QUEEN'S BENCH DIVISION
THE ADMINISTRATIVE COURT
Strand London WC2 |
||
B e f o r e :
____________________
THE QUEEN ON THE APPLICATION OF WILSDON | (APPELLANT) | |
-v- | ||
(1)FIRST SECRETARY OF STATE | ||
(2)TEWKESBURY BOROUGH COUNCIL | (RESPONDENTS) |
____________________
WordWave International Limited
A Merrill Communications Company
Smith Bernal Wordwave Limited
190 Fleet Street London EC4A 2AG
Tel No: 020 7404 1400 Fax No: 020 7831 8838
(Official Shorthand Writers to the Court)
MISS K OLLEY (instructed by the Treasury Solicitor) appeared on behalf of the FIRST RESPONDENT
The SECOND RESPONDENT did not attend and was not represented
____________________
Crown Copyright ©
"Without planning permission --
(a) the construction of a building in the position shown coloured blue on the attached plan;
(b) the excavation of an earth bank and the formation of a hard surface in the approximate position crosshatched black on the attached plan;
(c) the construction of a retaining wall in the approximate position indicated by a green line on the attached plan."
In summary, the requirements of the notice were to demolish the building and the retaining wall and to regrade the earth bank and reinstate all the land to its condition before the unauthorised development took place.
"(5) The appeal site is elevated above the land to its west. It consists of a level platform recently excavated into the natural hillside, which sloped from the south-east down to the north and north-west; there is a retaining wall some 1 to 1.5m high on the southern and eastern edges of the platform. In the platform's north-western section is a large modern building, essentially built round a metal frame and with a concrete slab floor. It has cavity walls, with an outer skin of coursed artificial stone and an inner skin of concrete blocks. The roof is of corrugated asbestos sheets. The building measures some 14m long and 8.3m wide and at its front it is about 3.5m high to the eaves and 4.8m to the ridge. The land's surface rises up next to the southern wall, so that at the rear the eaves are about 2m above the surface. The southern retaining wall is about 4.3m from the building and the distance to the eastern is some 10m. The areas between the retaining walls and the building are surfaced in hardcore or similar material. On the north-easter corner, behind the building, I saw a small pile of fence posts, netting and drainage pipes. The forecourt area, some 10m deep, in front of the building was unsurfaced.
(6) There is a metal roller-shuttered door, 3.1m wide and 2.7m tall, in the northern part of the building's front elevation; next to it is an arched window. Access is also possible through a metal pedestrian door in the western section of the southern elevation. To its east is a barred window, which I saw was blocked by sheeting on its inside. Inside the building internal blockwork walls separate off two compartments in the south-western corner. One housed a chemical toilet and the other, lit by the window on the front elevation, seemed to be a mess room and contained a table, three chairs, cupboards, kitchen units and a gas-powered stove. Just outside this room, in the main part of the building, was a fridge.
(7) In the north-eastern corner of the main part of the building was a large lockable metal storage container with a small tracked loader within it. Inside the container were also sets of shelves with various items of equipment, and a large toolbox. There was a ladder on the container's top. Just inside the roller shutter door I saw an 8 tonne tracked digger and next to it a site dumper; the digger was moved outside during my visit. There were several workbenches of varying degrees of permanence on the southern wall under the barred window and elsewhere on the concrete floor. Behind the dumper, and next to the storage container, was a large pile of timber, and near the building's rear wall were several large pipes, lengths of timber and a lawn mower. Apart from a pedestrian door and a few window units I saw no other building materials."
"It bears little resemblance to that actually built, being narrower and having an agricultural appearance, with timber-clad walls above a concrete blockwork plinth."
The Inspector noted that a photograph showed that the building had been completed by July 2005 and the Council's statement, which had been sent on 24th August 2005, had said that at that time no work had begun on any log cabin. By the time the Inspector inspected the site in November 2005, he saw that one of the log cabins was under construction:
"Its walls were up, windows glazed and the roof structure built but not yet clad. I could hear construction work being carried on inside."
"Under this ground [the appellant] claims that there is no breach because the building is intended to be a temporary one, to store materials and equipment securely during the period of the development on the adjoining land. He says that it will be removed once the development is completed."
In paragraph 12, the Inspector said this:
"The Town and Country Planning (General Permitted Development) Order 1995 (GPDO) identifies those developments that are defined as 'permitted development' and so can be carried out without the submission of the specific planning application. Under the heading 'Temporary Buildings and Uses', Class A of Part 4 of Schedule 2 includes 'the provision on land of buildings . . . required temporarily in connection with and for the duration of operations being or to be carried out on . . . that land or on land adjoining that land'. The class is subject to a condition that the building in question shall be removed when the operations have been carried out."
The Inspector continued in paragraph 13 of the decision letter by saying:
"Were it not for the adjacent development there would be no dispute that there has been a breach of planning control. There also appears no dispute that the building is currently used to store items in connection with the adjacent approved development. The appellant says that it is intended to remain for the duration of the authorised operations, which he estimates will take 2 to 3 years. However, it has already been there for about a year and it seems to me that work has taken place on only one of the approved buildings. The picture given in his statement is of a 'one man' builder, proceeding slowly with the development. It seems to me that the essence of a 'temporary building' which is 'required temporarily' is its short term nature, and the GPDO clearly seeks to exempt transitory buildings from planning control. I do not consider that it is intended to permit the retention of buildings of permanent construction for an inordinate period while a large development proceeds slowly."
"14. By no stretch of the imagination could this building be regarded as being of temporary construction; it is substantial and the views of some local residents that it took 7 months for excavation and building works have not been challenged. The appellant says that he intends to remove it and the associated works when the adjacent development is completed, as required by the GPDO but, in view of the building's size and nature and of the scale of the works which would be needed, I am not persuaded that this is a realistic intention.
15. Whether a building is required temporarily in terms of Part 4 of the GPDO is a matter of fact and degree. It is not clear to me whether the Council accepted that the one shown in the appellant's plan of January 2005 would be permitted development. However, in my opinion the appeal building, in terms both of its construction and likely period of existence is not a 'temporary building' and so does not fall within the description of those matters which are the subject of Part 4.
16. The appellant argues that his site was subject to burglaries after work started, with security units forced open. He says the building is needed to protect materials and equipment. I agree with him that the doorway is large enough to permit equipment to be kept inside, and I saw evidence of damage around the pedestrian door consistent with an attempted forced entry. However, I find it surprising that a building of such substantial construction would be built so far from the development it is supposed to serve, and not closer to the site access, where surveillance would be better, additional access works would not be needed and major earthworks would not be required to accommodate it. In my experience it is not unusual to keep vehicles, equipment and materials on a building site with, if necessary, protective and deterrent measures such as security cameras, alarms or vehicle immobilisers. I also noted the substantial metal gates at the entrance, and lockable site gates in front of them, which should provide a significant measure of security. In my opinion it is unnecessary to have such a substantial building of permanent construction to provide security.
17. I appreciate that the slow rate of this development may involve specialist equipment being on site for a considerable period but I see no reason why, for example, ground works requiring the stored equipment could not be carried out at the one time rather than piecemeal, and so reduce the time vulnerable items have to stay on the site. I saw some materials stored elsewhere on the site and I see no reason why others could not be, or be kept in the building under construction.
18. Even if I am wrong in my finding that the building is not 'temporary' in terms of Part 4, the word 'required' implies an element of being reasonably considered as essential rather than what a developer may consider desirable or convenient. However, I am satisfied that there are other means of providing any security needed and I conclude that as a matter of fact and degree the building is not 'required' for the carrying out of the adjacent development."
"Skerritts demonstrates that an insubstantial structure can still be permanent enough to be a 'building' and so subject to planning control. To my mind the present case is at the other end of the scale -- whether a substantial building of unquestionably permanent construction should nevertheless be considered as temporary in terms of Part 4 of the GPDO. In all the circumstances I consider that this building cannot be so regarded."
"I am not persuaded that more elaborate security measures than normally found on rural building sites are needed here."
"I do not consider that it [ie, Class A, Part 4] is intended to permit the retention of buildings of permanent construction for an inordinate period while a large development proceeds slowly."
It is submitted that it would have been open to introduce a time limit into Class A but Parliament chose not to do so.
"In the case of planning control, it is apparent from the Town and Country Planning (General Permitted Development) Order 1995, Schedule 2 Part 4, that a building may be sufficiently permanent for the purpose of planning control and yet be temporary so as to come within the exemption for which that order provides." (See page 14).
Whilst of course it is possible that a landowner would wish to erect a permanent building to serve a temporary purpose, as a matter of common sense, absent any other explanation, the larger and more permanent the building in question the less likely it is to be genuinely "required temporarily" in connection with the carrying out of development on the land or on adjoining land. Common sense has some role to play in planning control and the proposition that a permanent building may fall within Class A in Part 4, whilst in principle correct, raises the obvious question: why would anyone go to the time, trouble and expense of erecting a permanent structure if it is required only temporarily? In any particular case there may be a sensible explanation but it would be necessary to look at the facts of each case to see whether or not such an explanation had been provided. It is not unreasonable to adopt, as a starting point, the proposition that a landowner will not usually erect a permanent building if it is merely required temporarily. Similarly, the length of time taken to construct the building and the length of time that it has been and is likely to be in situ must also be relevant considerations. Perhaps not determinative in the manner indicated in the Inspector's paragraph 15, but highly relevant.
"It is clearly established that permanence has some part to play in the question of whether the operation is a building operation, and whether the product of the operation is a building or not. But it seems to me that it does not depend upon the intention of the erector as to whether it is a building operation or a building. Moreover, that permanence does not necessarily connote that the state of affairs is to continue forever or indefinitely. It is a matter of degree between the temporary and the everlasting." (Page 114).
While those observations were wholly apt in the circumstances of the Skerritts case, as the Inspector rightly pointed out the present case is very much at the other end of the scale. The question for the Inspector was whether a substantial building of unquestionably permanent construction should nevertheless be considered as temporary in terms of Class A in Part 4 of the GPDO (see paragraph 22 of the decision letter).
"In my opinion it is unnecessary to have such a substantial building of permanent construction to provide security."
That conclusion is explained further in paragraph 17 of the decision letter. One then has paragraph 18, which I accept contains a reference to "essential", but equally the Inspector concludes as a matter of fact and degree that the building is not required for the carrying out of the adjacent development. If one is in any doubt as to the Inspector's approach, one can then go to paragraph 33 where the Inspector makes it perfectly clear that he was not persuaded that more elaborate security measures than those normally found on rural building sites were needed on this particular site. Thus, on any basis, the only reasonable conclusion open to the Inspector was that this building was not required temporarily within Class A in Part 4.