ON APPEAL FROM THE CENTRAL LONDON
COUNTY COURT
HHJ BAILEY
TCC09070
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE MOORE-BICK
and
LORD JUSTICE KITCHIN
____________________
Relicpride Building Company Limited |
Appellant |
|
- and - |
||
(1) Mr Roderick Charles Cordara (2) Mrs Tsambika Cordara |
Respondents |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
The Respondents appeared in person
Hearing date: 12 February 2013
____________________
Crown Copyright ©
Lord Justice Kitchin:
"3.1.1. [Faddian] shall procure that [Relicpride] complies with its obligations in an Agreement dated 3 August 2001 and made between the [Cordaras] and [Relicpride] ("Relicpride Agreement") and if Relicpride fails to carry out its obligations then in default of the Seller carrying them out within a further month to indemnify the [Cordaras] in respect of the reasonable and proper cost of carrying out the List of Snagging Items (as that expression is defined in the Relicpride Agreement)
3.1.2 The [Cordaras] shall retain £35,000 out of the Purchase Price which shall be retained by the [Cordaras'] solicitor as stakeholder ("the Retention")
3.1.3 The Retention shall be paid to [Faddian] immediately upon the occurrence of the last of the following events:
a) completion of the Section 106 Agreement and the issue of the resultant Planning Permission in the form previously agreed with the [Cordaras'] solicitors;
b) the satisfactory completion of those works referred to in the Relicpride Agreement;
c) the issue by the District Surveyor for the London Borough of Camden of his certificate or other form of confirmation that the works referred to in this fax dated 30 July 2001 addressed to Liam Coyle of Relicpride Building Company Limited have been completed."
"1. [Relicpride] shall within the next two months carry out and complete
1.1 those snagging items set out in the attached list marked "List of Snagging Items";
1.2 the outstanding matters detailed in the District Surveyor's fax dated 30 July addressed to Liam Coyle of Relicpride bearing reference number 00/2/418.
2. [Relicpride] shall carry out and complete such further works to the Property in order to satisfy those objections of the Local Planning Officer set out in his two letters dated 25 July 2001 and the other 27 July 2001 both addressed to [Relicpride] in so far as they relate to the Property.
3. The [Cordaras] confirm that they will do all reasonable things necessary to assist in procuring completion of the Section 106 Agreement and the issue of the resultant Planning Permission including granting access to the Property on reasonable notice in writing and having been consulted prior thereto on the works required to enable [Faddian] to carry out any necessary works to it [Relicpride] making good all damage occasioned thereby and being a party to the Section 106 Agreement (if required by the Local Planning Authority) but without any obligation to incur any expense in doing so."
i) the failure to complete the s.106 agreement;
ii) the failure to complete all of the items of work set out in the Marshall list;
iii) the failure to complete the necessary works in relation to the air conditioning units;
iv) the failure to install an entrance canopy.
"The Retention shall be paid to Faddian immediately upon the occurrence of the last of the following events: …"
The crucial question, however, is what the parties intended should happen if one or more of the events did not occur within a reasonable time or if it were to become apparent that one or more of the events would never occur. This is not something which, on a literal reading, the clause addresses at all.
Lord Justice Moore-Bick:
Master of the Rolls: