ON APPEAL FROM THE HIGH COURT OF JUSTICE
TECHNOLOGY & CONSTRUCTION COURT
Mr. Justice Akenhead
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE TOMLINSON
and
LORD JUSTICE McCOMBE
____________________
RWE NPOWER RENEWABLES LTD |
Claimant/ Respondent |
|
- and - |
||
J N BENTLEY LTD |
Defendant/Appellant |
____________________
Miss Fiona Parkin Q.C. and Mr. Ronan Hanna (instructed by Renew Legal) for the respondent
Hearing dates : 20th & 21st January 2014
____________________
Crown Copyright ©
Lord Justice Moore-Bick :
" . . . the construction of the civil works associated with the Black Rock hydro scheme as more comprehensively set out in Part 2 Works Information."
"The key dates and conditions to be met are:
. . .
3. Completion of pipeline testing 24 November 2010
. . .
5. Completion of intake 22 November 2010."
"Option X5
( The completion date for each section of the works is
section 1 2 3 |
description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. |
completion date 14 February 2011 27 May 2011 4 October 2011 |
Option X7
( Delay damages for each section of the works are
section 1 2 3 |
description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. |
Amount per day £1,000.00 £2,544.00 £600.00" |
(Since the wording of Options X5 and X7 are for all material purposes identical, I shall not refer separately to Option X7 save where it is necessary to do so.)
"6.2 Completion
. . .
Section 2 Completion, including testing, of the intakes, penstock pipelines and tailrace, and the powerhouse (including building services) to be completed to allow the hydro plant to be tested and commissioned.
Completion of section 2 is defined as completion of the following items of the works:
( all of the intakes and associated facilities;
( all of the penstock pipelines and associated facilities, except for surface reinstatement;
( all of the tailrace;
. . . "
Lord Justice Tomlinson :
Lord Justice McCombe :