IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM TELFORD COUNTY COURT
(HIS HONOUR JUDGE MITCHELL)
Strand London, WC2A 2LL |
||
B e f o r e :
SIR WILLIAM ALDOUS
____________________
INDUSTRIAL SERVICE (TELFORD) LTD | Claimant/Respondent | |
-v- | ||
CHARLES RANSFORD & SON LTD | Defendants/Appellants |
____________________
Smith Bernal Wordwave Limited
190 Fleet Street, London EC4A 2AG
Tel No: 020 7404 1400 Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
MR JAMIE MCCRACKEN (instructed by Martin Edwards, Shropshire TF11 8AL) appeared on behalf of the Defendant
____________________
Crown Copyright ©
"The defendants [that is the appellants] are in the business of the manufacture and sale of treated timber products. In 2003 the process which they were employing for the treatment of that timber was to impregnate it with a mixture of water and chemicals, those being chrome, copper and arsenic. By European Directive which was due to come into force during the latter part of 2004 the use of such materials was to be phased out and prohibited.
The [appellants] at this time had a plant which comprised three vacuum pressure treatment vessels, together with four holding tanks for the diluted mixture that were to be used and reused in the vacuum pressure tanks, and a concentrate tank to hold the undiluted mixture. The total amount of liquid which might be held in these tanks at any one time would be in the order of 200,000 litres, depending upon the amount in use and the amount of timber which had been treated. The whole area of that plant was surrounded by a bund, and in order to change over the production process from the prohibited chemicals to the new process it was necessary for the appellants to secure the thorough cleansing of that entire area of the old chemicals.
At the end of 2003 they were seeking quotations for the necessary cleaning and removing of the residues, and they approached a number of contractors who were asked to estimate to carry out those works. One of those contractors were the respondents, who are contractors in waste removal and disposal but who had no previous specific experience of handling this type of waste.
All the contractors who were approached, other than the [respondents], quoted on the basis of a price which would include a fixed sum for labour and then a price to be calculated at so much per litre of the materials removed, depending on the nature of material, that is to say whether it was waste or whether it was re-usable material.
The [respondents], however, quoted for a fixed price by means of a written quotation dated 31 October 2003 which incorporated the following:
'We have pleasure in enclosing our quotation for the cleaning and disposal of your treatment plant. To supply all necessary trained personnel to high pressure steam clean the pressure vessels, tanks and gullies as shown to us and remove all Celcure contaminated waste material to a licensed incinerator plant and issue all appropriate paperwork. For the sum of £4,845...'
- which, as the judge commented, was a VAT inclusive figure.
"It was obvious to the director of the appellants, a Mr Walters, who was principally concerned with the contractual arrangements, when he received the claimants' estimate, that it was possible that there might have been some misunderstanding, having regard to the discrepancy between the price which was quoted by the claimants and the price which he had been quoted by other contractors.
On 3 November Mr Walters telephoned the respondents' director, Mr Adrian Rawlins, to confirm the price and then wrote on that day as follows:
'The contract will require (as described) several visits to clear and clean the various holding tanks, bund area, and finish clearing of the unused CCA solution, ie concentrate tank, 3 pressure vessels, 2 holding tanks in bund area, 2 holding tanks above ground, and the mixing tank, also to include to bund and surrounding areas.'"
Then there is a new paragraph in that letter, which commences as follows:
"All arising sludge and 3% residual liquid to be removed from site in specialised tankers to a disposal site of your choosing for disposal, all in the accordance with the Environmental Protection Act 1990 sections 34 and section 62 Special Waste Regulations 1996."
The judge continued:
"Those letters were the only original contractual documents. It transpires that there was indeed a misunderstanding. Mr Rawlins' estimate was prepared on the basis that the removal would be of [the liquid used for] the cleansing of the plant by the claimants, together with what would be possibly a small residue of around 3% of the original contents of the tank, all of which he estimated for the purpose of his price could be removed as one part load in one tanker, the maximum load to be carried by a road tanker of this kind being apparently between 20,000 and 22,000 litres, and it was on that basis that he concluded the price."
The judge continued:
"He did not anticipate that the defendants would leave full or partially full holding tanks of the unused but mixed material. On the other hand, the [appellants'] director, Mr Walters, says that he was asking for a price on the basis that anything that was left in the holding tanks, including all unused material which might be there at the time and of which there might be an uncertain quantity, because no-one would know until the day arrived how much might still be there, was to be cleared by the [respondents]; and that the reference to 3% residual liquid in his letter of 3rd November was a reference to the chemical concentration of the liquid in the tanks which so he says consists of 3% chemicals and 97% water.
Following the [appellants'] acceptance of the [respondents'] estimate, plans for the appellants' overall scheme proceeded. In January there was a meeting conducted at the appellants' premises between the engineer responsible for the works, [a] Mr Berryman, the defendants and the contractors, to agree the schedule of works, and it was important that the timings should be specified so that there should be an agreed programme to secure the smooth transfer of the plant to the new process.
Mr Rowlands up to that stage still thought that he had estimated and would be providing for one tanker to visit only and take away a part load. During the course of the discussions in January, however, it became clear to him that three to four tankers would be required because what was being required by the engineer and the defendants was that there should be a serial emptying and transfer of the respective pressure vessels and accompanying tanks so as to secure a smooth transfer of the process; and that a tanker would have to visit at approximately one-week intervals to clear each of the three tanks.
Mr Rawlins still continued to labour under the misapprehension that he was dealing with cleansing and residues only and that the defendants would be disposing of the unused mixture which they then had in the holding tanks. That seems to be a view which was also obtained by Mr Berryman. He has told me [said the judge] during the course of his evidence that he, from his perspective, thought that the defendants would make arrangement either to use or otherwise deal with the remaining mixed liquid in the tanks."
The judge continues:
"That impression was further reinforced so far as Mr Rawlins was concerned by Mr Berryman's schedule of the programme of works which, when detailing the ready-mixed chemicals to be removed, in each case detailed the party as responsible for that as the defendants themselves rather than the claimants. The claimants' works of cleansing and so forth are specifically and clearly specified separately.
Although he had originally estimated on the basis of one tanker only, Mr Rawlins was prepared to bite on the bullet and to accept the additional cost of the three to four tankers in total, notwithstanding that this had now become, so far as he was concerned, a wholly unprofitable contract.
When work started on the first tank on 13th February it became apparent to Mr Rawlins that what he was being required to remove was not simply the washings from the cleansing of the tank but also a considerable quantity of unused liquid in the holding tank, and he immediately faxed to the defendants to raise the issue. By fax dated 13th February he said this:
'Further to my conversations with my men on the site and the tanker driver this morning, we have established approximately 70,000 litres of material to come out of tank 2. It is also expected there will be a similar quantity in the final tank. When we first visited the site and at our meeting it was estimated there would be a total of approximately 60,000 to 70,000 litres. This is what our original quotation was based on. We are now in a situation where we estimate that a further 5 tanker loads will be required over and above the original 3, therefore there will be an extra charge to cover these extra costs involved. We would also point out that at our programme meeting it was decided that the first tanker would arrive today and the next tanker Thursday of the following week.'.
'Further to your fax regarding the quantities of solution to be removed, we do not wish to spend time on the question of how much liquid is remaining. We note that you now require 5 tankers over and above the original 3 stated in your consignment note... which clearly says "4 off tankers", therefore an extra one tanker is required over and above your estimate. Please advise of the costs to enable us to consider this extra figure. We confirm that you are bringing 2 (two) tankers on Thursday next, 19th February, so that your employees can complete the cleaning of this vessel. We also confirm your disposal of the sludge that is at present in the tanks.'"
The judge continues:
"Mr Walters had in fact got his figures wrong. The figures were three to four originally, or at least as from January, so far as Mr Rawlins was concerned, and what was required was significantly more than that, as it was to prove. But perhaps most significantly, at that point there was no suggestion by Mr Walters that this was simply a lump sum contract under which Mr Rawlins was to remove the entirety of the contents of the tanks, whatever they were, at the fixed price. There is, in my judgment, a clear indication there that the defendants were accepting that there would be an extra sum to pay.
The work proceeded. It was substantially completed by 25 February. As it proved in all there was a total of nine tankers which had to attend and to remove in total something over or in the region of 200,000 litres of material. All that then remained was a final residue of the final sludge from the final cleaning up process.
On 25th February, the final day of the main body of work, Mr Rawlins submitted an interim invoice which was simply in a sum of £4,000 for 'Part works completed against your order'. He followed that up within a few days, and on 29th February, with an invoice in the sum of £14,750 exclusive of VAT for what was stated to be extra cost incurred in the removal and disposal of 185,000 tonnes of CCA waste, including all necessary legal costs.
Again, in his response to that Mr Walters did not deny the liability to pay an extra sum. He simply queried the amount. His response was:
'We are in receipt of the above invoice showing 185,000 tonnes of CCA waste. We acknowledge this is not a correct figure. May we request confirmation? What is the correct measurement referred to, also, can you clarify what the "legal costs" refer to? As soon as these points are clarified we will pass for payment.'
Mr Rawlins duly responded on 16th March pointing out there was an error. What was referred to was not tonnes but kilograms, and on that day there was an immediate response from Mr Walters:
'We however wish to advise that contained in your original quotation ... total of £4,845 included all residues in this price. You subsequently stated that you required extra capacity, our letter dated 13th February requested to advise what this extra would amount to. On your invoice ... you have charged for all residues whereas your quotation included 4 tankers... The first four tankers removed 102,280 tonnes, the remaining 5 removed 108,840 tons. [The judge remarks that that should be a reference to kilos]. To attempt to resolve this issue we calculate ... [then there is a calculation done and the calculation is for a price in addition of £5,159.02.]'"
The communication continues:
"'We would like to settle this account as soon as possible and welcome your earliest response so that we may issue a cheque in settlement during the next week.'"
The judge then goes on to deal with the submissions.
"We are in receipt of the above invoice showing 185000 tonnes of CCA waste. We acknowledge this is not a correct figure. May we request confirmation what is the correct measurement referred to, also can you clarify what the 'legal costs', refer to. As soon as these points are clarified we will pass for payment."
Again apparently accepting that extra costs should be paid.
(Appeal dismissed; Appellants do pay Respondents' costs summarily assessed at £6,500).