COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM QUEEN'S BENCH DIVISION
OF THE HIGH COURT OF JUSTICE
Mr Justice Christopher Clarke
Strand, London, WC2A 2LL |
||
B e f o r e :
Vice-President of the Court of Appeal, Civil Division
LORD JUSTICE MOSES
and
LADY JUSTICE HALLETT
____________________
RTS Flexible Systems Ltd |
Appellant |
|
- and - |
||
Molkerei Alois Müller GmbH & Co KG |
Respondent |
____________________
WordWave International Limited
A Merrill Communications Company
190 Fleet Street, London EC4A 2AG
Tel No: 020 7404 1400, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Stuart Catchpole QC and Charles Manzoni (instructed by Addleshaw Goddard LLP) for the Appellant
Kenneth Maclean QC and Michael Fealy (instructed by Pinsent Masons LLP) for the Respondent
Hearing dates : 11th, 12th November 2008
____________________
Crown Copyright ©
Lord Justice Waller :
Introduction
The Facts
"As a final point, bearing in mind the importance of the project timescales, we would also be quite prepared to commence work even before signature of a contract, on the basis of a Letter of Intent/Instruction to Proceed".
Quotation J
The Letter of Intent
"Project: Build, delivery, complete installation and commissioning by RTS Advanced Robotics Limited ("RTS") of the Automated Pot Mixing Lines 1 & 2 and the De-Palletising Cell ("the Equipment") for the Repack line ("Repack Line") within the Repack facility in Market Drayton of Molkerei Alois Müller GmbH & Co (UK Production)("Müller").
Thank you for your mail dated 16th February 2005 setting out your offer (number FS04014 – Issue J) to supply the Equipment to Müller ("the Offer")
Please accept this letter of intent as confirmation of our wish to proceed with the Project as set out in the Offer subject to the following terms:-
(i) The agreed price for the engineering, build, delivery, installation and commissioning as set out in the Offer is GBP 1,682,000 (one million six hundred and eighty two thousand sterling) . . .
(ii) RTS is now to commence all work required in order to meet Müller's deadlines set out in the Offer to allow commencement of full production by Müller on the Repack Lines by 30th September 2005. Delivery of line also to be in accordance with the timetable set out in the Offer.
(iii) That the full contractual terms will be based on Müller's amended form of MF/1 contract and the full terms and the relevant technical specifications will be finalised, agreed and then signed within 4 weeks of the date of this letter. Prior to agreement on the full contractual terms, only Müller shall have the right to terminate this supply project and contract. However, should Müller terminate, Müller undertakes to reimburse RTS for the reasonable demonstrable out of pocket expenses incurred by RTS up to the date of termination. Müller will not be liable for any loss of profits (whether direct or indirect), loss of contracts, loss of anticipated savings, data, goodwill and revenue or any other indirect or consequential loss arising from such termination. No further legal rights or remedies shall be available to RTS upon such termination.
Please confirm your acceptance of the above by signing below where indicated.
This letter of intent shall be governed by English law and subject to the exclusive jurisdiction of the English Court."
"2. The Letter of Intent section (iii) also states that Müller will:
"reimburse RTS for the reasonable demonstrable out of pocket expenses incurred by RTS up to the date of termination". During the four week period covered by this Letter of Intent RTS will incur costs in both engineering time and in order to meet the project programme, will have placed orders for the long lead items such as robots, conveyors and tray erectors. In the event of Termination we would require reimbursement for these costs, including cancellation costs of subcontract commitments as well as any out of pocket expenses, albeit without profit".
"The parties did not contemplate that, in the absence of finalisation and signature within the specified timescale (or any agreed extension), RTS would be bound to continue with a project for which the applicable terms had not been agreed. Consistent with that the Letter of Intent said nothing about when any part of the price would be payable and gave Müller a right to cancel upon payment only of expenses and cancellation costs – a right that was entirely reasonable during a four week period but inappropriate for a contract for the entire project. The payment schedule in the Quotation specified a series of percentage payments, but the first of those was the 30% of TCV payable on receipt of order and the Letter of Intent was not an order."
Issue 1.1. What are the terms of the contract formed by the Letter of Intent and RTS' letter of 1 March 2005 and what are the obligations of the parties under it?
Answer:
a) The agreed price for the engineering, build, delivery, installation and commissioning of the work set out in the Quotation was to be £1,682,000;
b) RTS was bound to embark on such work as was necessary to ensure the provision of the equipment to be supplied by it in accordance with the provisions of sections 4 – 8 of Quotation J and the timetable set out in Appendix 7 thereof. Commissioning was to be completed by 30th September 2005 and the equipment was to be ready for production (but not full production) and Site Acceptance Testing as shown in that Appendix at that date;
c) Müller and RTS were to have a period of four weeks from 21 February 2005 to finalise, agree and sign a contract based on Müller's amended MF/1 form of contract. Following the expiry of that period the contract would terminate;
d) Prior to agreement of the full contractual terms and conditions based on Müller's amended MF/1 contract, only Müller had the right to terminate the supply project;
e) If Müller did so terminate or the term of the contract expired, it would reimburse RTS for the reasonable, demonstrable out of pocket expenses incurred by RTS up to the date of termination, including the cost of engineering time, cancellation costs of subcontract commitments, and any out of pocket expenses, but without profit;
f) RTS would have no further legal right or remedy on termination and Müller would not be liable for any loss of profit (whether direct or indirect), loss of anticipated savings, data, goodwill and revenue or any other indirect or consequential loss arising from termination;
g) There were no exclusions or limitations of liability in the contract.
Termination of the Letter of Intent contract
"Thank you for your letter of 1st March and your acceptance (subject to the qualifications you list) of the terms of the letter of intent dated 21st February 2005.
In accordance with section (iii) of the letter of intent above, we agreed that a formal contract with full contractual terms would be executed within 4 weeks of the date of the letter of intent. We have now mutually agreed to extend this period up to and including 16th May 2005 during which period the terms of the letter of intent will continue to have full force and effect.
Please confirm your acceptance of the above by signing below where indicated."
Mr Bradford signed a copy of this letter on behalf of RTS. The parties thereby agreed, or confirmed their agreement, to the qualifications made by RTS in its letter of 1st March; and to the fact that the period for execution of a formal contract would expire on 16th May.
"Given that the contract is now almost agreed we hereby confirm that the expiry date for the current letter of intent can be extended until the 27th May 2005, or, if sooner, the date the contract is actually signed…"
Negotiations continued
"For delay in delivery of the equipment, liquidated damages were to be 0.5% of the Contract Price for each week of delay subject to a maximum of 2.5% (i.e. five weeks delay);
For delay in completion, liquidated damages were to be 0.5% of the Contract Price, again subject to a maximum of 2.5%;
For each week in which the equipment did not pass the specified performance tests, liquidated damages were to be 0.5% of the Contract Price subject to a maximum of 2.5% (after which, following the scheme of the MF contract, Müller would be entitled to terminate the contract and take such steps as were necessary at the expense of RTS to ensure that the equipment did pass the performance tests);
Subject to certain exceptions, there was an overall cap on RTS's and Muller's liability under the Contract equivalent to the Contract Price.
Clause 27.8 also envisaged that there would be liquidated damages payable if the equipment failed to meet certain Key Performance Indicators during the Defects Liability Period, although the indicators and the amount(s) of any liquidated damages were left blank in Schedule 11 attached to the draft."
"Please find attached contract with final tweaks. Perhaps you can drop me a quick email confirming you are happy – we can then all concentrate on completing the schedules."
Schedule 1: General Conditions extending to 48 paragraphs.
Schedule 3: A page headed "Functional Design Specification". This is a document which states the intended functionality of the RTS equipment. It is usually derived from the User Requirement Specification: see below.
Schedule 4: A page headed "User Requirement Specification"
This is usually compiled by the client but, on this occasion, was lifted from RTS' Quotation K at Müller's request.
Schedule 5: A3 page schedule, drafted by Müller, divided into Part 1 "Tests on Completion" and Part 2 "RTS Tests".
Schedule 6: A two page schedule, drafted by Müller, headed "Performance Tests". The last paragraph of this read as follows:
"THIS SCHEDULE NEEDS TO PROVIDE THAT IF THE TEST WITHIN A CERTAIN PERCENTAGE OF THE REQUIRED LEVEL LDs WILL APPLY AND THE EQUIPMENT WILL STILL HAVE "PASSED". IF THE PERCENTAGE ACHIEVED IS LOWER THAN THAT SPECIFIED BY LDs (I.E. LOWER THAN THE MAXIMUM PAYOUT UNDER LDS) THE EQUIPMENT WILL HAVE FAILED THE TEST AND THE OTHER REMEDIES WILL BE AVAILABLE TO THE PURCHASER"
Schedule 7: An Advance Payment Guarantee to be given by RTS' parent.
Schedule 8: A defects liability demand guarantee also to be given by RTS' parent.
Schedule 9: This made provision for the supply of a list of stock items and wear and non-wear parts.
Schedule 10: A description of what the programme needed to include.
Schedule 11: An empty table of Key Performance Indicators, Performance required and Liquidated Damages.
Schedule 12: A page headed "Certificates of Payment" together with a form of Delivery Certificate, Completion Certificate and Final Certificate of Payment.
Schedule 13: A list of the operating manuals and other drawings and maintenance schedules required.
Schedule 14: A Schedule dealing with Training Requirements
Schedule 15: A Schedule headed "Health and Safety Requirements" but otherwise blank
Schedule 16: A Schedule headed "Free Issue Equipment" but otherwise blank.
Schedule 17: A Schedule headed "Site Preparations" but otherwise blank.
SCHEDULE | UNDERSTOOD STATUS | MY COMMENT |
1 | Not referred to in the e-mail | No need. Schedule 1 consisted of the General Conditions. |
2 | Assumed not required as the payment schedule is included in the body of the contract. | This schedule is described in the Contract as setting out the price; but that is in the General Conditions in Schedule 1 anyway. |
3 | FDS – currently being reissued Brown suggested it should be referred to rather than incorporated. |
The FDS was later agreed: see the RTS e-mail of 29th June and paragraph 52 |
4 | URS. Agreed that section 4 of the Quotation would form the URS, which was attached. | The URS had the appendices referred to at paragraph 26 |
5 | Agreed that RTS Test plan would form this Schedule. With Müller for approval. | The RTS Test plan was later agreed: see the RTS e-mail of 29th June: paragraph 52 |
6 | RTS TEST PLAN | RTS regarded its Test Plan as covering the ground of Schedules 5 and 6 and Müller was happy with that provided that it did so. But the only version of Schedule 6 contained Müller's wording. |
7 | Advance Payment guarantee already agreed. | The guarantee had been attached to the e-mail of 16th May |
8 | Defect Liability guarantee – RTS' parent company to approve. | A draft had been attached to the 16th May e-mail. The parent company never approved it. |
9 | To be completed during the project. | Part 1 related to stock items. It was never completed. Part 2 contains provisions for the durability of Wear Parts, which is capable of standing on its own. |
10 | Approved programme attached | The attachment was either as in Quotation I or Quotation J. This programme was overtaken by the overall project plan and installation-at-Müller plan referred to in paragraph 52 below. |
11 | KPIs agreed: attached. | These included details of the Performance Required and Liquidated Damages |
12 | Müller to complete. | This related to Certificates of Payment. Never completed. |
13 | To be completed during the project. | This related to operating manuals. Never completed, It would not have been possible to provide them at the time. |
14 | To be completed during the project. | This related to Training Requirements. Never completed |
15 | Müller to provide details. | This related to Health and Safety Requirements. Never completed |
16 | As per attached document. | The attached document contained the Assumptions for Free Issue Equipment for the Project |
17 | Müller to provide site preparation details. | This does not seem to have been provided, but the site was prepared. |
The variation
Payment
Judge's conclusions
"As is apparent from the above, after the Letter of Intent contract expired RTS continued to build the Equipment, delivered it to Müller and were partially paid for it. In those circumstances the court strongly inclines to concluding that the parties have entered into some contract even though such a contract cannot be spelt out by a classic analysis of the sequence of offer and acceptance.
As Steyn LJ, put it in Trentham v Archital Luxfer [1993] 1 Lloyds LR 25:
"Secondly, it is true that the coincidence of offer and acceptance will in the vast majority of cases represent the mechanism of contract formation. It is so in the case of a contract alleged to have been made by an exchange of correspondence. But it is not necessarily so in the case of a contract alleged to have come into existence during and as a result of performance…..The third matter is the impact of the fact that the transaction is executed rather than executory. It is a consideration of the first importance on a number of levels… The fact that the transaction was performed on both sides will often make it unrealistic to argue that there was no intention to enter into legal relations. It will often make it difficult to submit that the contract is void for vagueness or uncertainty. Specifically, the fact that the transaction is executed makes it easier to imply a term resolving any uncertainty, or alternatively, it may make it possible to treat a matter not finalised in negotiations as inessential. In this case fully executed transactions are under consideration. Clearly, similar considerations may sometime be relevant in partly executed transactions. Fourthly, if a contract only comes into existence during and as a result of performance of the transaction it will frequently be possible to hold that the contract impliedly and retrospectively covers pre-contractual performance…"
Müller's submissions
Müller submits that, although the parties reached a final draft of the contractual terms and conditions, namely Schedule 1, which contains the general conditions, as modified in the e-mails of 19th and 25th May, and 5th July 2005 set out in paragraphs 51-2 above, that final draft never became binding on the parties. This is because it was the parties' intention that detailed terms negotiated by them would not have contractual effect until the documentation i.e. the contract and the accompanying schedules, was formally executed and signed. That that is so appears from:
"(a) the Letter of Intent which referred to the full terms and the relevant technical specifications being finalised, agreed and then signed within 4 weeks of the date of that letter;
(b) Mr Morris' e-mail of 13th May, which referred to the Letter of Intent lasting until 27th May or, if sooner, the date the contract is "actually signed";
and is consistent with
(c) the evidence of Mr Brown of RTS, in paragraph 46 of his witness statement, referring to his e-mail of 26th May 2005 that:
"My view was that whilst we had agreed the wording in principal (sic), until the whole contract including the schedules had been compiled as a complete document and signed as accepted by RTS then it wasn't enforceable. Whether this is right or not, I don't now know, but it was what I thought then. Therefore, to my mind, the milestone event at which the terms and conditions of the anticipated contract were agreed and in force was when RTS signed the document"
Accordingly the contract between the parties and the obligations of RTS and Müller, are – Müller submits - to be found in the following documents which constitute an agreed description of the goods and services which RTS was to provide:
(i) the documents attached to the email of 26th May 2005 namely:
(a) the URS and its Appendices save that the Parent Company guarantee was never given and the Provisional Project Plan was overtaken by the documents at paragraph 52 above in June 2005;
(b) the KPIs;
(c) the Assumptions for Free Issued Equipment ("the Assumptions"); and
(ii) the documents attached to Mr Guest's first and second e-mails of 29th June namely:
(d) the FDS;
(e) the Test Plan;
(f) the overall project plan (which superceded the delivery programme attached to the e-mail of 26th May) which was to form Schedule 10;
(g) the installation plan;
(h) the Test and Build Schedule.
69. Müller's payment obligation was to pay £ 1,682,000 plus VAT in return for the goods and services that RTS was to provide as specified in the above documents. No further contractual terms as to payment having been agreed, RTS is not entitled to payment of the balance of the contract price until it has completed substantial performance.
70. This submission is a departure from the contention advanced by Müller in a letter to RTS of 12th April 2006 which asserted that "the contractual terms for the engagement of RTS were clearly agreed following discussion that took place throughout March, April and May 2005"; and that "An exchange of e-mail correspondence between the respective contract administrators at that time …. Confirmed that all of the key contract terms were settled and agreed". The letter purported to rely on clause 34.1.2 of the conditions in Schedule 1, which provides, inter alia, for the purchaser to give notice to remedy defects, and, in default of remedy within 30 days, a power to terminate.
RTS' submissions
71. RTS' primary submission was (i) that the Letter of Intent contract incorporated Quotation J, including RTS' standard terms, (ii) that it did not expire in May 2005, and (iii) that it was never replaced by any new contract. I have rejected (i) and (ii). In that event, RTS' alternative submission is that, if there was a new contract, it incorporated the agreed amended MF/1 conditions. If, as Müller submits, most of the Schedules were incorporated, so also were the terms and conditions in Schedule 1, which is the basis of the contract. These submissions are a departure from the contentions made by RTS' solicitors in their letter of 10th August 2006. In that letter Addleshaw Goddard, in setting out RTS' case on the contractual position, contended (a) that the parties' conduct was governed by the Letter of Intent until 16th May 2005 after which "a separate contract arises"; and (b) that the terms of Contract 45003600589 i.e. the contract enclosed with the e–mail of 16th May 2005 were not enforceable. This is consistent with the note to the accounts of RTS' parent for the year ending 31st December 2006, which records RTS' dispute with Müller "pursuant to a contract entered into during May 2005".
My conclusion
72. In my judgment Müller's submissions are well founded. After the lapse of the Letter of Intent the parties reached full agreement on the work that was to be done for the price that they had already agreed. It is, as Lord Justice Steyn contemplated, unrealistic to suppose that they did not intend to create legal relations. The natural inference is that their contract was that RTS would carry out the agreed work for the agreed price. It was not essential for them to have agreed the terms and conditions and they did not do so. In this respect they continued after the expiry of the Letter of Intent just as they had before, i.e. calling for and carrying out the work without agreement as to the applicable terms.
73. I decline to infer that the parties' contract included the final draft version of the MF/I conditions for a number of reasons. Firstly, Müller's Letter of Intent and its e-mail of 13th May 2005 indicated that the final terms were not to be contractually agreed until signature.
74. Secondly, the contract sent with the e-mail of 16th May was designed to operate as a composite whole, consisting of (a) the basic two page, seven clause contract, and (b) the 17 schedules that are annexed to it and referred to in the general conditions which constitute Schedule 1. Although many of these Schedules were agreed several were not. In particular it was not agreed what Schedule 6 would contain. The words in capitals set out in paragraph 48 above represented a proposed, but never agreed, refinement – to give Müller some ampler remedy than liquidated damages if the performance of the equipment was lower than that degree of non performance which would give rise to the maximum liquidated damages.
75. Thirdly, the parties did not proceed on the basis of the conditions. RTS did not procure the provision of the Advance Payment Guarantee (Schedule 7), which, under the conditions, was required to be procured prior to the advance payment being made. Schedules 15 and 17, which address matters relevant from the start of the contract, were not completed. Müller did not appoint an Engineer. Payment was not made in accordance with the application and certification procedure laid down in clause 11 and the procedure for Changes to the Contract laid down by clause 39 was not followed. The dispute procedure required by clause 41 was not followed.
76. Fourthly, clause 48 of the general conditions provides that:
"This Contract may be executed in any number of counterparts provided that it shall not become effective until each party has executed a counterpart and exchanged it with the other"
The contract was not executed nor were any counterparts exchanged.
77. I hold, therefore, that, by no later than 29th June 2005 the contract between the parties, which was to apply retrospectively, was that RTS was to provide the goods and services specified, and comply with the obligations set out, in the documents set out in paragraph 68 above, subject to the conditions specified therein."
Arguments in the Court of Appeal
"In the negotiations and during performance of phase 1 of the work all obstacles to the formation of a contract were removed. It is not a case where there was a continuing stipulation that a contract would only come into existence if a written agreement was entered into. Plainly the parties intended to enter into binding contractual relations."
"The real difficulty is to be found in the factual matrix of the transaction, and in particular the fact that the work was being done pending a formal sub-contract the terms of which were still in a state of negotiation. It is, of course, a notorious fact that, when a contract is made for the supply of goods on a scale and in circumstances such as the present, it will in all probability be subject to standard terms, usually the standard terms of the supplier. Such standard terms will frequently legislate, not only for the liability of the seller for defects, but also for the damages (if any) for which the seller will be liable in the event not only of defects in the goods but also of late delivery. It is a commonplace that a seller of goods may exclude liability for consequential loss, and may agree liquidated damages for delay. In the present case, an unresolved dispute broke out between the parties on the question of whether CBE's or BSC's standard terms were to apply, the former providing no limit to the seller's liability for delay and the latter excluding such liability altogether. Accordingly, when, in such a case as the present, the parties are still in a state of negotiation, it is impossible to predicate what liability (if any) will be assumed by the seller for, e.g, defective goods or late delivery, if a formal contract should be entered into. In these circumstances, if the buyer asks the seller to commence work 'pending' the parties entering into a formal contract, it is difficult to infer from the [seller] acting on that request that he is assuming any responsibility for his performance, except such responsibility as will rest on him under the terms of the contract which both parties confidently anticipate they will shortly enter into. It would be an extraordinary result if, by acting on such a request in such circumstances, the [seller] were to assume an unlimited liability for his contractual performance, when he would never assume such liability under any contract which he entered into."
(Note: I have put 'seller' in parenthesis since, although the report reads 'buyer', Robert Goff J must have meant 'seller'.)
"79. On its proper construction, clause 48 of the amended form MF1 prevented a contract on those terms taking effect without signature by the parties and RTS plc. It does not follow that in the absence of a signed agreement there could not be a binding contract between the parties on some other terms as a result of their conduct. "
Lord Justice Moses
Lady Justice Hallett
First issue: Should there be declaration of entitlement to quantum meruit or should the answer to Issue 1.2.4 read "The payment obligation of the defendant (if any) is by way of quantum meruit"?
Second issue: Should the judge's order under which he reserved the bulk of the costs to the trial judge, but made an order for costs on certain issues be varied in relation to those issues?
Third issue: The costs of the appeal.
The fourth issue: Should the judge's order of an interim payment of £65,000 be varied?
The final issue: Permission to appeal to the House of Lords.