ON APPEAL FROM THE HIGH COURT
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
THE HONOURABLE MR JUSTICE POPPLEWELL
Strand, London, WC2A 2LL |
||
B e f o r e :
THE RIGHT HONOURABLE LADY JUSTICE KING
and
THE RIGHT HONOURABLE SIR RUPERT JACKSON
____________________
CSSA CHARTERING AND SHIPPING SERVICES SA |
Respondent/Charterer |
|
- and - |
||
MITSUI OSK LINES LTD |
Appellant/ Owner |
____________________
Mr John Russell QC (instructed by Clyde & Co LLP) for the Respondent
Hearing date: 16th October 2018
____________________
Crown Copyright ©
Lord Justice Longmore:
The facts
i) By clause 3:"3. Subject to the provisions of this charter the vessel shall perform her service with utmost despatch and shall proceed to [Rotterdam or STS off Rotterdam] … and there…. load a full cargo…."ii) By clause 11:
"11. Should the vessel not be ready to load by [2359 local time on 4th February 2015] Charterers shall have the option of terminating this charter unless the vessel has been delayed due to Charterers' change of orders pursuant to Clause 26, in which case the laydays shall be extended by the period of such delay.However, if Owners reasonably conclude that, despite the exercise of due diligence, the vessel will not be ready to load by [the cancelling date] Owners may, as soon as they are able to state with reasonable certainty a new date when the vessel will be ready, give notice to Charterers declaring the new readiness date and asking Charterers to elect whether or not to terminate this charter. Unless Charterers within 4 days after such notice or within 2 days after the termination date (whichever is earlier) declare this charter terminated, [the laycan dates] shall be deemed to be amended such that the new readiness date stated shall be the commencement date and the second day thereafter shall be the termination date.……..The provisions of this Clause and the exercise or non-exercise by Charterers of their option to terminate shall not prejudice any claims which Charterers or Owners may have against each other."iii) By part 1(A) of the charter, as amended, the Owner guaranteed the Vessel's description "at the date hereof and from the time when the obligation to proceed to the loadport(s) attaches."
iv) By clause 1 the Owner undertook to exercise due diligence to ensure the seaworthy condition of the Vessel "from the time when the obligation to proceed to the loading port(s) attaches and throughout the charter service."
v) The printed Part 1(B) of the Shellvoy 5 form provides for completion of "Position/Readiness" by two entries, one under "Now" and the other under "Expected ready to load". The agreed terms in the fixture recap provided for the inclusion in 1(B) of words which did not adopt either heading as such, but instead gave details of the anticipated timetable for completion of the current voyage in the following terms:
"POSITION: ETA AIN SUKHNA 9 JAN, 2015 (PART DISCHARGE)ETA SUEZ CANAL 10 JAN, 2015 (TRANSIT)ETA SIDI KERIR 12 JAN, 2015 (RE-LOADING)ETA ANTIFER 25 JAN, 2015 (DISCHARGING)ALL ABOVE BSS IAGW / WP"which being interpreted, is "on the basis if all goes well/weather permitting".
The Judgment
"I think that, in order to consider the effect of that contention, it is as well to begin by seeing just what the printed words standing by themselves should be construed as meaning. The obligation is that the ship "shall with all convenient speed sail and proceed to Fort Churchill." Now, there is no date at all as to when the ship is to sail; nor is there any warranted date as to when she is to arrive. What, then, does the obligation mean? If it is to be given any effect at all, some time for sailing must be put in it. If there were nothing in the terms of the charter-party which could guide the Court, I think the Court would be constrained to hold that it means "shall forthwith with all convenient speed sail and proceed to Fort Churchill", or it might mean "shall within a reasonable time sail and proceed to Fort Churchill." But, whichever way you looked at it, the date that governed it would be the date of the charter-party itself, it being an obligation undertaken, and, though no time is mentioned, the implication or construction would be that it would be within a reasonable time. But the shipowner is permitted for this purpose to have recourse to the expected date of readiness to load. If he had warranted to be at Fort Churchill on Sept 27, then manifestly one would have said that he need not sail until the time arises for him to comply with his warranty. It could not possibly be argued that he was obliged to sail at once so as to get to Fort Churchill earlier than his warranty. So, in the same way, if he were to put in an earlier date than Sept 27, it is reasonable to construe the charter-party as providing that he should "sail at such time as is calculated to get him to Fort Churchill at or about the date he said he expected to be there." That is exactly the meaning given to the clause in Monroe Brother, Ltd v Ryan, sup."
"21. I conclude, therefore, that as in each of the voyage charter cases I have cited, there is in this charterparty an absolute duty on the Owners to commence the approach voyage, when the clause 3 obligation to proceed to the loading port attaches, at a particular point of time. That time is to be a reasonable time, and the identification of when is reasonable falls to be determined in the light of the other charterparty terms. There was some debate in argument as to whether the issue was one of construction or implication. I did not find this of assistance. Since Mr Buckingham accepted that on any view there needs to be implied some term as to when the clause 3 obligation arises, it is not a case in which it is necessary to impose the rigorous requirements which arise when considering whether to imply any term of the first type referred to by Lord Neuberger in Marks & Spencer PLC v BNP Paribas Security Services [2016] AC 742 AT [15]. If it mattered I would treat it as an issue of construction, as did both Greer LJ and Roche LJ in Monroe. The only implication is the implication into clause 3 that the obligation to proceed is one to do so within a reasonable period of time, which is an implication of law; it is then a matter of construction what a reasonable time is: see Devlin J in The North Anglia at p. 375 col 2.
…
23. In this case, I do not regard the cancelling date as the critical term which informs the question of what is a reasonable time at which the clause 3 duty to proceed attaches. The charterparty also contains ETAs which these Owners were prepared to give in relation to the estimated time of arrival of the Vessel at the intermediate ports for the cargo operations on the previous voyage, including her final discharge at Antifer. These estimates were qualified by the rubric "IAGW/WP" (If All Goes Well/Weather Permitting), but that is no different in substance from the caveats which are implicit in an unqualified ETA at the loading port, which is merely an estimate based on what can reasonably be expected to occur in the normal course of events and without unexpectedly adverse weather. These intermediate port ETAs attracted the attendant Sanday v Keighley Maxted obligation that they must have been honestly given and on reasonable grounds. They are considered contractual statements, albeit estimates not guarantees, in the same way as an ETA at the loading port. They are equivalent to an ETA of arrival at the loading port for the purposes of deriving a time at which the Vessel could be expected to commence her approach voyage and come under the obligation in clause 3 to proceed there with utmost despatch. The only difference is that the intermediate port ETAs help identify that point working forwards, whereas when an ETA at the loading port is given the time is calculated working backwards. That is an immaterial distinction in the context of determining what is a reasonable time for commencing the approach voyage by reference to owners' estimates for the progress of the vessel towards arrival at the loading port, which is what informs the content of the Monroe obligation. They are of equivalence in being the estimates on which charterers can reasonably rely in identifying the commencement of the chartered service and in order to make arrangements for loading. Further confirmation that the ETAs at intermediate ports were intended to perform the same function as an ETA at the loading port is to be found in the fact that in the fixture recap they were identified for insertion in part 1(B) of the Shellvoy 5 form which the printed words show is intended to record an expected ready to load date.
24. The Owners gave intermediate port estimates which involved the Vessel arriving at Antifer on 25 January 2015 for final discharge of her previous cargo. Such estimate carries with it an estimate that she would take a reasonable period after arrival at Antifer to complete discharge. She was bound thereafter to embark on the chartered service. It is therefore the end of that additional period of reasonable discharging time that the Owners gave as an estimate of the expected commencement of the approach voyage and of the chartered service. In my judgment that is the time at which the Owners were under an absolute obligation to commence the relatively short approach voyage to Rotterdam, namely at the end of a reasonable discharging period for the Vessel if she were to arrive for final discharge at Antifer on 25 January 2015."
The submissions
1) the previous authorities were decisions on their own wording; the charterparty in the present case had different wording which should be construed without any slavish adherence to previous authorities which certainly could not constitute in any sense a "hallowed doctrine";2) the two substantial differences in the wording were (a) that there was no date of expected readiness to load on arrival at Rotterdam and (b) that the obligation of utmost despatch was expressly made "subject to the terms of this charter";
3) accordingly the obligation of "utmost despatch" could only attach when the vessel departed from her last discharging port under her previous charter;
4) since she never did depart from her last discharging port, the obligation of utmost despatch never arose;
5) the inclusion of the itinerary of expected dates at Ain Sukhna, Sidi Kerir and Antifer under the previous charter was only to make clear the vessel was performing a previous service, a point underscored by the wording "bss iagw/wp"; and
6) the cancellation/termination clause was irrelevant because it merely gave the Charterer an option without giving any right to damages.
1) the court was bound by the principle of Monroe v Ryan that the exceptions in the charterparty (e.g. in this case, for collision or accidents or perils of the sea) did not apply to a time before the chartered service began;2) the Owner's proposition that the utmost despatch obligation only applied when the Vessel left the last discharge port under her previous charterparty meant that, even if the Owner were entirely to blame for the Vessel's failure to depart her last discharging port, the utmost despatch obligation would never apply;
3) the fact that the parties agreed to put the Vessel's itinerary under the previous charter into the section (or box) marked 'B' in Part I of the printed Shellvoy 5 form entitled "Position/Readiness" showed that the itinerary was intended as equivalent to a statement in respect of the time at which the Vessel was expected to be ready; why else would it be there?
4) The true construction of a combination of section/box B and clause 3 of Part II of the Shellvoy 5 form was therefore that the obligation of utmost despatch arose at such time as it was reasonable to suppose the vessel would reach the loading port of Rotterdam once a reasonable time for discharge had elapsed; and
5) If all this were wrong the obligation of utmost despatch must at least arise at such time as it was reasonable to suppose that the Vessel should sail to meet her cancelling date.
Decision
"In short, the position is this, that if a shipowner wants to make the beginning of one voyage contingent upon the conclusion of the one before, he must say so in clear terms. There is clearly a number of things that would have to be worked out in order that such an arrangement should be made as would be fair to both sides. It may be that the shipowner had it in mind in this case that that was what he wanted. But, if he did have that in mind, he has not put it into such language as would make it plain to any reasonable charterer that the charterer was being invited to accept the risks of delay under an earlier charter-party in which that charterer was not concerned. To pass those risks on to a person who was not a party to that charter requires, in my judgment, if not express language, at least much clearer language than that which has been adopted in the present case."
I would echo these observations and say that, if the Owner had wanted to make the beginning of the chartered service contingent on the conclusion of the previous voyage, much clearer words than the parties have chosen would be required.
Conclusion
Lady Justice King:
Sir Rupert Jackson:
CLAIM NO A3/2017/3026
IN THE COURT OF APPEAL
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Claimant/Respondent
Defendant /Appellant
UPON the Appellant Defendant appealing the Order of Popplewell J of 18 October 2017
AND UPON hearing Counsel for the parties
IT IS HEREBY ORDERED THAT:
a. The appeal is dismissed.
b. The Appellant shall pay the Respondent's costs of the appeal which are agreed in the sum of £64,386.01 within 14 days of the date of this Order.
c. The Appellant's application for permission to appeal to the Supreme Court is to be dealt with by written submissions, in accordance with the following timetable:
1) The Appellant's skeleton argument in support of its request for permission to appeal by 7 November 2018.
2) Any skeleton in response on behalf of the Respondent by 9 November 2018.
3) Any skeleton in reply on behalf of the Appellant by 13 November 2018.
6 November 2018
CLAIM NO A3/2017/3026
IN THE COURT OF APPEAL
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
BEFORE
LORD JUSTICE LONGMORE
LADY JUSTICE KING
SIR RUPERT JACKSON
BETWEEN:
Claimant/Respondent
Defendant /Appellant