Case No CO/1562/99
IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION
CROWN OFFICE LIST
At Liverpool
Friday 14 April 2000
In 1992 the then Government adopted a policy to upgrade the A1 Trunk Road to
motorway standard. One consequence of this was that it was necessary to
consider whether to develop motorway service areas (MSAs) to serve the motorway
once the road was upgraded. One of the proposed MSAs is in the Harrogate
district on a site north of Ferrybridge. The local planning authority there is
the Harrogate Borough Council. A number of applications for planning permission
in respect of an outline application were made to the Council. They related to
four different areas. The Applicant Macgay sought permission in respect of a
site within the north east quadrant of the proposed Kirk Deighton interchange
of the A1(M) motorway, on the outskirts of Wetherby. The Third Respondent, whom
I shall call "Heather Ive" made an application in respect of a site at Kirby
Hill; the Fourth Respondent ("Harrison") in respect of a site at Arkendale; and
the Fifth Respondent ("Swayfields") in respect of a site at Allerton. The
Council favoured the site at Allerton and, against the advice of its planning
officer, who favoured Kirk Deighton, it selected Allerton for allocation in the
deposit version of the local plan, whilst also resolving to give it outline
planning permission. That application was called in by the Secretary of State.
Macgay was refused planning permission by the Council in February 1995, and it
appealed to the Secretary of State. In respect of the other two applications,
no decision had been made within the specified time and accordingly they also
appealed to the Secretary of State. The result was that the Secretary of State
had to determine four applications. He appointed an inspector to carry out a
public inquiry, and subsequently confirmed the recommendation of the Inspector
by a letter dated 15 March 1999. This was that conditional planning consent
should be given to Heather Ive in relation to the site at Kirby Hill.
Two of the applicants were dissatisfied with this decision, as was the
Council. They all made applications pursuant to section 288 of the Town and
Country Planning Act 1990 to quash the Secretary of State's decision. One of
the applicants, Harrisons, withdrew its application shortly before the hearing,
but the other two parties maintained their challenges. Before the Inspector,
the Council had run arguments supporting the Allerton case, but it was no
longer pursuing that line before me. Indeed, it was lending its weight in
support of Macgay, although its submissions adopted a narrower focus.
Since in his decision the Secretary of State relied upon both the
recommendation and the reasons of the Inspector, it is necessary to examine the
Inspector's analysis in some detail in order to understand the nature of the
legal challenge.
The Inspector's Report
This was a detailed and very carefully constructed report. The
Inspector compared the relative merits of the various sites which all parties
accept he was obliged to do in accordance with the Court of Appeal decision in
Secretary of State for the Environment v Edwards[1994]1
PLR62. He prefaced his conclusions by setting out what he considered to be
the main considerations to all four proposals. In paragraph 14.1 he described
these as follows:
"In my opinion, the main considerations common to all 4 of the proposals
before the Inquiry in varying degrees are:
(a) the need for an MSA on the Wetherby-Dishforth section of the A1(M) and the
extent to which each proposal would meet the need in terms including location,
timing and convenience of access.
(b) having due regard to the Development Plan, the emerging Local Plan and
Government planning policies, the degree of harm which each particular MSA
proposal would cause in terms of:-
(i) encroachment in the countryside;
(ii) landscape and visual impact;
(iii) ecology;
(iv) agriculture;
(v) highways and traffic effects.
(c) in the case of each of the Inquiry proposals, whether or not there may be
an alternative site available which would meet the need while causing less
harm."
Broadly, therefore, he was concerned to determine whether there was a need and,
if so, how that need should be met whilst causing the least harm to planning
and environmental interests.
There was one particular feature of the Macgay application which, as we shall
see, proved to be crucial to the outcome of the Inquiry. It was that their
application was contingent on a stretch of the motorway actually being
constructed; their site between Wetherby and Walshford was not on the current
trunk road at all. The position with respect to the proposed extension was
described by the Inspector as follows:
"The HAg's (Highways Agency's) letter dated 8 October 1997 (HBC30) states that
Orders for the Walshford-Wetherby scheme have been fully made (albeit on hold
pending the outcome of the review) with Notices to Enter intended to be served
in October 1997. Nevertheless in their letter dated 2 October (CD12) the
HAg's say "there is no certainty over whether a scheme will go ahead and in
what form". In a further letter dated 20 October 1997 (CD10) The HAg say
"Assuming the scheme is given the go ahead in the review, that funding is made
available and design work recommences in June 1998, the earliest start of works
date is 2001 with the road open in the financial year 2003/4".
I now turn to consider the approach of the Inspector to the two issues that he
posed to himself, namely establishing the need, and meeting the need.
Establishing the need.
The Inspector observed that in an earlier inquiry in 1994 an inspector had
concluded that the need for an MSA was "beyond dispute". In that context the
Inspector considered afresh whether there was a need, analysing that issue by
having regard to the changes since the 1994 inquiry, the services provided by
existing roadside services, and the proximity to other substantial services
located on the trunk road (which he termed the "spacing" issue). He noted that
the parties' views on the significance to be given to the existing services
varied considerably. Some thought that they should be discounted entirely when
assessing need, although both applicants felt that weight should be given to
those services, concluding as a consequence that the need was "qualitative"
rather than "quantitative". By this they meant that the need was for better
quality services but not because there were insufficient places to stop. The
significance of this, so far as Macgay was concerned, was that it meant that
the need "carries with it no urgency" (para. 8.25). The Inspector's conclusions
on the impact of the existing services to the question of need were as
follows:
"......The composite A1(M)/A1(T) is clearly a high status road of national
strategic importance and I fully endorse the views expressed in the Council's
evidence (9.29) and by HIA (9.32) that the needs of its users for modern,
comprehensive, round-the-clock facilities are the same on both the trunk road
and motorway sections. Accordingly I find little comfort in Macgay's
unchallenged point that the existing facilities to the north of Dishforth, when
aggregated, provide parking for cars well in excess of RC1/94 requirements.
It cannot be right, as we approach the 21st century, for users of
the composite A1 route to have to rely "for the foreseeable future" on
fragmented partial service with questionable access arrangements.
In the light of the foregoing observations I conclude that the existing partial
services should be excluded from the gapping matrices in assessing the need for
an MSA on spacing grounds, and that it would be unreasonable to reject any of
the proposed MSAs at this Inquiry solely on the grounds of proximity to
existing partial services."
In my judgment the Inspector does not here reach any specific conclusion about
the extent to which the need is quantitative or qualitative; and it was not
strictly necessary for him to do so. He does, however, seem to be accepting
that it is at least in part qualitative, but that this is not a justification
for doing nothing "for the foreseeable future".
Overall, the Inspector concluded that "on balance...the need for MSA provision
remains compelling".
Meeting the need
When considering the question how the need should be met, the Inspector
analysed the issue under four headings which he identified as locational
considerations; the internal layout of each scheme; whether the proposed
schemes were "on-line" or "off-line" i.e. how far they were from the trunk road
itself; and timing. In addition to these factors he then considered the
potential harm which each site would cause to planning and environmental
considerations.
The Inspector's conclusions on the timing issue are critical in this case.
Having expressed the opinion, contrary to the submissions of Macgay, that all
the parties save for Macgay would, if granted planning permission, be able to
take it up without undue delay, he commented on Macgay's position as
follows:
"However, the situation with regard to Kirk Deighton, well documented in the
Cases for Macgay's competitors and the Council is totally different. The
HAg's draft programme showing an earliest opening date of October 2003 for Kirk
Deighton MSA, could only be achieved if all the following requirements
were to be met;
(a) approval of the Wetherby-Walshford upgrading scheme in the current Roads
Review
(b) the design of the scheme, including the proposed Kirk Deighton
interchange, remaining in its present form;
(b) detailed design work starting in Summer 1998;
(c) no delay in funding for the scheme.
Even if all 4 of above requirements were to be met, Kirk Deighton MSA would not
be available to the travelling public until at least 3 to 4 years later than
any of the other proposals in this Inquiry and completion of the M1-A1 Link.
This is a substantial length of time to expect users of the composite A1(M)/A1
to continue relying on the fragmented partial services which characterise the
route. In any case, this is clearly a hypothetical and optimistic scenario
which I examine further below.
It is likely that the outcome of (a) will be known prior to the Secretary of
State's decision in this Inquiry. If that outcome is that the
Wetherby-Walshford scheme is deferred or dropped from the National Roads
Programme, the Macgay's application would have to be refused for that reason
alone. If the scheme is approved, then possibly it may also be known that
requirements (b) and (c) are on course to be fulfilled. However, with regard
to (d), it would be folly for me to speculate now on the outcome of a Treasury
Spending Review in, say the year 2000, prior to invitations to tender. In
view of this uncertainty, it seems to me that the Kirk Leighton appeal must be
dismissed.
In summary, I conclude that the question of timing is essentially neutral
between Allerton, Arkendale and Kirby Hill and see no reason why any should not
be advanced reasonably quickly in accordance with the advice in PPG13 (9.44).
However, given the uncertainty as to whether and when Kirk Deighton MSA would
be built, Macgay's appeal should be dismissed".
The significance of this conclusion is made plain when one examines the overall
recommendation of the Inspector. In what he terms his "summary of key
conclusions" he succinctly summed up his conclusions on timing as follows:
"I see no material distinction between Allerton, Arkendale or Kirby Hill with
regard to the potential for reasonably prompt implementation of any planning
permission (14.39). However, because of the uncertainty as to whether, when
and in what form the Wetherby-Walshford section of the A1 upgrading will take
place (14.36, 14.39), I conclude that the Kirk Deighton appeal should be
dismissed."
In the following paragraph he set out his overall conclusion on "meeting the
need" in the following terms:
"On balance I conclude that Arkendale, Kirby Hill and Allerton (in that order
of preference) would all meet the need to a material degree. Kirk Deighton
would be second only to Arkendale in meeting the need in terms of location,
internal layout and convenience of access, but must fail in absolute terms on
the question of whether and when it would be available (14.137)".
This was the decisive blow for Macgay. Apart from this consideration, the
Inspector concluded that Kirk Deighton was the best site. He considered it to
be preferential to Kirby Hill in landscape terms, in agricultural terms and in
terms of meeting the need, and to be only slightly less favourable in highway
and traffic terms. In his "Overall conclusions" he said this:
"Kirk Deighton must fail on the fundamental problem of whether and when it
could be made available. Otherwise, and subject to the caveat concerning the
Wetherby Bypass (14.142), I consider on overall balance that it would be the
most preferable site".
(By the time the report was considered by the Secretary of State, the
particular caveat referred to was no longer an issue.)
The reasons for recommending Kirby Hill were explained as follows:
"Kirby Hill would meet the need to a material degree, and its effect on the
landscape and visual amenity, though greater than that of Allerton or Kirk
Deighton, would not be so serious as to outweigh the compelling need for a new
MSA on this section of the A1/A1(M)".
The Secretary of State's decision
The Inspector held his inquiry on certain dates between 7 October 1997 and the
23 January 1998. The Secretary of State's decision was given some 14 months
later on the 15 March 1999. In the interim, there were certain developments
which the Secretary of State referred to in his decision letter. I shall first
set out the material passages in that letter and then look at the fresh
material to which he refers.
The decision letter
The Secretary of State annexed a copy of the Inspector's report, and his
conclusions, to the decision letter. The key paragraphs of the letter were the
following:
"3 The Secretary of State agrees with the Inspector's conclusions and accepts
his recommendations. He has taken into account the announcement made by the
Minister for Roads, Lord Whitty, on 31 July 1998 about future arrangements for
motorway service areas. He has also taken into account the results of the
trunk roads review set out in "A New Deal for Trunk Roads in England" published
in the same month, and of the subsequent announcement of start dates for
schemes included in the programme. However, in his view these do not raise
any issues which would cause him to depart from his decision.
4. The Secretary of State has received two items of post-inquiry correspondence
from the Hepher Dixon Partenership who act on behalf of Macgay Limited. The
first refers to the results of the roads review and the new policy statement on
arrangements for motorway service areas. The second relates to the inclusion
of the Bramham Cross motorway service area site as a pre-inquiry change to the
Deposit Draft of the Selby District Local Plan. These representations have
been considered but have not affected the Secretary of State's decision.
.....................
6. Therefore, for the reasons given by the Inspector, the Secretary of State
hereby refuses to grant outline planning permission for an MSA on land situated
at the south-east quadrant of the A1(M)/A59 interchange at Allerton and
dismisses the appeals by JJ Harrison (Properties) Limited and Macgay Limited.
He allows the appeal by Heather Ive Associates and hereby grants outline
planning permission for a twin-sided motorway service area on land to the east
and west of the A1(M), just north of the B6265 Ripon-Boroughbridge road near
Kirby Hill, subject to the following conditions......."
Although the language in paragraphs 3 and 4 is different, each is apparently
intended to say the same thing, namely that the Secretary of State has taken
into account the new material but that it has not affected his decision.
The fresh issues
Paragraph 3 refers to three developments which are said, however, to raise "no
issues" which would cause the Secretary of State to depart from his decision.
The first is the announcement of the Minister of Roads made to Parliament on
the 31st.of July 1998 relating to the review of the trunk roads
programme. After referring to the fact that there had been extensive
consultation, the Minister said this:
"For the first time ever we have provided financial stability through our
three year spending programme and seven year transport investment plan which
will enable our programme to go ahead. And for the first time ever we have a
practical and focused programme. Gone is our predecessor's massive wish list
of 150 schemes, some of which would never have been built, over a timescale
which was never specified and for which money was never assured.
We have looked at the schemes which could be started in the foreseeable future
and produced a programme that is funded and delivers our objectives. This is
the 37 schemes in our targeted programme of improvements, all of which can be
started within seven years".
The second development was the document entitled "A new deal for trunk roads in
England". This identified the 37 targeted schemes, which included the
Wetherby-Walshford stretch of the A1. These schemes were at various stages:
some were at a stage where draft orders had been published, in the case of
others orders had been made, and some were at a more advanced state termed
"start of works". The Wetherby-Walshford road fell into that last category.
The third development referred to was an answer given to a Parliamentary
question by the Minister for the Environment Transport and Regions on the 10
December 1998. He confirmed that the 37 schemes would "definitely start within
the next seven years, subject only to the completion of any outstanding
statutory procedures". He also announced that the Wetherby-Walshford stretch
was one of two schemes were the statutory procedures had been completed, and
one of five schemes that were being made subject to a Design, Build, Finance
and Operate contract ("DBFO"). It had a contract award date of 2002/03. An
advantage of this type of contract is that it is not necessary for the whole
capital payment to be made up front: rather it is made over a thirty year
period. However, the contract will be awarded only if the Highways Agency,
which is responsible for entering into the contracts, and the Minister are
satisfied that the DBFO contract provides value for money when compared with
conventional procurement arrangements.
In paragraph 4 of the decision letter the Secretary of State referred to two
items of correspondence from the Hepher-Dixon partnership, planning consultants
who act on behalf of Macgay. The first of these was a letter written on the 13
November 1998, after the Inspector's report had been received by the Secretary
of State in September of that year. Essentially it drew attention to two of the
developments which I have already mentioned but not the December announcement,
which it predated. The letter urged the Secretary of State to take these
developments into account. It concluded:
"For the most part, these [developments] affect interpretation of evidence
given at the multiple inquiry, rather than occasioning the need for new
evidence".
The other letter dated 19 January 1999 drew attention to the fact that a
motorway service area site at Bramham Cross had been included as a change to
the Selby District Local Plan. It was written on behalf of Granada Hospitality
Limited which owned and operated an MSA at Selby Fork and had objected to the
change in the local plan. They were also Macgay's proposed operator in the
event of the planning application for Kirk Deighton proving to be successful.
The letter concluded:
"I am writing to bring the matter to your attention since it may be an issue
upon which the Regional Office will also wish to comment at that time"
It is material to point out, however, that in drawing attention to this matter,
the partnership made no reference at all to the planning appeal, although
Bramham had been considered by the Inspector in assessing need.
The grounds of challenge.
The statutory appeals are made pursuant to section 288 of the Town and Country
Planning Act 1990. Subsection (1) provides, is so far as it is material, as
follows:
"If any person-
(a) is aggrieved by any action on the part of the Secretary of state to which
this section applies and desires to question the validity of that action, on
the grounds that the action is not within the powers of this Act, or that any
of the relevant requirements have not been complied with in relation to that
action, he may, within six weeks from the date on which the order is confirmed
or the action is taken, as the case may be, make an application to the High
Court under this section."
Where the allegation is that relevant requirements have not been complied with,
it is necessary for the applicant to show that he has been substantially
prejudiced by that failure. This is plain from subsection (4):
"On any application under this section the High Court-....
(b) if satisfied that the ...action in question is not within the powers of
this Act, or that the interests of the applicant have been substantially
prejudiced by a failure to comply with any of the relevant requirements in
relation thereto, may quash that...action."
The principal ground of Macgay's appeal, which is the only ground relied on by
the Council, is that the reasons given by the Secretary of State are wholly
inadequate. They contend that he has failed to provide proper reasons for his
decision as he is required to do by regulation 17 of the Town and Country
Planning (Inquiries Procedure) Rules 1992, and that they have been
substantially prejudiced by this failure. The applicants say that in view of
the developments which I have mentioned, the reasons which the Inspector gave
for not recommending the Kirk Deighton site were no longer applicable. The
Inspector had pointed to fundamental uncertainties which were no longer present
by the time the Secretary of State came to determine the matter. To the extent
that there were any remaining doubts about whether and when the motorway
construction would take place, they were fundamentally different in kind to the
doubts and uncertainties that presented themselves to the Inspector.
Accordingly, it is said, the Secretary of State could not conceivably be
reaching his decision for the same reasons as the Inspector, and by saying that
he had done so, he must have erred in law. At the very least, he has left
wholly obscure the basis of his reasoning.
The other grounds advanced by Macgay go to the substance of the decision
itself. It is alleged that the Secretary of State erred in law in various ways
and therefore reached a decision which was not within the powers of the Act.
The errors relied upon are as follows:
(1) The Secretary of State failed to take into account the fresh
developments.
(2) If and insofar as the Secretary of State had regard to any need for the MSA
to be developed as a matter of urgency, he erred in law since there was no
finding of the Inspector that the need was so urgent as to override normal
planning considerations.
(3) The Secretary of State failed to have regard to the fact that a local plan
inquiry was pending; he ought to have delayed his decision until a report had
been issued by the local plan inspector. The inquiry into objections had
already been heard in July 1998 (although in fact no report was issued until
January 2000.)
(4) The Secretary of State had failed to have regard to the consequences of
different sites upon future applications within the Green Belt. The thrust of
this argument was that the selection of Kirby Hill would increase the need for
a further MSA to the south, within the Green Belt. A related argument was that
the Secretary of State should in any event have given reasons for continuing to
select Kirby Hill in the light of the fact that by then Bramham was identified
in the Selby Local District Plan.
(5) The Secretary of State had acted irrationally in concluding that the site
at Kirby Hill would be acceptable in landscape terms. In reaching this
conclusion he had acted on two misunderstandings of a landscape appraisal
report prepared by Woolerton Truscott.
If any of these grounds succeeds then the decision must be quashed without
Macgay having to establish substantial prejudice.
I shall first address the ground which relates to the alleged failure properly
to comply with the requirements of the Act by giving inadequate reasons, and
then consider the substantive grounds of the challenge, which raise the
question whether the decision was within the powers of the Act.
Defective Reasons: the Law.
The principal issue in this case raises the question of how the Secretary of
State should approach planning appeals and, more specifically, the extent to
which he is required to explain his reasoning in the decision letter. In the
past decade these questions have on three occasions been considered by the
House of Lords. The relevant cases are Save Britain's
Heritage v Number 1 Poultry Ltd.[1991]1W.L.R.153;
Bolton Metropolitan District Council v Secretary
of State for the Environment(1996)71P.&C.R.309; and
City of Edinburgh Council v Secretary of State
for Scotland[1997]1W.L.R.1447
In the Bolton case Lord Lloyd summarised the position as follows (p.3113):
"Before dealing with each of these challenges, I should first make some
preliminary observations on the correct approach to decision letters in
planning appeals, with which alone we are concerned in this case. This can be
done very briefly, since the question was fully covered in the recent speech of
Lord Bridge of Harwich in Save Britain's Heritage v. No. 1
Poultry Ltd.
Under Section 70(2) of the Act of 1990, read with section 77(4), it was the
duty of the Secretary of State to have regard "to the provisions of the
developments plan...and to any other material considerations". Under rule
17(1) of the Town and Country Planning (Inquiries Procedure) Rules 1988 (S.I.
1988 No.944), it was the duty of the Secretary of State to "notify his
decision...and his reasons for it in writing to all persons entitled to appear
at the inquiry who did appear..." So the Secretary of State had to have
regard to all material considerations before reaching a decision, and then
state the reasons for his decision to grant or withhold planning consent.
There is nothing in the statutory language which requires him, in stating his
reasons, to deal specifically with every material consideration. Otherwise
his task would never be done. The decision letter would be as long as the
inspector's report. He has to have regard to every material
consideration; but he need not mention them all".
Similar observations were made by Lord Clyde in the Edinburgh case
(p.1464E to 1465C). In that case his Lordship quoted a brief passage from the
judgment of the Lord President Emslie in Wordie Property Co.
Ltd. v Secretary of State for Scotland, 1984
S.L.T.345,348 in which he had adopted the concept of the "informed reader".
Lord Emslie said this:
"The decision must, in short, leave the informed reader and the court in no
real and substantial doubt as to what the reasons for it were and what were the
material considerations which were taken into account in reaching it."
In the Save case Lord Bridge had commented on the degree of
particularity required and had also expanded on the circumstances in which a
defect in the reasons might invalidate the decision on the grounds that
substantial prejudice had been made out. He said this (p.166 to 167):
"The three criteria suggested in the dictum of Megaw J. in In re Poyser
and Mills' [1964] 2Q.B. 467, 478 are that the reasons should be
proper, intelligible and adequate. The application of the first two of these
presents no problem. If the reasons given are improper they will reveal some
flaw in the decision-making process which will be open to challenge on some
grounds other than the failure to give reasons. If the reasons given are
unintelligible, this will be equivalent to giving no reasons at all. The
difficulty arises in determining whether the reasons given are adequate,
whether, in the words of Megaw J, they deal with the substantial points that
have been raised or, in the words of Phillips J. in Hope v.
Secretary of State for the Environment, 31 P & C.R. 120,
enable the reader to know what conclusions the decision-maker has reached on
the principal controversial issues. What degree of particularity is required?
It is tempting to think that the Court of Appeal or your Lordships' House
would be giving helpful guidance by offering a general answer to this question
and thereby "setting the standard" but I feel no doubt that the temptation
should be resisted, precisely because the court has no authority to put a gloss
on the words of the statute, only to construe them. I do not think one can
safely say more in general terms than that the degree of particularity required
will depend entirely on the nature of the issues falling for decision.
Whatever may be the position in any other legislative context, under the
planning legislation, when it comes to deciding in any particular case whether
the reasons given are deficient, the question is not to be answered in vacuo.
The alleged deficiency will only afford a ground for quashing the decision if
the court is satisfied that the interests of the applicant have been
substantially prejudiced by it. This reinforces the view I have already
expressed that the adequacy of reasons is not to be judged by reference to some
abstract standard. There are in truth not two separate questions; (1) where
the reasons adequate? (2) if not, were the interests of the applicant
substantially prejudiced thereby? The single indivisible question, in my
opinion which the court must ask itself whenever a planning decision is
challenged on the grounds of a failure to give reasons is whether the interests
of the applicant have been substantially prejudiced by the deficiency of the
reasons given. Here again, I disclaim any intention to put a gloss on the
statutory provisions by attempting to define or delimit the circumstances in
which deficiency of reasons will be capable of causing substantial prejudice,
but I should expect that normally such prejudice will arise from one of three
causes. First, there will be substantial prejudice to a developer whose
application for permission has been refused or to an opponent of development
when permission has been granted where the reasons for the decision are so
inadequately or obscurely expressed as to raise a substantial doubt whether the
decision was taken within the powers of the Act. Secondly, a developer whose
application for permission is refused may be substantially prejudiced where the
planning considerations on which the decision is based are not explained
sufficiently clearly to enable him reasonably to assess the prospects of
succeeding in an application for some alternative form of development.
Thirdly, an opponent of development, whether the local planning authority or
some unofficial body like Save, may be substantially prejudiced by
a decision to grant permission in which the planning considerations on which
the decision is based, particularly if they relate to planning policy, are not
explained sufficiently clearly to indicate what, if any, impact they may have
in relation to the decision of future applications".
Very exceptionally, it may be said that the decision of the Secretary of State
is irrational, but this can be only where the other known facts and
circumstances point overwhelmingly in favour of a different decision; see
R v Secretary of State for Trade aand Industry,
Exparte Lonhro plc [1989] 1WLR 525 at 540 per Lord Keith
Finally, it is also necessary to bear in mind certain observations of Sir
Thomas Bingham M.R., as he was, in Clarke Homes Limited v
Secretary of State for the Environment and East Staffordshire
District Council(1993)66 P.&C.R.263 where the construction of
a decision letter was in issue. He said this:
"....the central issue in this case is whether the decision of the Secretary of
State leaves room for genuine doubt as opposed to forensic doubt as to what he
has decided and why. This is an issue to be resolved as the parties agree on a
straightforward down-to-earth reading of his decision letter without excessive
legalism or exegetical sophistication."(p.271-272).
In my opinion the following principles can be derived from these
authorities:
(1) The Secretary of State must have regard to all material considerations
before reaching his decision. These include the provisions of any development
plan (which, by virtue of section 54A of the 1990 Act he is obliged to follow
unless there are good reasons not to) and any other material considerations. In
an appropriate case, these will include the merits of alternative sites.
(2) He need not, however, refer to all material considerations in his
reasons. But he must state his reasons intelligibly and in sufficient detail to
enable the informed reader and the court to understand the reasoning and to
know what conclusion he has reached on the principal important controversial
issues.
(3) The degree of particularity or detail required depends on the nature of
the issues falling for decision. It is not, however, necessary for the reasons
to be elaborately expressed; a concise statement of reasons will suffice.
(4) Any doubt as to the reasoning i.e. what the Secretary of State has
decided and why, must be a genuine and not an artificial or forensic doubt. The
doubt must exist on a sensible reading of the decision by an informed reader
and not as a result of an excessively legalistic or over sophisticated analysis
of the decision letter.
(5) When a planning decision is challenged for failure to give reasons as
required by regulation 17, the single indivisible question for the court is
whether the interests of the applicant have been substantially prejudiced by
any deficiency in the reasons given.
(6) Such prejudice will include, but is not limited to, the three examples
given by Lord Bridge in Save.
(7) As the first of these examples makes clear, a developer refused planning
permission will suffer prejudice if the reasons are so inadequately or
obscurely expressed as to raise a substantial doubt whether the decision was
taken within the powers of the Act. It is not necessary to establish that the
decision was in fact out with the powers of the Act.
(8) Exceptionally, where no or no adequate reasons have been given in relation
to the principal issues in dispute, the court may infer that the Secretary of
State had no rational basis for his decision, but any such inference should be
made only where other facts and circumstances appear to point overwhelmingly in
favour of a different decision.
Applying the law to the facts
The essential question I have to ask is whether either Applicant has been
substantially prejudiced as a result of any defect in the reasons given by the
Secretary of State. Plainly Macgay, as developer, will be able to show such
prejudice if the reasons are so inadequately or obscurely expressed as to raise
a substantial doubt as to whether the decision was taken within the powers of
the Act.
The Applicants contend that the basis of the Secretary of State's decision is
left completely obscure by his decision letter. They say that he purports to
rely upon the reasons given by the Inspector but that this is puzzling because
they are simply no longer applicable in view of the developments to which I
have referred. The Secretary of State and the Third Respondent dispute this:
they contend that the developments did not substantially change the position,
and that the Secretary of State was fully entitled to base his decision on the
reasons given by the Inspector. In resolving this issue, it is in my opinion
necessary to analyse carefully the reasons why the Inspector made the
recommendation that he did.
In my opinion the kernel of the Inspector's reasons for rejecting Kirk
Deighton is found in paragraphs 14.36 and 14.38 which I have set out above.
This is strongly supported by the fact that it is these two paragraphs to which
cross-reference is made in paragraph 14.137 where the Inspector describes the
reason for rejecting the site as being the "uncertainty as to whether, when and
in what form the Wetherby-Walshford section of the A1 upgrading will take
place". More specifically, as paragraph 14.38 makes plain, it was the
uncertainty about funding- what the Inspector referred to as the "folly" of
second guessing the outcome of a Treasury Spending Review- which was the most
important factor of all. The Inspector envisaged that the other elements which
created the uncertainty might be resolved by the time the matter came before
the Secretary of State, but he did not anticipate that the funding issue would
be. In my opinion he was saying that even if the construction were to take
place at all, it was anyone's guess when that would be, and it would be
irresponsible for him to base any recommendation in favour of Kirk Deighton on
mere speculation about a favourable outcome to that question. I accept that he
also had some concerns that there should not be undue delay before the MSA was
built. This is clear from the fact that he considered it to be relevant that
the other operators would be in a position to take up the planning permission
without undue delay (para.14.35), and also by the fact that on his analysis
Kirk Deighton, even on the most favourable scenario, would not be open and
available to the public until three or four years later than the other
proposals. He described this as a "substantial length of time" to expect users
to put up with the current services (para. 14.37). It is pertinent to note,
however, that he did not say that this delay would of itself be sufficient to
discard Kirk Deighton, and indeed he did not cross-refer to this paragraph at
all in his conclusions. The specific delay was a cause for concern, but in my
view it was the general uncertainty which was decisive - so decisive that it
meant that the merits of Kirk Deighton could no longer be compared with the
other sites. As the Inspector put it in paragraph 14.138, Kirk Deighton "must
fail in absolute terms on the question of whether and when it would be
available"(my emphasis).
The Respondents contend that it is plain that the Inspector considered that
the matter was urgent. Apart from the factors I have considered above, they
submit that it is implicit in his having found the need to be "compelling" that
it should be urgently met. They point to the fact that he did not conclude, as
Macgay had contended, that the need was qualitative rather than quantitative
and therefore not a matter of urgency. As I have indicated earlier in this
judgment, I accept that the Inspector did not find that the need was purely
qualitative. However, I do not agree that his description of the need as
compelling implies that an urgent response was necessarily required. It was
necessary to establish a real or substantial need in order to justify any MSA
being constructed at all, given the fact that all of the proposals conflicted
with the current development plan (see para.5.29of his report.) Accordingly,
describing the need as "compelling" does not, in my judgment, necessarily imply
urgency. For the reasons I have already given, I do not consider that the
Inspector did conclude that the need was urgent in the sense that the time
constraints to which Kirk Deighton would inevitably be subject, even if the
"whether" question was swiftly resolved, would of itself be bound to defeat
Macgay's application. If that had been the Inspector's view, it would have been
very simple for him to have said so in terms.
In my judgment, therefore, the critical issue was the uncertainty. Had that
changed by the time the Secretary of State came to give his decision? The
applicants say that it had fundamentally altered: there was now a firm contract
award date of 2002/03; there was a strong commitment to construct the motorway,
as opposed to it being one of what the Minister termed the "wish" list of 150
schemes; and the funding was to be secured by a DBFO contract which took it
outside Treasury spending control. In any event, the Minister had said that the
money would be found to fund these schemes and that, say the Applicants, was a
promise which it was reasonable to assume would be honoured. In short, the
principal concern of the Inspector, namely the difficulty of predicting whether
funding would be made available, was no longer an issue. Moreover, Macgay had
submitted to the Inspector that the MSA could be built concurrently with the
motorway, and he accepted that this would provide advantages in terms of
sustainability and landscape mitigation. Obviously, therefore, this would
reduce the potential delays before the MSA could be built.
The Respondents accept, as they were bound to do, that the development post
the Inspector's report had an impact on the question whether the road would be
built, but they submit that the Secretary of State was still justified in
concluding that overall there remained too much uncertainty. Mr. Purchas Q.C.,
for the Third Respondents, points to a range of matters that remained uncertain
notwithstanding the developments. Apart from the inherent uncertainty in any
political commitment to act in the future, he identifies the fact that the DBFO
contract will go ahead only if there are interested bidders who meet the value
for money criteria, and that under that contract there was flexibility as to
when the tenderer would be able to start construction. He submitted that there
was no obligation on the Secretary of State to analyse all these various
strands of uncertainty.
Mr. Mould, for the Secretary of State, put a different emphasis in his
argument. He accepted that the subsequent announcements had indeed gone some
way - and I believe he recognised a very substantial way- towards resolving the
"whether" issue, since the programming and funding had been determined.
However, the "when" issue, he submitted, remained decisive. In particular, it
remained in doubt whether Kirk Deighton would become available even within
three or four years of the other developers, which the Inspector had described
as the "hypothetical and optimistic" scenario (para.14.37).
In my judgment the Applicants' arguments should succeed on this point. I
consider that Mr. Stone Q.C., counsel for the Council, was correct in his
submission that the nature of any uncertainty as it might have appeared to the
Secretary of State was wholly different in character to that which caused the
Inspector to reach the conclusions that he did. As he put it, in the real world
of the administrator there could be no real doubt that the motorway would be
constructed in accordance with the policy fixed by the Government. Even if
there was genuine uncertainty about whether a successful DBFO contract would be
entered into (which he did not accept), the Secretary of State should have
spelt out that concern since it was radically different to the much more
fundamental uncertainty perceived by the Inspector. I accept that submission: I
do not consider that it was enough for the Secretary of State to have adopted
the Inspector's reasons, as he did in paragraph 6 of his decision letter, when
the basis of that reasoning had materially changed. In my view, an informed
reader of the decision letter would genuinely be in doubt about the basis of
the conclusion reached by the Secretary of State. Was it that the matter was so
urgent that any delay was unacceptable? If so, I do not consider that this was
in fact reflecting the views of the Inspector and it suggests that he might
have misunderstood the Inspector's view about urgency. Was it that there
remained uncertainty about whether the scheme would go ahead at all because of
funding uncertainties, which was the decisive reason in the mind of the
Inspector? Presumably not, since that was not the submission of the Secretary
of State before me, although if the Secretary of State was adopting the
Inspector's reasons, that would be his analysis. Furthermore, was the Secretary
of State taking the view that the uncertainties that remained still involved
the absolute rejection of the Macgay bid, or was he engaging in a balancing
exercise in which the additional delays inherent in the Kirk Deighton scheme
were weighed as against the planning and environmental considerations?
Presumably the former, since that was the Inspector's view, although the
Applicants say that this would not be justified given the different nature of
the uncertainty, and that a comparison of the sites would now be necessary
It follows that I do not accept, as Mr. Purchas Q.C. submitted, that the
Applicants have manufactured a forensic doubt and that the real meaning of the
Secretary of State's letter is clear. In the circumstances of this case, it is
not in my judgment sufficient for the Secretary of State simply to say that he
has taken the material into account but that it has not caused him to depart
from his decision. There may, of course, be perfectly cogent reasons why the
Secretary of State would choose to confirm the recommendation of the Inspector,
notwithstanding the post-inquiry developments. (This is clearly not in my view
one of those exceptional cases where it can be inferred that the reasons were
bad). In my judgment, however, the Secretary of State's reasons are not obvious
from the decision letter when read together with the Inspector's report, and
the Applicants have satisfied me - the onus being on them - that there is a
real doubt about whether the Secretary of State did reach his decision in
accordance with the powers of the Act.
It follows from this analysis that Macgay have been substantially prejudiced
by the defect in the reasons. The position of the Council is different since
they do not fall into the first of Lord Bridge's examples in
Save. Mr. Stone submits that it is prejudiced by virtue of
being the Local Planning Authority for the District in which the proposals lie.
It has an interest in the appropriate site being properly chosen. In addition,
he submits that the decision could influence future applications for in-fill
sites which could be made, thereby bringing it within Lord Bridge's third
category in Save. Although I think that the implications of the
Secretary of State's decision for further applications are relatively marginal,
since in large part the decision turns on its own facts, I am just persuaded
that taken together with the Council's status as Local Planning Authority, its
interest is such that it can claim to have suffered substantial prejudice under
the Act. Accordingly, both Applicants are entitled to the relief sought.
Other Grounds
I now turn to consider the other grounds advanced by Macgay which, if
sustainable, provide alternative bases for invalidating the decision of the
Secretary of State. I summarise the grounds by reference to the description of
them that I have given above.
(1) The Secretary of State failed to take into account the further
information.
In my opinion this ground is manifestly unsustainable. The Secretary of State
has said in terms that he has taken the further material into consideration.
Absent bad faith, which is not and could not properly be alleged, that is the
end of the matter.
(2) The Secretary of State took into account an irrelevant consideration,
namely urgency.
This argument is closely interlinked with the primary contention on reasons, as
will be clear from the earlier part of the judgment. As I have indicated, it is
not clear in my view precisely what significance was given by the Secretary of
State to the need urgently to build an MSA. However, if he did in fact consider
that the need was very urgent, that was a view he was entitled to take. It
would not have been an irrelevant consideration. In my judgment the proper
criticism is that the decision leaves obscure precisely whether the question of
urgency did in fact weigh with the Secretary of State, not that he could not
properly have treated urgency as a relevant factor.
(3) Delaying pending a local plan
It is alleged that the Secretary of State failed to take into account the
submissions which Macgay had made to the Inspector, namely that no decision
about which site should be granted planning permission should be taken until
the Harrogate local plan inspector had issued his report. It was submitted that
it was for the local plan to address the question of the timing or urgency of
the need. The Inspector was plainly aware of this submission since he
recorded it (paras.8.5 to 8.8 and 8.128). Although he did not expressly deal
with it, by implication he clearly rejected it by making a recommendation for
planning permission in advance of the local inquiry report. Equally, the only
reasonable inference is that the Secretary of State also rejected this
submission. This was entirely in accordance with PPG 1 para.48 which indicates
that generally planning applications should be considered in the light of
current policies, although account can be taken of policies in emerging
development plans, the appropriate weight to be given depending upon which
stage the plan had reached. Similarly, Annex B to PPG13 makes it clear that in
normal circumstances the Secretary of State should determine appeals
expeditiously and should only in exceptional cases delay them so that they can
be heard during the course of a development plan inquiry.
In my opinion in the light of these principles, the only possible complaint
here is that neither the Secretary of State nor the Inspector had expressly
dealt with this particular submission. The decision not to accept it was
plainly open to them. This criticism can succeed as a matter of law only if the
issue can fairly be said to be a principal controversial issue which the
Secretary of State was obliged to address. I do not think that it would
properly fall into that category, not least because it was not supported by any
other party, not even the Council, who might be thought to have had the closest
interest in this matter. Furthermore, the logic of the argument would seem to
be that no decision at all should be taken until the local plan inquiry has
been completed, but not even Macgay was arguing for that. They were not saying
that it was premature to make any decision. Rather they were seeking to be
granted planning permission in conjunction with the local planning process.
Even if I am wrong about this not being a principal controversial issue, I do
not accept that Macgay has suffered substantial, or indeed any, prejudice by
the failure of the Secretary of State to spell out what was in any event
implicit in his decision, namely that it was not in his view desirable to
depart from the normal approach which is to deal with appeals expeditiously and
on the basis of current planning policies.
(4) The Green Belt issue.
This is again an allegation that the Secretary of State has failed to take into
account a material consideration, namely the consequences for the Green Belt of
the different sites. The argument was clearly advanced by Macgay before the
Inspector. It was specifically put to him that only Kirk Deighton removed
entirely the pressure for an "in-fill" MSA at Bramham, which is within the
Green Belt, since it was only seven miles away from Bramham (para 8.31). The
Inspector rejected the argument that this should be considered in the need
assessment for the following reasons:
"The proposed MSA at Bramham is the subject of a current planning application
but lies in the Green Belt and is not supported by a site-specific MSA
allocation in the draft Selby Local Plan (10.19,10.20). Hence its fate is
uncertain at this stage and I consider that it would be imprudent to include it
in the "need" assessment."
The Inspector did, however, consider that a proposed MSA at Skelton Grange
should be taken into account for the following reason:
...I agree...that material weight should attach to the proposal for a new MSA
at Skelton Grange on the M1-A1 Link itself. Although no planning application
has yet been made, it is a brownfield site outside the Green Belt identified
for an MSA in the Leeds Deposit Draft UDP, albeit subject to objections
(7.18,10.17).Accordingly, although there can be no certainty, it seems to me
that there is a greater likelihood of this than either Bramham or Selby
Fork."
The Inspector then put Skelton but not Bramham in his "gapping" matrix.
Macgay say that the Inspector erred in failing to give consideration to the
possibility of an MSA at Bramham. I reject that argument. It was a matter for
his judgment whether he should give any weight to the possibility of an MSA
there, and he gave cogent reasons for choosing not to take it into
consideration. Macgay then have another point. After the inquiry, Bramham was
included in the Selby District Local Plan and the Secretary of State was
notified of this by the letter of January 13, 1999 to which I have already
referred. Macgay contends that he has failed to reconsider the Inspector's
recommendations in the light of this material change, or alternatively has not
given reasons for continuing to select Kirby Hill.
In my judgment neither of these arguments can succeed. As to the first, the
Secretary of State in terms said that he had taken account of the information
given in the letter; the fact that it has not caused him to change his view is
irrelevant. As to the second, the Secretary of State was not obliged to give a
specific explanation about the implications of the new information for the
Green Belt issue. In my judgment this was not a principal controversial issue.
In my opinion that is supported by the fact that the Secretary of State's
attention was not even drawn to the Bramham issue in the context of these
appeals at all. This is a matter to which I have already made reference. Had
this information been seen to be crucial to these appeals, much more would have
been made of it in that context.
(5) Irrationality in respect of the landscape impact of Kirby
Hill
The final ground of appeal is that the Secretary of State acted irrationally in
accepting the recommendations of the Inspector that Kirby Hill would be
acceptable in landscape terms. In fact the argument as developed was not really
that the decision was perverse or irrational in a Wednesbury sense, but rather
that the Inspector had misunderstood the factual basis for his decision, in two
material ways. As I understand it, it is accepted that if there were no
misunderstandings, this ground fails. That must be right since questions of
this nature are classically issues for the Inspector unless his judgment is
plainly perverse, and that could not seriously be alleged here. I will consider
the two alleged misunderstandings in turn.
The first related to woodland planting. The Woolerton Truscott report
recommended planting tree cover in blocks of 2 to 5 hectares. The Inspector
recommended that 20 hectares should be planted. He said this (para.
14.113):
"With regard to the proposed woodland planting, it is true that his would be
extensive and that there are currently few trees in the area. However, it is
equally true that the "absence of significant woodland blocks" is identified as
the first of the negative attributes of this landscape in the WT report (9.80).
Moreover, contrary to the council's claim (10.76), the report expresses the
view that "This open rural landscape offers opportunity for significant
change..." (9.81) and under "Landscape Guidelines" advocated the introduction
of new woodland planting in large blocks of 2-5Ha (9.82). Hence it appears to
me that the proposed woodland planting would accord with the recommendation of
the WT report to provide a more diverse landscape and also to create new
habitat and opportunities for wildlife (9.82) in an area somewhat arid in these
respects".
It is said that the Inspector has plainly misunderstood the position. How
otherwise, it is said, could he have thought that a 20 hectare area was in
accordance with the recommendation for blocks of 2 to 5 hectares? In my view
this is a misreading of the report. The Inspector did not say that his precise
recommendation would accord in every way with the Woolerton Truscott advice: he
said that it would accord with the aim to provide a diverse landscape, new
habitat, and opportunities for wildlife which had also been the aim of the
Woolerton Truscott recommendation. He did not misunderstand the position as
alleged.
The second alleged misunderstanding relates to mounding. The Inspector
concluded that an artificial perimeter mound would not constitute an
unacceptably alien feature in the landscape (para.14.110). His analysis of the
relevant landscape was as follows (para.14.107):
"The landscape here - Floodplain Type 3; Rolling Arable Farmland (8.54) is
acknowledged to be of different quality to the other sites (8.71, 7.95) and is
described as wide open with large scale intervisibility (4, 8.71). The
Council were advised that it is fragmented and in need of the reintroduction of
structure and repair (6.87). I do not demure from these observations nor from
the view expressed by HIA that the landscape character is unremarkable (9.79).
Its main characteristic is its large scale openness, but any benefit that this
might offer is offset by the absence of any significant natural features or
interest to relieve the general uniformity of very large arable fields
stretching into the distance. Relief is provided only by man-made features,
including the A1(M), the Ripon Road overbridge and roundabout, and the
development at Dishforth Airfield (9.79)".
It will be seen that there is a cross reference to paragraph 9.79. Macgay says
that in his description of the site, the Inspector wholly misunderstood what
was being said in that paragraph about the site. That paragraph reads as
follows:
"Inevitably, the proposed MSA would have some impact. However, the landscape
character is unremarkable. It is classified in the WT report (CD4, p68) as
"Floodplain Farmland Type FF3 - Rolling Arable Farmland, characterised by open,
intensively farmed arable land in large fields on gentle rolling round where
trees and woodlands are generally scarce. The report observes that the open
rural character of the landscape is degraded by a number of urban elements
including Dishforth airfield, the A1(M), the A168 and their elevated junctions
at Ripon Road, Marton-le-Moor and Dishforth (CD4, pp65 & 68). Of all the
sites before the Inquiry, this undistinguished and degraded landscape is the
least constrained in environmental terms. It also provides the best scope for
assimilation into its surroundings by means of significant landscape planting
wholly in accordance with the WT report strategy".
The Applicant submits that this paragraph makes it clear that the urban
features degrade the landscape whereas the Inspector appears to have thought
that they improve it. I do not believe that the inspector was saying that: he
merely noted, quite accurately, that the urban features did in fact relieve the
landscape. His recommendation about mounding was then made with a full
appreciation of the nature of the site. In my opinion there is no basis for
saying that he misunderstood the position and accordingly the Secretary of
State was fully entitled to follow his recommendations.
Conclusions
In my judgment the Secretary of State failed to give adequate reasons for his
decision, and both Applicants have been substantially prejudiced as a result.
The other grounds of appeal fail. The outcome, however, is that the decision of
the Secretary of State must be quashed and the decision will have to be
reconsidered.