because, having examined the conditions of the 1984 approval, he had concluded the works had been commenced unlawfully.
"… it should not be overlooked that several of these administrative decisions were taking place against a background of shifting judicial authority. The section 106 obligation, based on the earlier committee report, is almost contemporaneous with Whitley and some time would need to elapse before the full implications of this important Court of Appeal decision could be absorbed at local level. The Hart Aggregates judgment may have reined in some of the more extreme interpretations placed on Whitley by some planning authorities, but it post dates the local planning authority's apparent change of heart after its statement on what was in any event only an early version of an emerging unadopted Local Plan. I remain convinced that the Council's current interpretation of the legislation of when a start has been made, as interpreted through case law, is the correct one, for the reasons I have set out in paragraphs 5-17 inclusive above. In these circumstances, it would have been wrong for the Council to continue to argue that there was still a valid planning permission on the appeal site … if it thought that notion was fundamentally unsound".
I would not question the broad proposition that the planning authority was entitled to review its position where the law changed or developed but, in my judgment, a real issue arose as to whether, after it had entered into a section 106 Agreement on one basis, it was open to the District Council to change its view on the lawfulness of the commencement operations and to exercise its powers so as to refuse a certificate on a contradictory basis.
"23. The other matter on which I was addressed at considerable length was, on the authorities of R ex p Hammerton & London Underground Ltd v English Heritage, The Prince's Foundation, LB Tower Hamlets, LB Hackney & Railtrack plc (in administration) (Document 14), R ex p Prokopp v London Underground Ltd (Document 17) and Norris v First Secretary of State & Stoke-on-Trent City Council (Document 19), that it would be an abuse of power if the local planning authority took enforcement action at this juncture against development that was implemented as closely as possible to planning permissions RR/79/0400 and RR/84/0498. With the greatest respect to the submissions made on this point, there seems to me to be considerable confusion between the Council taking enforcement action, if development were to proceed with the form of operational development so far approved on this site, and whether going down that road would, in itself, constitute a breach of planning control, which is, in effect, all that I am being asked to consider that this juncture. It seems to me to be worth emphasising that my decision in this instance simply means that, were the local planning authority to invoke its discretionary enforcement powers at this time, the appellants would not be able to rely on the defence in any subsequent appeal that the resultant operational development, carried out in any attempt to implement these planning permissions, would be immune from enforcement action because it was lawful.
Conclusions
24. For the reasons given above, and having regard to all other matters raised, I conclude that the Council's refusal to grant a certificate of lawful use or development in respect of erection of industry/warehousing/wharfage, marine and waterside housing, yacht club and public facilities, in accordance with planning permissions RR/79/0400 and RR/84/0498, on land at The Saltings, Harbour Road, Rye Harbour, Icklesham, East Sussex, TN31 7TE, was well-founded and that the appeal should fail. Accordingly, I shall exercise the powers transferred to me in section 195(3) of the 1990 Act as amended."
Sections 191 and 192 Town and Country Planning Act 1990 (substituted with effect from July 27th 1992 by the Planning and Compensation Act 1991)
"On the other hand if you feel that Counsel's 2nd Opinion should prevail, then it follows that his view that … "the works were undoubtedly carried out" but they were in breach of conditions is correct. Then it follows that your Council is clearly out of time in which to enforce against these breaches, thus they are lawful and have implemented the consent".
I can see no reflection of this argument in the DL.
(1) Whether the proposed development can be lawfully implemented under the planning permission and approval RR/79/0400 and RR/84/0498 because the construction of the access road to the site commenced before 31st January 1987 amounted to a lawful operational development pursuant to the permission and approval because either:(a) the access road was not commenced in breach of condition; or(b) if it was commenced in breach of condition the operations are to be regarded as lawful because they are now immune from enforcement.
(2) Whether the proposed development can be lawfully implemented because the District Council or the County Council have created a legitimate expectation that the said permission and approval are extant;
(3) Whether the proposed development can be lawfully implemented because the District Council or the County Council have created a legitimate expectation that the said permission and approval had been validly implemented and was therefore extant (see Skeleton Argument of the First Defendant at paragraph 2);
(4) Whether it would be an abuse of power for the District Council to take enforcement action against the proposed development on the ground that there was no extant permission or approval.
The Law
"130.(8) However, if after the expiry of the five year period, it is possible to conclude that enforcement action is not lawfully possible, I see no reason why the development which cannot be enforced against should not be regarded as effective to commence development."
(1) Legitimate expectation is an established public law principle but:"The court should in my view be very slow to find that the principle of legitimate expectation operates so as to keep alive a planning permission that has on the face of it expired because there was no lawful commencement of the development within the time laid down; or, to pursue the matter to the conclusion sought by the claimant in this case, to find that it operates so as to require the grant of a certificate of lawful development in circumstances where on a proper analysis the development would be unlawful." (Richards J in Coghurst Wood Leisure Park Ltd. v Secretary of State for Transport, Local Government and the Regions [2003] JPL 206).(2) The proper application of planning law is not something which should be side stepped by means of a "bilateral agreement between the developer and the local planning authority" (Henry Boot Homes Ltd v Bassetlaw DC [2003] 1 P&CR 372).
(3) "The interests of third parties and the public in such matters also greatly reduce the potential for a legitimate expectation … to arise…. It is possible that circumstances might arise where it was clear that there was no third party or public interest in the matter and a court might take the view that a legitimate expectation could then arise from the local planning authority's conduct or representations…". (Henry Boot paragraphs 55-56).
The application of the law to the facts of this case
Legitimate Expectation and Abuse of Power
(1) Legitimate expectation is based on the concept of fairness expected from public bodies in the exercise of their statutory functions. The concept of abuse of power is a related principle of fairness which governs a public authority in its dealing with citizens.(2) There can be no legitimate expectation that a public body will confer a substantive benefit or extinguish an obligation when it has no power to do so.
(3) The courts should not, in the field of public law, introduce and apply principles derived from private law, unless expressly authorised by Parliament to do so, or if it is necessary to give effect to the purposes of the legislation.
(4) "The court should in my view be very slow to find that the principle of legitimate expectation operates so as to keep alive a planning permission that has on the face of it expired because there was no lawful commencement of the development within the time laid down; or, to pursue the matter to the conclusion sought by the claimant in this case to find that it operates so as to require the grant of a certificate of lawful development in circumstances where on a proper analysis the development would be unlawful" (Richards J (as he then was) in Coghurst).
(5) Statutory procedures and powers cannot be sidestepped or bypassed by private agreements between a developer and planning authority or by mere inaction on the part of a local authority. Planning law, controlling development in the public interest, cannot be implemented so as to exclude the public from being involved in decision making (see Henry Boot Homes v Bassetlaw DC [2003] 1 P & CR 23).
(6) In an area of law where the applicable principles are being developed and changed it must be open to a public authority to take account of changes in the law and where it would not be unfair and an abuse of power to do so, to "change its mind".
Application to the Facts
(1) The developer elected not to take up the invitation of the local authority to have the 1987 renewal application determined.(2) Views expressed prior to the above invitation were the views of the planning officer, not the Council. They were explicitly qualified.
(3) The views subsequently expressed which led up to the section 106 Agreement in 1992 reflect differing opinions against a changing legal context.
The 1992 Section 106 Agreement
(1) By entering into the section 106 Agreement the authorities were discharging a statutory function. It has to be said a statutory function in connection with an application for the same site and a similar but not identical development. Clearly the interests of the public had been adequately represented in connection with the application.(2) The local authorities intended to and did enter into fully binding legal obligations in connection with the development. The agreement imposed obligations on the developer and successors in title to the land, the subject of the development. The issue is whether the express basis upon which the parties to that agreement accepted their obligations can, notwithstanding that the Agreement was not implemented, be read as having given rise to any benefit or right upon which Rastrum can rely.
(3) Clause 11 of the Agreement refers to the implementation of the 1981 permission and the 1984 approval by works being carried out. The acts of "implementation" are not qualified as "purported" or "unlawful". Implementation could not have occurred unless the works had amounted to lawful "commencement". The clause constitutes a clear representation that the 1981 permission and 1984 approval had been lawfully commenced.
(4) Clause 15 constitutes a clear statement that the 1981 permission and the 1984 approval were capable of being the subject of a section 97 application revoking or modifying the same. The developer (and successors in title, see clause 12) agreed not to oppose such an application. The effect of the section 106 Agreement was that the developer agreed not to proceed on the 1981 permission and 1984 approval if the 1992 permission was implemented or if the 1981/84 permission was revoked.
(5) In my judgment, the local authorities clearly accepted legal obligations and conducted themselves upon the basis that the 1981/84 permission was extant. A third party coming to the Agreement, like Rastrum, would not have been left in doubt that in 1992, at the date of the section 106 Agreement, the Agreement constituted the authorities' publicly stated position in connection with the 1981/84 permission.
"(2) If, on an application under this section, the local planning authority are provided with information satisfying them that the use or operations described in the application would be lawful if instituted or begun at the time of the application, they shall issue a certificate to that effect: and in any other case they shall refuse the application".
(i) the development would take place unlawfully and there would be no means of enforcing the terms of the 1981/84 permission;(ii) consequently the public interest would not be adequately protected.
(1) a case can be made for a local authority to be held to public statements made by it in the course of the discharge of its statutory functions;(2) whilst a statement may be made upon the basis of a view of the prevailing law, which subsequently the local authority may have cause to doubt was the correct view, a citizen is entitled to some certainty being attached to a public statement which is made in the exercise of a statutory function;
(3) where the balance of fairness in favour of the claimant is overwhelming, a local authority may be held to its previous position.