COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
CHANCERY DIVISION
Lightman J.
HC02CD3501
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE KEENE
and
LORD JUSTICE MAURICE KAY
____________________
CHANNEL HOTELS AND PROPERTIES (U.K.) LTD. |
Appellant |
|
- and - |
||
FAHAD AL TAMIMI |
1st Respondent |
|
and FIRST PENTHOUSE LTD. |
2nd Respondent |
____________________
____________________
Crown Copyright ©
Lord Justice Peter Gibson:
Waiver
"If the breach consists in a failure to act, it may be held to continue die in diem until the obligation is performed or becomes impossible of performance or until the innocent party elects to treat the continued non-performance as a repudiation of the contract."
"In my judgment however the breach of covenant is not a continuing breach: there was a once and for all obligation to "carry out and complete" the Project with the required expedition. The time for completion expired in 2001 and the right of re-entry arose on that date."
I take the reference to the expiration of the time for completion in 2001 to be based on CHAPS's pleaded case that, had ACP complied with its obligation to complete the Works as expeditiously as possible, they would have been completed by April 2001 (see. para. 12 of CHAPS's Particulars of Claim in the second action).
"If he fixes the brackets but fails to supply the shelf or if he supplies and fixes a shelf of unseasoned pine, my complaint against him is not that he has failed to exercise reasonable care and skill in carrying out the work but that he has failed to supply what was contracted for. He may fix the brackets and then go away for six months, but unless and until I accept that conduct as a repudiation, his obligation to complete the work remains."
So here, Mr. Morgan argued, the obligation on the lessee to carry out and complete the Works remains in the absence of acceptance by the landlord of the lessee's conduct as repudiatory.
"It is clear that the existence of the breach of covenant was not of itself a ground …. for refusing consent, for the proposed assignment secured the effective remedy of the breach."
Refusal of consent to the assignment
"The effect of this transfer was that, from 19th July 2002 such sums as might fall due under clause 9 of the Preliminary Agreement were charged to FP, and the only persons with a direct financial interest in the late completion of the Project under the Preliminary Agreement were ACP (as the developer) and FP."
"i.) a landlord is not entitled to refuse his consent to an assignment on grounds which have nothing whatever to do with the relationship of landlord and tenant in regard to the subject matter of the lease;
ii.) it is not necessary for the landlord to prove that the conclusions which led him to refuse to consent were justified, if they were conclusions which might be reached by a reasonable man in the circumstances;
iii.) in each case it is a question of fact, depending on all the circumstances, whether the landlord's consent to an assignment has been unreasonably withheld."
"The Court of Appeal in the Judgment pointed out that Britel as owner of the freehold reversion on the Lease and Meretz as holder of a mortgage securing its entitlement under the Introduction Agreement were parties to the 1999 Deed of Priorities and that deed expressly provided that (whatever may have been its effect in this regard otherwise) the FP Charge on the subsequent discharge or redemption of the Varlet Charge should come into full force and take effect. The Court of Appeal held that this provision was totally inconsistent with the provisions of the Introduction or Preliminary Agreements in favour of Meretz and CHAPS restricting the full and unfettered exercise by FP as mortgagee of the power of sale conferred by the FP Mortgage. The issue raised before me is whether the 1999 Deed of Priorities likewise precludes CHAPS as successor in title to the reversion upon the Lease from exercising the power to refuse consent to an exercise of the power of sale on the ground that it will defeat the rights in question. In my view the answer is clearly in the affirmative. Since the 1999 Deed of Priorities conferred on FP as mortgagee the right to override the rights of CHAPS and Meretz in question, it cannot be reasonable for CHAPS as landlord to refuse consent to an assignment by FP to Mr Tamimi on the grounds that the assignment will have this overriding effect and to require as a condition of giving consent that Mr Tamimi confer equivalent rights on CHAPS and Meretz. CHAPS by taking this position was not protecting or preserving existing rights but attempting to create new ones. To allow CHAPS to take the position which it has taken is to set at nought the provision in the 1999 Deed of Priorities and a refusal of consent on these grounds and the insistence on these conditions are in fundamental derogation from the rights conferred on FP by the 1999 Deed of Priorities. Whilst the 1999 Deed of Priorities left it open to CHAPS to object to an assignment on other grounds (e.g. the character or worth of the assignee), it precluded objections in principle to an assignment on the grounds that it would have the legal effect contemplated and provided for by the 1999 Deed of Priorities. I accordingly hold that the refusal of consent was unreasonable on this ground."
"I accept that circumstances can exist where a landlord trustee may be entitled to take into account the consequences of an assignment on the beneficiaries under the trust if the consequences have something to with the relationship of landlord and tenant in regard to the subject matter of the Lease. In my view the fundamental objection to the approach adopted by CHAPS in this case is that the considerations relied on have nothing whatever to do with the relationship of landlord and tenant in regard to the subject matter of the Lease: they are totally collateral to that relationship. I therefore hold that the grounds relied on afford no basis for the refusal of consent unless reinforced by the provisions of the 1995 Act."
"AND First Penthouse acknowledges that this Variation shall not in any way affect its guarantee dated March 7, 1996, given to Britel in respect of the obligations of ACP under the Agreement."
Conclusion
Lord Justice Keene:
Lord Justice Maurice Kay: