A1/2008/2608 |
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEENS BENCH DIVISION
MR JUSTICE COULSON
HT07/260
Royal Courts of Justice Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE WALL
and
LORD JUSTICE AIKENS
____________________
PERSIMMON HOMES (SOUTH COAST) LIMITED |
Appellant / Claimant |
|
- and - |
||
(1) HALL AGGREGATES (SOUTH COAST) LIMITED (2) CEMEX UK PROPERTIES LIMITED |
Respondents/ Defendants |
____________________
Mr Tom Keith (instructed by Messrs Eversheds LLP) for the Respondents
Hearing dates : Tuesday 7th, Wednesday 8th & Thursday 9th July 2009
____________________
Crown Copyright ©
Lord Justice Rix :
"Of course the difficulty was that many of these costs could not be accurately ascertained in December 1999, because the precise scope of the necessary rehabilitation works had not been defined. It appears that the parties decided that the best way of dealing with this problem was to calculate the initial purchase price by taking the notional value as the starting point, and deducting from an estimated figure for the costs of the necessary rehabilitation works. These were referred to as "benchmark costs", and they were designed to represent the parties' best estimate of the costs of those works at the time that the Sale Agreement was entered into. However, those benchmark costs would be capable of adjustment, when greater certainty was possible, and that adjustment would, in turn, lead to an adjustment in the purchase price. That is the genesis of the clause 7A mechanism."
I shall set out clause 7A below. It is headed "Price Adjustment".
The Sale Agreement
"The purchase price for the land is £29,892,372. This is to be paid in 7 instalments. It is based on a Gross Land Price of £45,830,872, which equates to £587,500 per net acre (78.01 net acres)…
The Purchaser's costs are to be deducted from the Gross Land Price. These are to be calculated within 6 months of the sale agreement. An estimation has been made of these in Schedule 5 of the Agreement of £15,938,500 to give the purchase price. If the costs are different after 6 months then there will be an adjustment of price. The schedule 5 costs are deliberately low so as to focus everyone's minds to keeping them low. However, I do anticipate them increasing to near Persimmon's figures of £19.7m, which would reduce the price by about £3.8m i.e. the purchase price will be approximately £26 million. The majority of the costs will be calculated either by going out to tender to contractors or they will be figures supplied by statutory undertakers providing services and so will be the lowest achievable. The remaining costs will be calculated with the assistance of Quantity Surveyors…
The above summarises the sale contract with Persimmon…"
"7A.1 Within 6 months of the date hereof the parties shall endeavour to agree final figures for the Costs (the figures in the table of Costs being provisional estimated figures) and the parties shall have regard to any projected increase in the Costs due to the time period for the incurring of Costs in any such agreement and if such figures are not agreed by the end of such period of 6 months then the determination of the outstanding Costs (and any projected increase thereof as above) shall be referred to an Independent Engineer…
7A.3 The Independent Engineer shall act as an expert and not as an arbitrator (unless he shall refuse to act as an expert when he shall act as an arbitrator) but before making his determination he shall afford to each party the opportunity to deliver to him written representations…
7A.4 The Independent Engineer shall make his determination as soon as practicable but in any event within two (2) months from the date of his appointment
7A.5 Unless the Independent Engineer has failed to observe the procedures specified in this Clause then his determination shall be final and binding on the parties
7A.6 Following the agreement or determination of the Costs the Price shall be adjusted by a sum equal to the difference between the total of the Costs as so agreed or determined and the total of the Costs set out in the table under the column "benchmark costs" (to the effect that if the final figure of Costs is more than the figure for the benchmark costs the Price shall be reduced by the amount of the difference and if the final figure for Costs is less than the figure for the benchmark costs the Price shall be increased by the amount of the difference
7A.7 The Price adjustment shall be apportioned equally between the various Parcels and (in respect of a Price adjustment for any Parcel the transfer of which has been completed) the Purchasers shall pay to the Vendors such sum as is due to the Vendors for that Parcel if the Price has been adjusted upwards and vice versa if the Price for that Parcel has been adjusted downwards but in either case without interest
7A.8 The parties shall use all reasonable endeavours to keep the Costs to a minimum which is commensurate with and in accordance with all necessary approvals for the Development
7A.9 In the event of the Costs being determined by an Independent Engineer pursuant to the provisions of this clause the Independent Engineer shall not have regard to the sums of money referred to in the Fifth Schedule as benchmark costs"
"14A.1 In this clause "Approvals" means:-
a) any drainage agreement which is required from Southern Water Services Limited relating to the provision of foul and surface water sewers and mains water supply forming part of the Development
b) any approval which is required from Hampshire County Council or Gosport Borough Council as the Highways authority relating to the construction and dedication of the Link Road and other highway works forming part of the Development
c) any drainage discharge approval which is required for the Development being secured from the Environment Agency
14A.2 The Vendors shall use all reasonable endeavours to procure the Approvals within 5 months of the date of this agreement
14A.3 The Purchaser shall be entitled to assume responsibility for negotiations as necessary to procure any Approvals that have not been procured by the Vendors under 14A.2
14A.4 The Vendors shall bear the Purchasers reasonable and proper costs (including the costs of consultants employed by the Purchaser) incurred as a result of the Purchaser taking over negotiations and procuring any Approvals pursuant to clause 14A.3
14A.5 The Vendors shall bear any additional and proper costs of works required by any Approval to the extent that such works have not been taken into account in the calculation of the Price (or vice versa if the reasonable and proper costs of such works is less than any allowance in respect of such works made in the calculation of the Price) with any dispute to be referred to an Independent Engineer on the same basis as set out in clause 7A."
"1. The Link Road constructed to a specification which accords with any approval which is required by the highways authority
2. Provision of public utilities for the Development to the Development site boundary at point 'X' as shown on the Plan. Provision of foul and surface water connections (including any pumping stations and balancing facilities) connected to all points on the boundary to the Development west of the Link Road to service the Development the positions to be in accordance with drawings approved by Southern Water…"
The clause 14A issue
The judgment
"49. However, it is plain to me that clause 7A operated on the basis that both parties intended that the figure for costs would be finalised within 6 months of the sale, so that an agreed purchase price could be fixed as quickly as possible. That explains the reference to the 6 months in clause 7A.1, and the prompt timetable required of the independent Engineer (who had to deal with any disputed items) set out in clauses 7A.3 and 7A.4. Therefore, whilst the costs figure for the necessary rehabilitation works, and thus the price, remained uncertain as at the date of the Sale Agreement, the parties were operating on the basis that both the costs and therefore the price, would be fixed within 6 months or so of the date of the Sale Agreement.
50. This is important when considered against the background of the proposed development. As noted above, the proposed development was going to last in excess of 7 years; at the time it was entered into, the parcel of land relevant to phase 7 would only be provided to Persimmon on 7 January 2006. Accordingly, on the proper construction of clause 7A, I conclude that the parties intended to agree the costs, and therefore the purchase price, long before the works at the site had been completed by Persimmon.
51. How could they do that where the costs of those works would not be known (at least with complete precision) for years? The answer can again be found in clause 7A.1. The clause envisaged that the parties would agree "final figures for the Costs" within 6 months based on their best estimate of the likely future costs. That estimation and agreement of future costs is what 7A.1 envisaged: it expressly referred to the parties having regard to "any projected increase in the Costs due to the time period for the incurring of Costs". Moreover, if such an agreement was not possible between the parties, then clause 7A.1 expressly envisaged that the binding determination of the outstanding costs by the independent engineer would also include "any projected increase" in those outstanding costs.
52. Accordingly, it is clear that clause 7A envisaged a situation in which the parties would either agree (or have determined by a independent engineer) long before the works had been completed, a figure for the necessary rehabilitation works, and therefore a final purchase price…
53. Furthermore, I am in no doubt that this mechanism was designed to fix figures for the costs, and therefore the price, which were both final and binding. There were two options open to the parties: either the costs would be agreed, or they would be determined by the independent engineer. Clause 7A.5 makes plain that the independent engineer's determination "shall be final and binding on the parties". In those circumstances, it seems to me that, once the costs of the necessary rehabilitation works, and therefore the price, had been fixed, either by agreement or by a determination of the independent engineer, those costs and that price could not be opened up. Subject to any part of the Sale Agreement which might provide to the contrary, those costs and that price could not be opened up. Subject to any other part of the Sale Agreement which might provide to the contrary, they would be final and binding."
The submissions
Discussion
Conclusion
Lord Justice Wall :
Lord Justice Aikens :
"The Vendors shall make available at no cost to the Purchaser such void space located within the Extraction Area for the deposit of surplus remediation materials arising from such parts of the Property as are remediated by the Purchaser and the Vendors shall provide the haulage for such surplus remediation materials at no cost to the Purchaser and the Vendors shall remediate the void space all in accordance with the Purchaser's reasonable requirements subject to there being sufficient capacity within the void space and provided such deposit and remediation is in accordance with any licence consent or permission that is necessary to permit such activity".
"The provision of the haulage and the remediation of the void space was to be carried out by RMC, but at a time and in a way that was convenient for Persimmon, subject to the proviso, of course, that Persimmon's requirements had to be reasonable".