ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
ADMINISTRATIVE COURT
Cardiff Civil Justice Centre 2 Park Street Cardiff CF10 1ET |
||
B e f o r e :
LORD JUSTICE ELIAS
and
LORD JUSTICE PITCHFORD
____________________
TEGNI CYMRU CYF |
Respondent |
|
- and - |
||
THE WELSH MINISTERS & ANR |
Appellant |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400 Fax No: 020 7404 1424
Official Shorthand Writers to the Court)
Mr William Norris QC and Mr James Burton (instructed by the Treasury Solicitors) appeared on behalf of the Respondent.
____________________
Crown Copyright ©
Lord Justice Pitchford:
"To the north of the Appeal Site is open moorland beyond which is the A543 which leads Denbigh to the A5 in the south. The Appeal Site is bounded to the east by upland farmland, to the south by an unclassified road linking Nantglyn to the B4501 and to the west by further coniferous plantation, beyond which is the Llyn Bran reservoir. The Appeal Site is approximately 290 ha in area and is situated at an elevation between 400m and 518m Above Ordinance Datum ("AOD") which is the highest point in the immediate vicinity. However the turbines forming part of the proposed wind farm would be located below the 500m contour.
The Appeal Site is presently covered in coniferous forest, the felling of which will be necessitated by the construction of a proposed wind farm."
1) Its unacceptable impact on the character and appearance of the landscape, comprising views into and out of the Snowdonia National Park.
2) Its unacceptable cumulative visual impact affecting views across the den and moors.
3) Its adverse affect upon the community of Nantglyn by creating an arc of turbines around the village.
4) Harm to the enjoyment of the local landscape for recreational uses.
5) Noise level from the development alone, and cumulatively including existing turbines in the area.
"37. In paragraph 7 of his decision letter the Inspector identified TAN 8 as being the national policy most relevant to this case. It is necessary to describe some of its guidance in a little detail. First, TAN 8 advises that large scale on-shore wind development (defined to mean developments with generating capacity over 25 MW) should be concentrated into particular areas defined as Strategic Search Areas (SSAs). Seven such SSAs are shown within the Advice Note. One such SSA is designated within Clocaenog Forest. The indicative capacity for the whole area identified at Clocaenog Forest is 140MW. The SSA boundaries within TAN 8 are "at a "broad brush" scale". The Advice Note recognises that not all of the land within SSAs may be technically, economically and/or environmentally suitable for major wind power proposals.
38. Annex C of TAN 8 contains much technical information relating to renewable energy technologies. In terms, however, one of its purposes is to contribute to the development control process (see paragraph 1.1). Paragraphs 2.14 to 2.16 contain important guidance in relation to the noise which may be generated by wind farms. The relevant parts of those paragraphs are as follows:-
'2.14 Well designed wind farms should be located so that increases in ambient noise levels around noise-sensitive developments are kept to acceptable levels with relation to existing background noise. This will normally be achieved through good design of the turbines and through allowing sufficient distance between the turbines and any existing noise-sensitive development. Noise levels from turbines are generally low and, under most operating conditions, it is likely that turbine noise would be completely masked by wind-generated background noise. There are two quite distinct types of noise source within a wind turbine – the mechanical noise produced by the gear box, generator and other parts of the drive train and the aerodynamic noise produced by the passage of the blades through the air. There has been a significant reduction in mechanical noise since the early 1990s so the latest generation of wind turbines are much quieter than those first installed in Wales. Aerodynamic noise from wind turbines is generally unobtrusive – it is broad-band in nature and in this respect similar to, for example, the noise of wind in trees.
2.15 Wind generated background noise increases with wind speed, and at a faster rate than the turbine noise increases. The noise of the wind farm is therefore more likely to be noticeable at low wind speeds. Varying the speed of the turbines in such conditions can, if necessary, reduce the sound output from modern turbines.
2.16 The report, "the Assessment and Rating of Noise from Wind Farms" (ETSU-R-97), describes a framework for the measurement of wind farm noise and gives indicative noise levels calculated to offer a reasonable degree of protection to wind farm neighbours, without placing unreasonable restrictions on wind farm development or adding unduly to the costs and administrative burdens on wind farm developers or planning authorities. The report presents the findings of a cross-interest Noise Working Group and makes a series of recommendations that can be regarded as relevant guidance on good practice.'
39. Annex D to TAN 8 contains guidance both relating to noise and visual impact. Paragraph 3.4 of this Annex suggests that 500 metres may be an appropriate separation distance between a wind turbine and residential property to avoid unacceptable noise impacts. However the same paragraph makes it clear that this limit should not be applied in a rigid manner. Section 6 of Annex D contains detailed guidance upon assessing the visual impact of a wind farm and its impact upon the landscape. Section 8 contains supplemental information on cumulative landscape and visual impact. During the course of oral submissions in particular, Mr Norris QC drew my attention to passages within those sections but for reasons which will become clear I do not think it necessary to set out the extracts to which I was referred."
"40. Policy MEW 10 of the Denbighshire Unitary Development Plan deals, specifically, with wind power. It is in the following terms:-
Wind turbines or wind farms, including any ancillary associated developments, will be permitted provided that:
...iii) the proposal will not unacceptably harm the character and appearance of the landscape especially the AONB, AOB, LLA's, Historic Landscape or the Snowdonia National Park;
iv) the proposal does not lead to unacceptable noise levels to residential amenity in the surrounding areas;
...
vii) the proposal would not lead to an unacceptable cumulative visual impact in an area where zones of visibility overlap, particular attention would be paid to the potential effects of a proliferation of such developments in any one area;
viii) the proposal does not cause unacceptable harm to the enjoyment of the landscape for recreational and tourism purposes ..."
"At the Welsh level I attach most weight to TAN 8 and the associated Ministerial statements. This site is located within Strategic Search Area A (SSA A) where one might expect large scale wind energy projects to be concentrated. This aspect carries considerable weight. SSA A has been the subject of further detailed study by Arup. I attach significant weight to the findings of that study which suggest that the appeal site performs well when compared to many other sites within SSA A. However not all sites within SSAs will be suitable. I must weigh the advantages of renewable energy from this proposal against any harmful effect of the proposal in judging this particular case on its merits, having regard to the Development Plan and the other material considerations."
"13. Mr Roden's evidence included an assessment of the visual impact on most dwellings closest to the turbines together with representative assessments of the effect on groups of dwellings such as at Soar and Bylchau. He accepted that they were a representative selection identified off the ordnance survey map. It is perhaps unfortunate that the assessment omitted Nant Glyn, the second closest dwelling to the east. However I identified several other dwellings close to the site which were not included. These included the new bungalow on the approach track to Ty Newydd, Pennant Isa and the farm house on the lane leading up to Pen Y Lon. I was not trying to identify every dwelling which might not be affected but trying to assess the general level of visual impacts over a range of properties. However I came to the conclusion that this area contains a relatively large number of dwellings scattered across the countryside to the north and east of the site which would experience significant visual effects from the proposal.
14. In terms of those effects becoming such that they would be unacceptably overbearing to residents I consider that they include the following properties; Wern Uchaf, Nant Gwyn, Rhiwiau, Cwm-y-rhinwedd, Pennant Isa, Nant-y-Garreg, Nant-y-Lladron, the Bungalow at the garage on the A543, the Sportsmans Arms, and the new bungalow on the approach to Ty Newydd. From at least all these properties the views of the turbines would be such that the presence of such large turbines located on the elevated appeal site would be overbearing.
15. The cumulative effect of this proposal together with the existing and consented turbines would result in the local community having the appearance of becoming increasingly surrounded by turbines on all the high ground to the south and west. I consider that this proposal would be in conflict with UDP policy MEW10 criteria (vii)."
"21. Turning to the more general effects of noise on the amenity of local residents I have no doubt that these turbines could, with the suggested, conditions, operate within or at the levels suggest in ETSU 97. These are the standards normally applied in Wales, however they are for guidance and are not absolute vales. The problem is that those noise levels do not mean that the turbines cannot be heard. Local residents gave a clear account of the noise from the existing turbines which they currently experience. Some of the descriptions may have been a little colourful but they do indicate a level of nuisance which is experienced and which would not normally trigger a breach of the planning conditions on Tir Mostyn.
22. The experience of the noise is affected by the wind direction. On my visits in the area on the Thursday and Friday I experienced the difference as a result in the change of the wind direction. On the Thursday the wind was blowing towards the turbines from the dwellings in the valley opposite and I could not hear them. On the Friday the wind was blowing in the opposite direction and I could hear the turbines in a variety of locations where there was no other noise source. The consented Brenig turbines together with any at Clocaenog generally lie to the south of most of the neighbouring dwellings in the valley and to the south west of Nantglyn village centre. This means that any additional cumulative noise impact will be experienced when the wind blows from a southerly direction.
23. Gorsedd Bran lies to the west and south west of the dwellings most affected by Tir Mostyn noise. This means that the prevailing wind would introduce additional noise to the same dwellings when they might currently expect not to hear the existing turbines. This would significantly increase the general noise nuisance experienced by a significant number of local residents. This cumulative increase in noise, whilst likely to be within ETSU 97 levels, would result in a level of harm which would conflict with UDP policy MEW10 criteria (iv)."
"This report describes the findings of a Working Group on Wind Turbine Noise. The aim of the Working Group was to provide information and advice to developers and planners on the environmental assessment of noise from wind turbines. While the DTI (now BERR) facilitated the establishment of this Noise Working Group this report is not a report of Government and should not be thought of in any way as replacing the advice contained within relevant Government guidance.
The report represents the consensus view of the group of experts listed below who between them have a breadth and depth of experience in assessing and controlling the environmental impact of noise from wind farms. This consensus view has been arrived at through negotiation and compromise and in recognition of the value of achieving a common approach to the assessment of noise from wind turbines."
"The suggested noise limits and their reasonableness have been evaluated with regard to regulating the development of wind energy in the public interest. They have been presented in a manner that makes them a suitable basis for noise-related planning conditions or covenants within an agreement between a developer of a wind farm and the local authority."
"The report presents the findings ... and makes a series of recommendations that can be regarded as relevant guidance on good practice."
The report contains an important acknowledgment at paragraph 16, which is relevant in the context of the present case:
"The Noise Working Group is of the opinion that absolute noise limits and margins above background should relate to the cumulative effect of all wind turbines in the area contributing to the noise received at the properties in question. It is clearly unreasonable to suggest that, because a wind farm has been constructed in the vicinity in the past which resulted in increased noise levels at some properties, the residents of those properties are now able to tolerate higher noise levels still. The existing wind farm should not be considered as part of the prevailing background noise."
The report did not, however, have a specific contribution to make to a situation in which the issue was not noise level, but the frequency of occasions when noise intruded on amenity. It is, in addition, important to record the acknowledgment in TAN 8 that suitability of a site for development is ultimately a matter of judgment, even within the boundaries of an SSA.
"2.3 SSAs have been identified through a variety of means as outlined below in paragraphs 2.4-2.9 and in the Arup Final Report 2004. This approach addresses the issue of location of onshore wind facilities at a strategic all-Wales level. Local planning authorities are best placed to assess detailed location requirements within and outside SSAs in the light of local circumstances.
Strategic Search Areas (SSAs)
2.4 The 7 Strategic Search Areas (SSAs) are shown on Maps 1-8 [Clocaenog Forest is situated within SSA 8]. The SSA boundaries are at a 'broad brush' scale. Not all of the land within the SSAs may be technically, economically and/or environmental suitable for major wind power proposals; however the boundaries are seen as encompassing sufficient suitable land, in one or more sites, to deliver the Assembly Government's energy policy aspirations. It is a matter for local planning authorities to undertake local refinement within each of the SSAs in order to guide and optimise development within each of the areas. […]"
(1) On the one hand, the Inspector found that Tir Mostyn operated within its noise provision. On the other, the Inspector accepted the residents were suffering a "level of nuisance". Although the Inspector had explained that he had not used this term in its legal sense, the judge was unable to reconcile what the Inspector meant by these two findings, which appeared to be contradictory without further explanation.
(2) The judge observed that in paragraph 22 of his reasons the Inspector had simply concluded that when the wind was in a particular direction the development would contribute cumulatively to the noise impact. Mr Moffett has submitted that the judge plainly misunderstood the Inspector's reference in paragraph 22 to "cumulative noise", thinking that he was referring to that produced by the proposal rather than by the consented development at Brenig. I am not at all sure that Mr Moffett is right about that.
(3) The judge understood the Inspector to say in paragraph 23 that "the proposed development would introduce noise to residences currently affected by noise from Tir Mostyn at a time when otherwise those residences would not be affected by noise". At the same time, the Inspector had said that noise levels would not exceed ETSU indicative levels. He was, therefore, in the judge's view, contradicting himself. He was on the one hand finding that the development conformed with TAN 8 policy, and on the other that it was in conflict with local policy MEW 10. The judge expressed a tentative view that the Inspector's conclusion that noise levels were unacceptable was unreasonable in the Wednesbury sense. While the judge would not find the decision to be Wednesbury unreasonable on this ground in case the evidence was more compelling than the Inspector had described in his report, his reasons were nevertheless singularly lacking.
(4) Paragraph 21 was perfunctory in its description of evidence from the local residents. It did not, in the judge's view, begin to explain how that evidence might be sufficiently compelling to displace the powerful case presented by the developer on the issue of noise. The Inspector had not even identified the properties from which he had made his observations, which in view of the fact that the nearest residents to a proposed turbine was more than 500 metres away, was the "very least" that was to be expected. There was simply no means of knowing from the decision letter whether it was correct to conclude that a significant increase in noise would be caused to a significant number of local residents.
"There is an emerging best practice approach within the onshore wind industry of siting development a minimum of 500m from residential properties (for noise/amenity and safety reasons)."
Reference to the emerging standard appears also in the terms of TAN 8.
"36. The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the 'principal important controversial issues', disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision-maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision."
"38. Mr Taylor made a detailed critique of the reasoning of the Inspector and the Secretaries of State on the noise issues. While the degree of technical detail to which he descended was unusual for a legal challenge of this kind, I accept that to a large extent it was necessary to set the groundwork for his submissions of principle. Indeed, it was part of his case that noise is a technical subject, which parties are encouraged by Government policy guidance to approach with the benefit of technical advice and according to established criteria. Thus for example, PPG 24 Annex 3 gives specific guidance on the assessment of noise from aircraft and invites those concerned to seek technical advice on the applicable indices and noise contours from the Department of Transport and the Civil Aviation Authority. Thus, in this case the main parties were assisted by technical witnesses, and the Inspector had the assistance of a technical assessor to evaluate the evidence. This no doubt is a recognition that the subjective reactions of individuals to the prospect of an airport use, based on their experiences elsewhere, may not be a very objective or reliable way of judging the matter, and that there are now well developed and tested means of reaching an evaluation."
Having considered some of the details of the submissions made, my Lord turned at paragraph 44 to the legal effect of those submissions:
"44. I have considerable sympathy with Mr Taylor's general point, and his comments on the individual points I have mentioned. Given the time and expense on technical noise evidence, which attempted to follow the guidance in PPG 24 and other official advice, it is unsatisfactory that at the end of the day it is not clear how the conclusions of the Secretaries of State relate to that guidance or to the technical evidence based on it.
45. Mr Taylor's difficulty however, is to convert this into a point of law, or to show that it would have affected the ultimate decision. It is clear that as a matter of law, the Secretaries of State and the Inspector were entitled to reach their own conclusions on the noise issue, even though that might conflict with the technical evidence before them. It seems to me highly desirable, as a matter of policy and practice, that the Inspector and the Secretaries of State should follow the framework established by the technical guidance and evidence. But I know of no principle of law which says that they are bound by that approach. This point was forcibly expressed by Forbes J in Westminster Renslade Ltd -v- Secretary of State [1983] 48P&CR 255, 263. He was there referring to the Inspector's conclusion, contrary to the appellants' technical evidence, that:
'the subjective reaction of the people affected would be quite out of proportion to the increase in noise level'.
He said:
'One asks oneself why on earth an expert planning inspector should not have come to that conclusion perfectly properly, even if he had every single noise expert in the country ranged on the appellants' side. It does not seem to me that he is saying that there is necessarily going to be a tremendous lot of noise; he is putting it squarely on the point that this is a deprived area in the sense that it is an area that is now deprived of any form of silence and that if one intrudes more noise into that sort of environment one must expect people to react pretty sharply. It seems to me that that is a perfectly proper view for an informed inspector to take, so, in my view, he was entitled to take the view that he did take.'
46. Although that case was not specifically referred to in argument before me, it expresses an approach which, in my view, is unassailable as a matter of law."
In other words, my Lord was emphasising the desirability of the application of a recommended noise assessment framework, notwithstanding that the Inspector was entitled to make his own judgment upon the evidence.
"...this proposal would be in serious conflict with the appropriate UDP policy. The benefits of the provision of renewable energy would not outweigh the benefits I have identified. The imposition of conditions would not overcome those strong planning objections."
"It is on the basis of my personal visits to the area that I made my judgments on the effect of the proposal ..."
"63. I am not persuaded that there is a base-line principle operating with the inflexibility suggested by Mr Norris when the issue of noise is under consideration either by a local planning authority or an Inspector upon appeal. Ultimately, a planning judgment has to be made about objections to a proposed development which relate to the noise generated by that development. However, as is clear both from TAN 8 itself and from policy MEW 10(iv) an objection to a proposed wind farm situated within an SSA which is based upon noise can only be justified if an Inspector reasonably concludes that the noise levels associated with the proposed development will be unacceptable.
...
68. In my judgment the Inspector is clearly correct when he says (as he does in paragraph 21 of the decision letter) that the indicative noise levels set out in ETSU-R-97 are guidance not absolute values. That is the clear effect of paragraph 2.16 of TAN 8. It follows that there may be circumstances in which it is open to a local planning authority or an Inspector to conclude that noise levels associated with a wind farm are unacceptable notwithstanding compliance with ETSU-R-97. However, on the basis of that which is set out in the decision letter, the Inspector's statement in these proceedings and the documentation put before me, my tentative view is that this conclusion is not justified. On that basis it would be my duty to hold that the Inspector had reached a decision on the issue of noise which was unreasonable in the Wednesbury sense."
"... result in the local community having the appearance of becoming increasingly surrounded by turbines on all the high ground to the south and west."
In my judgment, the Inspector could hardly have been more explicit in his demonstration of the effect of the proposal.
Lord Justice Elias:
Lord Justice Carnwath:
"Luckily, our prevailing wind is southerly, meaning that only when southerly wind blows we experience nuisance. The Gorsedd Bran site is to our southwest, i.e. the direction from which the wind blows most frequently. We know that should these turbines be approved, we will be subject to many more days and nights of disturbance. We therefore object strongly to the application."
That reflects the concerns of a number of residents, and was clearly an issue that the Inspector had to consider. My observation is that it is surprising if, as we are told, that situation is not dealt with in the relevant guidance. We have heard that the ETSU guidance deals with the cumulative impact in respect of noise levels, but it does seem odd that it does not deal in terms with duration. That perhaps needs to be looked at in order to meet Mr Norris's reasonable concern that developers should have guidance on which they can work in planning future schemes.
Order: Appeal allowed.
MR MOFFETT: My Lords, I am very grateful for that. It does not make a great deal of difference, but could I two points in relation to the judgment at the beginning. First is a very small correction if I may suggest to my Lord, Lord Justice Pitchford. My Lord, at the outset of your judgment you referred to the Inspector summarising the nature of the local area. I believe that your Lordship is reading from the statement of common ground, which was cited by the learned judge; so it is only a very small point.
Just one further point, and I put this broadly. At a number of points in your Lordships' judgments you referred to the frequency of the noise; of course "frequency" --
LORD JUSTICE CARNWATH: Yes, I was wondering –
MR MOFFETT: It is simply a technical --
LORD JUSTICE CARNWATH: Maybe "duration" is a better word.
MR MOFFETT: I was wondering whether, on looking at the judgments after the shorthand writer is finished with it, perhaps, yes, a different term might be clearer to a reader who has not been in court and did not hear the arguments.
LORD JUSTICE CARNWATH: Can we use "duration"?
MR MOFFETT: I think that would be -- certainly the term I used in argument.
LORD JUSTICE CARNWATH: Yes, thank you.
MR MOFFETT: So I am grateful for you listening to those points. That being your Lordship's judgment, I simply ask that the order of Wyn Williams J be set aside, and that the Welsh Ministers have their costs here and below.
LORD JUSTICE CARNWATH: That will result in the refusal standing.
MR MOFFETT: Yes.
LORD JUSTICE CARNWATH: And you ask for your costs here and below?
MR MOFFETT: Yes.
LORD JUSTICE CARNWATH: Are we asked to assess them or is it --
MR MOFFETT: No, I am not asking for summary assessment.
LORD JUSTICE CARNWATH: Mr Norris, your –
MR NORRIS QC: My Lord, I cannot resist that, but may I suggest a further correction to something that my Lord, Lord Justice Pitchford, said on two occasions, simply for the record? My Lord said twice that I had submitted that the TAN 8 constituted a policy presumption in favour of development.
LORD JUSTICE PITCHFORD: That was my gloss on your argument.
MR NORRIS QC: It is a side gloss, but it has a particular meaning in the context.
LORD JUSTICE PITCHFORD: What would you prefer?
MR NORRIS QC: What I would prefer, what I actually said was that it was powerfully persuasive, or constituted substantial support for the policy, and you might add that I did submit that one should depart from it only for very good reason.
LORD JUSTICE CARNWATH: All right. Well, thank you very much. I think that is enough corrections on our judgments. So I thank you both. So the appeal will be allowed, which will mean that the Inspector's decision will be restored, and the respondent will pay the appellant's costs, subject to a detailed assessment if not agreed. That is here and below?
MR MOFFETT: Yes.
LORD JUSTICE CARNWATH: Thank you both very much.