QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
Between:
The Alliance Spring Co Ltd & Others
- and -
The First Secretary of State
____________________
The Alliance Spring Co Ltd & Others |
Claimant |
|
- and - |
||
The First Secretary of State |
Defendant |
____________________
Mr Christopher Katkowski Q.C. & Ms Karen McHugh (instructed by Islington Council) for the First Interested Party
Ms Karen McHugh (instructed by David Cooper & Co) for Arsenal Football Club (Second Interested Party)
____________________
Crown Copyright ©
Mr Justice Collins:
1. This case concerns a major development resulting from Arsenal Football Club's (AFC) need for a stadium with increased capacity and a desire that that stadium should continue to be in Islington. A result of the Taylor recommendations following the Hillsborough disaster was that football stadia should provide seating for all spectators. This resulted in the capacity for the existing stadium in Highbury being reduced to 35,000. AFC is a major player in the Premier league and needs to accommodate more spectators if it is to be able to finance the enormous sums which now have to be paid to attract the top quality players to enable it to maintain its position in the league. The new stadium will have a capacity of about 60,000.
"The matter now before me is brought by only two residents. The other claimants have fallen by the wayside. The consolidated grounds in part were not really pursued, notably to the extent that they raised human rights grounds, which were misconceived and unsupported by any evidence. A number of additional grounds were sought to be raised. The grounds raised were refined and altered in the skeleton argument, and before me, from those set out in the claimants' skeleton argument. No possible point or permutation of a point has been overlooked by counsel for the claimants. I hope I do justice to the variety and ingenuity of his multifaceted arguments. They have put the decision-making process of the London Borough of Islington through a demanding legal audit as if a roving commission were being conducted on behalf of all objectors. I have examined all these points. In the end I have concluded that these applications fail. Most of the points raised are indeed unarguable. "
An attempt to persuade the Court of Appeal to grant permission to appeal failed.
5. Since the planning permissions were for a major redevelopment which would necessarily involve the demolition of a number of buildings not all of which were owned by the Council or AFC, a Compulsory Purchase Order was likely to be needed. On 17 June 2002 the Council made such an order under s.226 of the 1990 Act. This provides, so far as material, as follows: -
"(1) A local authority … shall … have power to acquire compulsorily any land in their area which –
(a) is suitable for and required in order to secure the carrying out of development, re-development or improvement …
(2) A local authority and the Secretary of State in considering for the purposes of subsection (1)(a) whether land is suitable for development, re-development or improvement shall have regard –
(a) to the provisions of the development plan, so far as material,
(b) to whether planning permission for any development on the land is in force; and
(c) to any other considerations which would be material for the purposes of determining an application for planning permission for development on the land.
(4) it is immaterial by whom the local authority propose that any activity or purpose mentioned in subsection (1) … should be undertaken or achieved (and in particular the local authority need not propose to undertake any activity or to achieve that purpose themselves)."
The Order, which is entitled 'London Borough of Islington (Ashburton Grove and Lough Road, Islington) Compulsory Purchase Order 2002', covered 134 plots of land. It was stated to provide for "the purchase for the purposes of securing the carrying out of development, redevelopment or improvement as a mixed use scheme including a 60,000 capacity stadium, an education 'learning centre', a replacement Arsenal Sports and Community Centre, a replacement waste and recycling centre, new and refurbished houses, new live-work units, new general business space, new shops, financial services and cafes/restaurants, new leisure space, two new gym/health clubs, two new nurseries, four new community health facilities and new publicly accessible open space of the land and new rights described in the Schedule hereto".
6. There were a considerable number of objectors to the Order and so an inquiry was held before an Inspector. It sat for 14 days between 14th January and 20th February 2003. At a pre-inquiry meeting, it was agreed that it should proceed in two parts, the first to consider objections in principle to the order, the second to consider matters specific to particular plots. By the time the inquiry commenced, 24 of 33 statutory objections had been withdrawn. The only effective remaining objections related to plots in Queensland Road, which was at the south end of the Ashburton Grove site and in which there were a number of businesses. The statutory objectors carried on businesses there and were concerned that it would be impossible to find suitable alternative premises and that compensation payable under the Act would be insufficient to enable them to set up or maintain their businesses elsewhere.
" If any person aggrieved by a compulsory purchase order desires to question the validity thereof, or if any provision contained therein on the ground that the authorisation of a compulsory purchase thereby granted is not empowered to be granted under this Act or any such enactment as is mentioned in section 1(1) of this Act [which includes the 1990 Act], he may make an application to the High Court".
"This wide power may be used to acquire land for a variety of planning purposes such as a town centre redevelopment or other comprehensive regeneration scheme for which the authority wishes to assemble a number of individual properties or areas of land.
But it is always necessary for the acquiring authority to be sure that the purposes for which it is making a CPO sufficiently justify interfering with the human rights of those with an interest in the land affected. In this case, the five claimants with businesses in Queensland Road will clearly suffer an interference with their rights under Article 1 of the First Protocol to the European Convention on Human Rights, which deals with the protection of property. It reads, so far as material: -
"Every natural or legal person is entitled to the peaceful enjoyment of his possessions. No-one shall be deprived of his possessions except in the public interest and subject to the conditions provided for by law and by the general principles of international law …"
Compulsory purchase powers are granted in the public interest and so, provided they are exercised in accordance with the law and in a properly proportionate fashion, will not constitute a breach of the Article.
"The land that the Council now seek to acquire compulsorily is suitable for this stadium led scheme of redevelopment to the extent that planning permissions have been granted for the proposals. That land is required, if the scheme is to proceed through to completion, but I am not persuaded that there is a compelling case in the public interest that the CPO should be confirmed. There are clear conflicts with the development plan's requirements and little could be achieved by way of effective regeneration, particularly for those areas that are most in need".
There was an issue whether the proposals were financially viable. The Inspector was concerned that insufficient information had been given to establish viability, but was persuaded that it was likely that the scheme would be deliverable. He considered the need for the Queensland Road properties since the Council had decided to permit the new stadium to be constructed. In paragraphs 757 and 758 he said this: -
"Other plot Specific objections … all relate to land that is associated with those parts of the scheme that would be centred around the realigned Queensland Road. In some cases plots could be omitted from the CPO without affecting the stadium or access to it. Certainly the scheme could be modified to alter the access arrangements and to exclude some or all of the development that is proposed to the south of the podium (sic). However, if existing buildings were to be retained on those plots, they would appear in stark contrast to the new development. This would undermine the architectural quality of the scheme and would fundamentally upset the urban composition on this part of the site. As I have already indicated, the development to the south of Queensland Road is clearly needed to achieve a successful transition from the stadium to the surrounding area.
758. The location of the Ashburton Grove site is highly valued by objectors who operate businesses from there. They are worried about the consequences of having to move away and, for some, the practicalities of achieving the move without undue harm to the businesses raise particular challenges. I have no doubt that suitable relocation premises could be found, albeit in another part of the city. However, AFC's early efforts in this respect have caused unnecessary delays, in certain cases, and I am not convinced that all businesses could be successfully relocated before the Queensland Road part of the scheme commences in 2005 … Nevertheless, these considerations, together with those that relate to the scope of compensation payments, do not persuade me that the redevelopment of the Ashburton Grove site should be reduced in extent if the scheme were to proceed, given the design considerations that I have referred to".
"689. The Council's approach to regeneration of the area, in and around the CPO sites, appears to be opportunistic and weakened by its failure to engage the local community. Their Regeneration Strategy requires regeneration activity to be planned, to achieve defined objectives, with active involvement at all levels by the people who live and work in these areas. Indeed the Unitary Development Plan makes it clear that the Council will seek such involvement. Extensive consultation on the planning aspects of what is being proposed is no substitute for canvassing views on what is required.
690. Opportunism in matters concerning regeneration is understandable and not necessarily wrong. However, in the absence of objectives that are informed by local needs, there is a danger that the benefits to the community will be overly constrained by private interests.
691. The AFC scheme represents the largest development proposal ever made in the Borough. A critical requirement here is to secure a proper balance between the public and private interests. AFC want to fund and construct a new stadium whereas the Council are hoping to secure regeneration across a wide tract of north London. Indeed the Council have consistently refuted suggestions, that the scheme is for AFC's benefit, by pointing out that all their actions have been predicted on the basis that the scheme would deliver a comprehensive scheme of regeneration.
692. The question of whether the scheme is likely to be completed is a matter that I shall return to. The Council maintain that development at Drayton Park and residential development at Lough Road are likely to proceed in any event. They also point out that the effects of losing the Queensland Road element of the scheme would be severe and that planning permission for the overall scheme is indivisible. Certainly the need to obtain control over properties in Queensland Road, and thereby secure the overall scheme, is the main reason advanced for confirmation of the CPO. It was therefore surprising to learn towards the end of the inquiry that, shortly after the proceedings closed, the Council would sell AFC sufficient land to enable the stadium to be built. This willingness to allow the stadium to proceed, in absence of any certainty that it would form part of the publicly promoted comprehensive scheme of redevelopment, does not strengthen the Council's case and is not adequately explained by their unsubstantiated analysis of the risks involved.
693. These considerations undermine the Council's stated commitment to effective regeneration and are consistent with objectors' claims that regeneration arguments have been retrofitted to what is, in effect, simply a redevelopment scheme. This has particular significance in the light if the Council's acknowledgement that they would need to manage the process if successful regeneration is to be achieved.
696. I am led to the following conclusions. The main justification for the use of compulsory purchase powers here would be to achieve a comprehensive regeneration scheme. Confirmation of the Compulsory Purchase Order would overcome any outstanding uncertainties regarding title to the land, but the scheme of development that it would facilitate was not conceived with a view to effective regeneration. In any event successful regeneration would not flow automatically from completion of the scheme; it would require the Council's active involvement. However the Council's stated commitment to regeneration and to achieving a comprehensive scheme is undermined by their failure to adhere to their own Regeneration Strategy and by their willingness to allow the proposed new Arsenal stadium to be built, irrespective of whether the Order is confirmed".
He was not persuaded that the scheme would have the effect that the Council was putting forward and, as was submitted to me, there were unsatisfactory elements in it. For example, a waste recycling centre and a stadium were hardly desirable neighbours for residential accommodation, affordable housing was to be allocated in the least desirable parts of the site, and there would be a loss of areas of industrial and business use which would be detrimental overall.
"In considering whether to confirm the CPO the Secretary of State has judged the desirability of the overall scheme not solely on the basis that there is a planning approval, but also whether there is a compelling case in the public interest to justify acquiring private interests. Whilst the fact that planning permission for the proposals has been granted does not automatically mean that the CPO should be confirmed, the Secretary of State is satisfied that the provisions of s.226(1) and (2) have been met and that it is in the public interest that the development should proceed."
"The Secretary of State agrees with the Inspector's conclusions that the desire to bolster the Club's chances of future success is not a sound reason for use of compulsory purchase powers, but that a more compelling reason to confirm the CPO is the need to secure a comprehensive regeneration scheme. In this respect he also agrees with the Inspector that parts of the Borough are in need of regeneration and accepts the Inspector's conclusions that the Lough Road site and its surroundings are more in need than the area which includes the Ashburton Grove site. The proposals represent an opportunity to regenerate two of the Borough's poorest areas – the Lough Road site has been identified as an Area of Opportunity since at least 1988 and although much of Queensland Road is in use, many of its buildings are outdated and in poor condition".
Further on in the same paragraph he said: -
"He also notes that the Council originally sought to justify the use of compulsory purchase powers on the basis that this would help to secure AFC's long term future in the Borough and that the scheme proposed would bring regeneration benefits. However, the main justification presented to the inquiry was that the CPO was needed to achieve a comprehensive regeneration scheme. The Secretary of State considers that the Council's actions have all been predicated on the basis of a comprehensive scheme".
He concluded that the benefits were indeed such as to satisfy him that a compelling case had been established.