COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
THE HONOURABLE MR JUSTICE FIELD
Strand, London, WC2A 2LL |
||
B e f o r e :
THE RIGHT HONOURABLE LORD JUSTICE LONGMORE
and
THE RIGHT HONOURABLE LORD JUSTICE WILSON
____________________
GB GAS HOLDINGS LIMITED |
Respondent |
|
- and - |
||
ACCENTURE (UK) LIMITED ACCENTURE SCA ACCENTURE INTERNATIONAL SARL ACCENTURE INC |
Appellants |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400, Fax No: 020 7404 1424
Official Shorthand Writers to the Court)
Mr Jonathan Sumption QC, Mr Jeffery Onions QC and Ms Sonia Tolaney (instructed by Linklaters LLP) for the Respondent
Hearing dates : 9th, 10th & 11th June 2010
____________________
Crown Copyright ©
Lord Justice Longmore:
Introduction
i) Centrica agreed to pay an additional £10 million to the overall amount payable to Accenture under the JPA (Clause 1.1).ii) Accenture agreed to provide an additional 18,000 man days towards completion of Release 3 (Clause 1.5).
iii) Accenture agreed to a three to four month pilot of Release 3B with live users for which the parties were to agree a set of objective pilot acceptance criteria to identify any faults in relation to Release 3B during the pilot. It was also agreed that the relevant warranties under Clause 15 of the JPA would not start to run until after completion of the pilot and the start of the migration of accounts from the old billing systems to the new one, rather than at the start of the pilot.
iv) Releases 4 and 5 were suspended.
Relevant Provisions in the JPA
15.2 Release Warranties
15.2 .1 Subject as provided below Accenture warrants to Centrica that
i) for the duration of the Initial Warranty Period:
(a) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and
(b) completion of each Release will not materially adversely affect functionality achieved in any previously delivered Releases;
ii) in respect of the Release(s) which implement the Billing System (currently planned to be Release 3), for the duration of the Full Warranty Period:
a) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and
b) completion of each Release will not materially adversely affect the functionality achieved in any previously delivered Releases.
and in respect of this Clause 15.2.1(ii) only with regard to any functionality, processes, End User or data volumes which do not occur or are not used, operated or introduced during the Initial Warranty Period.
15.2.2 Without limiting Clause 15.2.1, for the relevant Warranty Period:
i) a Release will be free from material design and material programming and material implementation errors; and
ii) a Release will meet in all material respects the Statement of Release Requirements to give Centrica the capability to achieve competitive advantage and the System will be capable of providing the Benefits.
15.3 Warranty Process
The Parties shall agree, prior to 31 July 2002 or (if earlier) the Acceptance Date for Release 1, a process for the notification and rectification of claims under Clauses 15.1.1, 15.2.1 and 15.2.2 including processes for (i) the categorisation of such warranty claims as being within the scope of Clauses 15.1.1, 15.2.1 or 15.2.2 (ii) the prioritisation of and tracking of such claims, and (iii) acceptance by Centrica of rectifications and/or work arounds delivered by Accenture and if the Parties fail to agree such a process within a reasonable time, the matter shall be referred to the Dispute Resolution Procedure.
15.4 Level of Effort
15.4.1 Accenture will fix Material Defects and Fundamental Defects to the level of effort set out in this Clause 15.4 during the relevant Warranty Period.
15.4.2 Material Defects
Upon being notified by Centrica of a Material Defect Accenture shall promptly take all steps reasonably necessary to correct the Material Defect breach provided always that for the avoidance of doubt in no event shall the cost spent on fixing (being calculated on either the Time and Materials Basis or the Maintenance Daily Rate, whichever is relevant to the appropriate personnel being used) exceed the cap on liability set out in Clause 16. This shall constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Material Defect. For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Material Defect shall be if Accenture does not promptly take all steps reasonably necessary to correct the breach, and nothing in this Clause 15.4.2 shall remove Centrica's right to terminate this Agreement in accordance with its terms.
15.4.3 Fundamental Defects
Upon being notified by Centrica of a Fundamental Defect Accenture shall do what a commercial, reasonable and prudent organisation using the System to carry on its business would do when acting in its own best interests (having due regard to the costs necessary and benefits likely from correcting the Fundamental Defect) provided always that in no event shall the cost spent on fixing (being calculated on either the Time and Materials Basis or the Maintenance Daily Rate, whichever is relevant to the appropriate personnel being used) exceed the cap on liability set out in Clause 16. This shall constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Fundamental Defect. For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Fundamental Defect shall be if Accenture does not promptly use the endeavours set out in this Clause 15.4.3 to correct the breach and nothing in this Clause 15.4.3 shall remove Centrica's right to terminate this Agreement in accordance with its terms.
15.4.4 Reduction in Cap
The effort expended by Accenture in meeting its obligations under this Clause 15 will be calculated on either the Time and Materials Basis or the Maintenance Daily rate, whichever is relevant to the appropriate personnel being used, and will be treated as liability of Accenture and will count towards and reduce the aggregate liability cap set out in Clause 16. Accenture shall agree an action plan for fixing particular breaches of warranties with Centrica, implement such plan and keep Centrica informed as to the amount of money spent.
15.4.5 Data and Documentation
Notwithstanding Accenture's obligations under Clauses 15.1.1, 15.2.1 and 15.2.2 in relation to defects under Clause 5 (Data Audit, Cleansing, Matching, Conversion and Migration) Accenture will only be obliged to fix errors and to remedy the causes and consequences of such errors and then only errors notified during the Initial Warranty Period. In relation to Documentation defects shall be dealt with in accordance with Clause 7.1.4.
15.4.6 Material Defects and Fundamental Defects caused by Centrica
Accenture shall charge Centrica on a Time and Materials Basis or the Maintenance Daily rate, whichever is relevant to the appropriate personnel being used, for the correction of any Material Defects or Fundamental Defects notified by Centrica to the extent arising from or caused by:-
i) defects in the Centrica System and/or Legacy System not caused by Accenture;
ii) Centrica computer operator error or omission after Go-Live; and
iii) diagnosis and/or rectification of problems not associated with the System and not caused by Accenture.
"Fundamental Defect" means a fundamental breach of Clauses 15.2.1 and/or 15.2.2 and/or 15.1.1(i) (to the extent a breach of Clause 15.1.1(i) would also constitute a breach of Clauses 15.2.1 and 15.2.2 had it occurred during the Warranty Period) in relation solely to the release(s) relating to the Billing System (currently planned to be Release 3) which causes a severe adverse effect on the British Gas Business;
"Material Defect" means a breach of Clauses 15.1.1 (i) (to the extent a breach of Clause 15.1.1(i) would also constitute a breach of Clauses 15.2.1 and 15.2.2 had it occurred during the Warranty Period), 15.2.1 and/or 15.2.2 which has or is likely to have an adverse effect on the British Gas Business, and which is not a Fundamental Defect;
Relevant Provisions in the Amended JPA
15.2 Release Warranties
15.2.1 Subject as provided below Accenture warrants to Centrica that
i) for the duration of the Warranty Period:
d) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and
e) completion of each Release will not materially adversely affect functionality achieved in any previously delivered Releases;
ii) in respect of the Release(s) which implement the Billing System (currently planned to be Release 3), for the duration of the Warranty Period:
a) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and
f) completion of each Release will not materially adversely affect the functionality achieved in any previously delivered Releases.
15.2.2 Without limiting Clause 15.2.1, for the relevant Warranty Period:
a) a Release will be free from material design and material programming and material implementation errors; and
b) a Release will meet in all material respects the Statement of Release Requirements to give Centrica the capability to achieve competitive advantage.
15.3 [Not used].
15.4 Level of Effort
15.4.1 Accenture will fix Fundamental Defects to the level of effort set out in this Clause 15.4 during the relevant Warranty Period.
15.4.2 Material Defects
Accenture shall have no obligation to fix Material Defects during the Warranty Period, but has agreed to fund the fixing of Material Defects and any other defects caused by Accenture that are not Fundamental Defects, by Centrica that might arise during the Warranty Period, which defects shall be determined by reference to the scope definition document set out in Schedule 21 and, in relation to Material Defects by reference to Clause 15.2 ("Defects") in the following circumstances and subject to the following conditions:
i) the Centrica JAM Team (funded solely by Centrica) will comprise a 30 Full Time Equivalents team ("the Fix Team") which are intended to be sufficient to fix Defects that might arise during the Warranty Period (for the avoidance of doubt, this is in addition to the capacity provided by Accenture and Centrica for the Maintenance Release Development Services);
ii) "Full Time Equivalents" for the purposes of this Clause 15 means an appropriately qualified, productive and skilled person working a 8 hour day (where productive means the expenditure of no more than an average of 5 days per Defect);
iii) in the event that average effort required to fix such Defects exceeds 30 Full Time Equivalents then Centrica shall pay for such additional resource up to a cost of £100,000 and thereafter Accenture shall pay Centrica for such additional resource, in each case on the basis of hours worked multiplied by £460 per 8 hour period worked and lesser periods shall be prorated accordingly;
iv) the additional effort for the purpose of this Clause 15.4.2 shall not include and Accenture shall not pay for time spent by Centrica on the following activities;
(a) business effort;
(b) design authority;
(c) management;
(d) merge of fixes into future code stream;
(e) Change requests;
v) the additional effort for the purposes of this Clause 15.4.2 shall only be payable by Accenture where:
(a) Centrica has used reasonable endeavours to confirm that the code change required is to remedy a Defect rather than to implement a change to an agreed design;
(b) there is reasonable evidence that the Defect was present in the code as at 23 December 2005 as a result of actions by Accenture or that the fix effort is required to remedy a Defect caused by the implementation of a Change Request by Accenture in any of RJ313, 314, 314.2 and 315;
(c) Centrica has used reasonable endeavours to accurately prioritise the impact of the Defect in accordance with the classifications set out in (f) below;
(d) Centrica has provided adequate time reporting of effort spent on fixes of Defects;
(e) if within a calendar month Centrica is at any stage likely to exceed 30 Full Time Equivalents in order to fix Defects, Centrica shall promptly advise the Accenture Client Partner;
(f) Only Categories P1, P2, P3 or clusters of P4 as defined below shall be included:
Fault Priority | Abbreviation | Definition |
Priority 1 | P1 | Fault is of such severity that activities cannot continue at any level. (All users out). |
Priority 2 | P2 | i) Fault prevents an entire business process from being completed or, ii) Prevents a team of business users from performing their role in its entirety. |
Priority 3 | P3 | Fault impacts designed process so significantly that the workarounds required to complete a process are not sustainable at volume ramp up. |
Priority 4 | P4 | Fault impacts the designed process and requires workaround to complete, however in isolation there is no risk to volume ramp up |
(g) Centrica is managing the fix team effectively and efficiently so as to minimise as far as reasonably practicable the average effort required to fix Defects and the utilisation of FTEs in any month.
vi) The payment obligation set out in this Clause 15.4.2 shall be Accenture's sole liability and Centrica's sole remedy with respect to Defects.vii) The Parties shall meet on a monthly basis to review the number of Defects and effort expended to fix such Defects.
viii) Any invoices delivered by Centrica shall be payable by Accenture within 30 days of receipt.
15.4.3 Fundamental Defects
Upon being notified in writing by Centrica of a Fundamental Defect (and subject always to Centrica having provided such analysis and detail as is reasonably practicable as to its reasons for believing there is a Fundamental Defect in relation to Release 3B) Accenture shall do what a commercial, reasonable and prudent organisation using the System to carry on its business would do when acting in its own best interests (having due regard to the costs necessary and benefits likely from correcting the Fundamental Defect) provided always that in no event shall the cost spent on fixing (being calculated on a Time and Materials Basis, and for the purposes of calculating Centrica's time and materials costs for fixing Fundamental Defects Centrica shall only be entitled to multiply the number of days worked by relevant Centrica personnel as follows: £150 per day for business personnel; £550 per day for business IS personnel; and £460 per day for Centrica JAM personnel) exceed the cap on liability set out in Clause 16. This shall constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Fundamental Defect. For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Fundamental Defect shall be if Accenture does not promptly use the endeavours set out in this Clause 15.4.3 to correct the breach and nothing in this Clause 15.4.3 shall remove Centrica's right to terminate this Agreement in accordance with its terms.
15.4.4 Reduction in Cap
The effort expended by Accenture in meeting its obligations under this Clause 15 will be calculated on a Time and Materials Basis, and will be treated as liability of Accenture and will count towards and reduce the aggregate liability cap set out in Clause 16. Any moneys paid by Accenture to Centrica pursuant to Clause 15.4.2 shall count towards and reduce the aggregate liability cap set out in Clause 16. Accenture shall agree an action plan for fixing particular breaches of warranties with Centrica, implement such plan and keep Centrica informed as to the amount of money spent.
15.4.5 Data and Documentation
Notwithstanding Accenture's obligations under Clauses 15.1.1, 15.2.1 and 15.2.2 in relation to defects under Clause 5 (Data Audit, Cleansing, Matching, Conversion and Migration) Accenture will only be obliged to fix errors and to remedy the causes and consequences of such errors and then only errors notified up until 30 June 2006. In relation to Documentation defects shall be dealt with in accordance with Clause 7.1.4.
15.4.6 Fundamental Defects caused by Centrica
Accenture shall charge Centrica on a Time and Materials Basis, for the correction of any Fundamental Defects notified by Centrica to the extent arising from or caused by:-
i) defects in the Centrica System and/or Legacy System not caused by Accenture;ii) Centrica computer operator error or omission after Go-Live; and
iii) diagnosis and/or rectification of problems not associated with the System and not caused by Accenture.
It will be noted that the detailed warranty process applicable to both Material and Fundamental Defects in clause 3 of the original JPA has been replaced by a much more detailed process applicable only to material defects.
Release of Accenture: Centrica and each of its affiliates hereby release Accenture, and each of its respective subsidiaries, divisions, parents and affiliated corporations or partnerships, and each of their directors, officers, shareholders, agents, employees, partners, representatives, attorneys, successors and assigns, from the Released Claims.
The Released Claims were then set out with the proviso:
provided, however, that Released Claims shall not include: (i) ….(ii) …(iii) …or (iv) any right accruing to Centrica now or in the future to pursue the warranty provisions in Clauses 5.2.2, 7.1.3, 7.1.4 and 15.2 to 15.4 hereof (the "Warranty Provisions"), in relation to a Release or Deliverable under a Release, is expressly reserved.
For the purposes of this Clause 21.3, the commission of a "material breach" shall include the commission of a series of related or unrelated breaches of this Agreement which, taken together, constitute a material breach of this Agreement.
The emergence of problems with the new billing system
The Notification Letter of 12 February 2007
The information set out in this letter represents our best understanding and analysis of the matters which are currently causing us extreme concern. At this stage we cannot rule out the possibility that other Fundamental Defects will emerge as we further implement and use the System… Furthermore, at this stage we are not in a position to fully particularise all aspects of defects we have identified, although we have given here what particulars are reasonably practicable and clearly further issues are likely to arise….
In accordance with Clause 15.4.3 of the JPA Accenture is required to commit to the process of identifying remedies and implementing them, failing which Centrica will make its own arrangements to do so and recover the costs from Accenture by way of damages….
Accenture's refusal to take any steps under Clause 15.4.3
Centrica's claim against Accenture
A. There were 6 fundamental breaches of warranty:-
i) the Exceptions Error; and/orii) the Automation Error; and/or
iii) the combination of the Exceptions Error and the Automation Error; and/or
iv) the individual material errors in combination; and/or
v) the combination of the individual material errors which manifested or evidenced the Exceptions Error; and/or
vi) the combination of the individual material errors which manifested or evidenced the Automation Error.
B. Each of the above six fundamental breaches of warranty caused a severe adverse effect on the British Gas Residential Business such that each constituted a Fundamental Defect.
C. Alternatively, the six fundamental breaches of warranty in combination caused a severe adverse effect on the British Gas Residential Business such that there were one or more Fundamental Defects.
Accenture's contentions
The Preliminary Issues to be decided
1. On a true construction of the Amended JPA:-
1.1 In order for there to be a Fundamental Defect, does each individual breach of warranty proved by Centrica have to constitute a "fundamental" breach of warranty, or can a "fundamental" breach of warranty be constituted by the breaches of warranty proved by Centrica?
1.2 In order for there to be a Fundamental Defect can the consequences of individual fundamental breaches of warranty alleged by Centrica be aggregated for the purposes of determining whether there was a severe adverse effect on the British Gas Business in order to constitute a "Fundamental Defect" or must an individual fundamental breach of warranty by itself cause a "severe adverse effect" without regard to the overall effect of different breaches?
2. In order for a "fundamental" breach of warranty to constitute a "Fundamental Defect", must the breach have caused an actual "severe adverse effect" on the British Gas Business before it was notified to Accenture under Clause 15.4.3? Or was it sufficient if, at the time of notification, the breach had started to cause or would cause a "severe adverse effect" if left unremedied?
3. On a true construction of the Amended JPA, to what extent is it legitimate to take into account the parties' prior knowledge of alleged defects in Release 3 when determining whether the letter of 12 February 2007 was a valid notice, in order to interpret it?
4. In order to provide valid notification under Clause 15.4.3, was Centrica required to state in the notification:
(i) what warranties it was alleging had been breached; and/or
(ii) with what requirements of the SoRR it was alleged that Release 3B did not materially comply; and/or
(iii) the nature of the alleged material design, programming or implementation errors; and/or
(iv) the severe adverse effect that was alleged to have resulted from each breach?
5. What is the correct basis for calculating the damages which can be claimed by Centrica for a Fundamental Defect under the terms of the Amended JPA? In particular:-
5.1 Is Centrica entitled to recover as damages its costs incurred in relation to the alleged Fundamental Defect before Accenture was notified of the alleged Fundamental Defect?
5.2 Are the losses recoverable by Centrica in relation to any alleged Fundamental Defect limited to those suffered after the expiry of a reasonable time for Accenture to comply with its obligations under Clause 15.4.3 following notification?
5.3 Is Centrica's entitlement to recover losses limited to losses calculated on a "Time and Materials Basis" in accordance with Clause 15.4.3?
6. In respect of the damages claim and the classes of loss claimed by Centrica in Schedule A, are any of those items of loss excluded under Clause 16.2 of the Amended JPA? If so, are they nevertheless (as a matter of principle) recoverable as sums expended in mitigation of Centrica's losses?
7. Can Centrica (in principle) recover for the cost of Hardware under clause 15.4.3 of the Amended JPA?
8. Does the release in Clause 27.4B(c) of the Amended JPA preclude Centrica from bringing any claim for breach by Accenture of the obligation to specify Hardware pursuant to paragraph 2.1.1 of Schedule 10 to the Amended JPA?
9. Is Centrica entitled to make requests for Hardware after 28th February 2007? If not, is Centrica otherwise entitled to purchase Hardware after 28th February 2007 under the Amended JPA?
10. If Accenture has unreasonably withheld or delayed consent to a request by Centrica for Hardware in breach of paragraph 1.4 of Schedule 10 to the Amended JPA, is Centrica (in principle) entitled to recover the cost of that Hardware as damages for breach, or as reimbursement under paragraphs 5.3 and/or 5.4 of Schedule 3 to the Amended JPA?
The factual matrix
i) the new billing system was immensely complex and involved inter-related processes and sub-processes;ii) an error in one process could affect a related process;
iii) it was quite common to have defects in a billing system which in combination created an aggregated defect;
iv) design errors in different processes could cumulatively impact on other processes;
v) exceptions not designed-in could occur as customers' accounts were migrated and it could be very difficult to identify precisely what was causing those exceptions;
vi) if something went wrong when the system was running for real with the data flows operating it could be very hard to find out why;
vii) what appeared at first to be trivial non-functions could turn out to be more important; and
viii) the billing system was of critical importance to Centrica: if it failed to function properly to a significant degree there could be a serious impact on Centrica's revenues.
I see no reason to differ from the careful and detailed judgment in respect of any of these matters and can proceed to the first preliminary issue.
Fundamental Defect
i) defects came about because the Billing System was, in the words of the Release Warranties Provision, not free froma) material design error; orb) material programming error; orc) material implementation error;or because it did not meet in all material respects the Statement of Release Requirements for the Billing System;ii) those obligations were "fundamental" obligations breach of which would be a "fundamental" breach if "fundamental" had any meaning independent of causing "a severe adverse effect" (which it did not);
iii) to the extent that the consequence of such breach caused "a severe adverse effect" that consequence was a Fundamental Defect;
iv) the requirement that the breach was to have a severe adverse effect was a requirement that a state of affairs must exist for there to be a Fundamental Defect;
v) if that state of affairs was not brought about by any single breach of clause 2 it could be brought about by a combination of breaches;
vi) those breaches need not necessarily themselves have individually caused a severe adverse effect but could have caused merely an adverse effect and themselves therefore be material breaches;
vii) but if, acting together, they caused a severe adverse effect there was then a Fundamental Defect.
Issue 1
1. On a true construction of the Amended JPA:-
1.1 In order for there to be a Fundamental Defect, does each individual breach of warranty proved by Centrica have to constitute a "fundamental" breach of warranty, or can a "fundamental" breach of warranty be constituted by the breaches of warranty proved by Centrica?
1.2 In order for there to be a Fundamental Defect can the consequences of individual fundamental breaches of warranty alleged by Centrica be aggregated for the purposes of determining whether there was a severe adverse effect on the British Gas Business in order to constitute a "Fundamental Defect" or must an individual fundamental breach of warranty by itself cause a "severe adverse effect" without regard to the overall effect of different breaches?
53. In my opinion, the meaning which Clause 15.4.3 would convey to a reasonable person having the background knowledge I have set out is: (1) a fundamental breach of warranty can be constituted by individual breaches of warranty all falling within the same subparagraph under Clause 15.2.1 or Clause 15.2.2; and (2) the consequences of such individual fundamental breaches of warranty can be aggregated for the purposes of determining whether there was a severe adverse effect on the British Gas Business.
54. In reaching this conclusion I have given careful consideration to all of Accenture's submissions, particularly those that focused on the distinct regimes established under the JPA for Material Defects and Fundamental Defects. In my judgement, the categories of Material Defects and Fundamental Defects are not mutually exclusive. There is no obligation under the JPA on Centrica to classify an apparent breach of warranty as either a Material Defect or a Fundamental Defect and I can see nothing in the agreement that prevents Centrica from asserting that a breach is a Fundamental Defect when to begin with they thought that the effects of the breach did not justify such an assertion, and may even have attempted to fix it. Nor do I see why Accenture should not come under the Clause 15.4.3 obligation even though they have paid a claim on the basis that the breach was a Material Defect. That obligation will not inevitably involve the further expenditure of money and if it does, it will go, together with the earlier expenditure, to reduce the Clause 16 cap.
i) The most important background fact was that the parties had terminated their relationship and embarked on a new one; Accenture had left the site and was no longer responsible for fixing material defects (but only for funding the fixing of such defects by Centrica) and it only remained responsible for fixing Fundamental Defects; the judge had given far too little weight to what Mr Smouha QC, on behalf of Accenture, called this "seismic shift" in the parties' relationship;ii) There were two requirements for a Fundamental Defect to exist:-
a) There had to be a fundamental breach of one of the warranty provisions;b) That breach, being already fundamental, had in addition to cause a severe adverse effect on Centrica's business;iii) Any other defect was just a defect or a Material Defect. Thus the concept of a material defect would embrace
a) a non-fundamental breach of one of the warranty provisions which caused a severe adverse effect;b) a fundamental breach of one of the warranty provisions which caused an adverse effect;c) a non-fundamental breach of one of the warranty provisions which caused an adverse effect.iv) While a single Material Defect could, by becoming more serious, become a Fundamental Defect, it was never intended that Material Defects could combine to become Fundamental Defects because the regimes in both the original JPA and the Amended JPA were different. Accenture could not be expected to begin to fix a defect to the level of effort for Material Defect (reasonable steps) but at a later stage have to fix it to a different level of effort (as for one's own business) if it became fundamental. This difference was even more critical after the amendment to the JPA when Accenture only had to fund the fixing of Material Defects by Centrica while remaining responsible for fixing Fundamental Defects.
v) When the parties wanted to include a concept of aggregation into their contractual scheme, they did so. Reliance was placed in particular on (A) clause 15.4.2(v)(f) of the Amended JPA in which prioritisation of Material Defects was to be in categories one of which (P4) permitted clusters of faults to be taken into account and (B) clause 21.3 in both the JPA and the Amended JPA which provided that the commission of a material breach for the purposes of a Termination for Default Clause was to include
"the commission of a series of related or unrelated breaches of this Agreement which, taken together, constitute a material breach of this Agreement."
Issue 2
2. In order for a "fundamental" breach of warranty to constitute a "Fundamental Defect", must the breach have caused an actual "severe adverse effect" on the British Gas Business before it was notified to Accenture under Clause 15.4.3? Or was it sufficient if, at the time of notification, the breach had started to cause or would cause a "severe adverse effect" if left unremedied?
"which causes a severe adverse effect on the British Gas Business."
A Material Defect is defined to be a breach of the warranty provisions
"which has or is likely to have an adverse effect on the British Gas Business."
Both the definitions of the respective phrases and the warranty provisions themselves refer to "during the Warranty Period" or "for the duration of the Warranty Period" which must be relevant to this question of construction.
Issue 3
On a true construction of the Amended JPA, to what extent is it legitimate to take into account the parties' prior knowledge of alleged defects in Release 3 when determining whether the letter of 12th February 2007 was a valid notice, in order to interpret it?
The letter of 12th February 2007 can be construed against the background of the parties' prior knowledge of alleged defects in Release 3 in order to determine its meaning. The question can then be decided whether, so construed, it is a valid notice.
Issue 4
4. In order to provide valid notification under Clause 15.4.3, was Centrica required to state in the notification:
(i) what warranties it was alleging had been breached; and/or
(ii) with what requirements of the SoRR it was alleged that Release 3B did not materially comply; and/or
(iii) the nature of the alleged material design, programming or implementation errors; and/or
(iv) the severe adverse effect that was alleged to have resulted from each breach?
Issue 5
5. What is the correct basis for calculating the damages which can be claimed by Centrica for a Fundamental Defect under the terms of the Amended JPA? In particular:-
5.1 Is Centrica entitled to recover as damages its costs incurred in relation to the alleged Fundamental Defect before Accenture was notified of the alleged Fundamental Defect?
5.2 Are the losses recoverable by Centrica in relation to any alleged Fundamental Defect limited to those suffered after the expiry of a reasonable time for Accenture to comply with its obligations under Clause 15.4.3 following notification?
5.3 Is Centrica's entitlement to recover losses limited to losses calculated on a "Time and Materials Basis" in accordance with Clause 15.4.3?
The judge answered the first question Yes and the second and third questions No. The general question at the beginning of this issue requires the court to determine whether the parties have excluded Centrica's common law rights in respect of Fundamental Defects by clause 15.4.3. Common law rights to damages for breach of contract can only be excluded by a clear provision to that effect. It has been accepted law since Hancock v Brazier [1966] 1 WLR 1317 that an obligation to repair or make good defects in a contract for the provision of services does not of itself exclude common law remedies.
"constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Fundamental Defect."
That is easy enough to apply to a Fundamental Defect fixed in accordance with the clause; but it must be doubtful whether that provision on its own would be clear enough to exclude any liability if Accenture do not fix the Fundamental Defect. However, the clause continues:-
"For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Fundamental Defect shall be if Accenture does not promptly use the endeavours set out in this Clause 15.4.3 to correct the breach."
What is left doubtful is thus made explicit; the right to common law damages remains if endeavours to fix are not promptly used. That covers Centrica's claims in respect of Fundamental Defects in this case (if such defects exist).
Issue 6
6. In respect of the damages claim and the classes of loss claimed by Centrica in Schedule A, are any of those claims of loss excluded under Clause 16.2 of the Amended JPA? If so, are they nevertheless (as a matter of principle) recoverable as sums expended in mitigation of Centrica's losses?
i) loss of profits or of contracts arising directly or indirectly;ii) loss of business or of revenues arising directly or indirectly;
iii) losses or damages to the extent that they are indirect or consequential or punitive.
The judge considered each item and held that none of the losses claimed came within the second limb of Hadley v Baxendale (1854) 9 Exch 341, were not therefore indirect and could therefore be recovered. This meant that the losses did not fall within 16.2 and to that extent I agree with the judge.
i) the claim for gas distribution charges is pleaded as an amount overpaid to the distributors from whom they purchased their gas. As a result of the alleged Automation Error, Centrica was unable to provide meter data for 15% of the consumption of its gas customers. The distribution charge for the gas was not therefore made on meter readings from customers and over-estimated the consumption of those customers. The judge held the sums thus paid by Centrica to the distributors were not a claim for revenue but rather a claim for charges which they paid to distributors but would not have paid but for the alleged Automation Error. On the pleadings that seems to me to be correct and I would not disturb the judge's conclusion;ii) Accenture's objections to the claim for compensation paid to customers was restricted in their skeleton argument to the assertions
a) that the claim was for an ex gratia payment and not one for which Accenture assumed responsibility under the Amended JPA; andb) that the loss was an indirect or consequential loss falling within the second limb of Hadley v Baxendale.Assertion (a) does not fall within the terms of issue 6 which asks if the claims are excluded under clause 16.2 of the Amended JPA. One would need to know much more than this court knows about the nature of this claim to be able to deal with this assertion and I do not think it would be right to deal with it at this stage. But, as a claim, it falls within the first not the second limb of Hadley v Baxendale.
Issue 7 – the cost of Hardware
7. Can Centrica (in principle) recover for the cost of Hardware under clause 15.4.3 of the Amended JPA?
The question here is whether, if the existence of a Fundamental Defect renders it necessary for Centrica to buy in more hardware for the billing system, the claim to recover the cost of that hardware can only be made pursuant to the contractual provisions for hardware as set out in Schedules 3 and 10 to the Amended JPA or whether it can be part of the free-standing claim to damages under clause 15.4.3.
"accruing to Centrica now or in the future to pursue the warranty provisions … in relation to a Release."
That clause is clear as far as it goes but does not clearly (or, in my view, at all) restrict claims for hardware consequent on a breach of warranty to sums which Centrica may be able to claim pursuant to Schedules 3 and 10 while the contract was being performed. That is not to say that no claim can be brought by Centrica pursuant to Schedules 3 and 10 if it wishes to do so, merely that that is not the limit of its entitlement.
Issue 8
Issue 9
9. Is Centrica entitled to make requests for Hardware after 28th February 2007? If not, is Centrica otherwise entitled to purchase Hardware after 28th February 2007 under the Amended JPA?
Conclusion
Lord Justice Wilson:
Lord Justice Mummery: