COURT OF APPEAL (CIVIL
DIVISION)
ON APPEAL FROM MR RECORDER MOXON-BROWNE QC in the
TECHNOLOGY
and CONSTRUCTION COURT
Royal Courts of Justice Strand, London, WC2A 2LL | ||
B e f o r e :
LORD JUSTICE RIX
and
SIR MURRAY
STUART-SMITH
____________________
C & B Scene Concept Design
LtdAppellant
- and -
Isobars Ltd
Respondent
Smith
Bernal Reporting Limited, 190 Fleet Street
London EC4A 2AG
Tel No: 020
7421 4040, Fax No: 020 7831 8838
Official Shorthand Writers to the
Court)
____________________
AS APPROVED BY THE
COURT
Crown Copyright ©
Sir Murray Stuart-Smith :
Introduction
The Contract
The Interim Applications
(a) No. 4 ‘as per original agreement’ in the sum of £69,000
(b) No. 5, in respect of 7 alleged variations, in the sum of £45,496.33
(c) No. 6 in respect of “AA Print and Design’ in the sum of £1500.
The Referral to Adjudication
“If either Party does not comply with the decision of the Adjudicator the other Party shall be entitled to take legal proceedings to seek compliance pending any final determination of the referred dispute or difference pursuant to clause 39A.7.1.”
“31. A dispute has arisen between the parties as to the Employer’s obligation to make payment and the Contractor’s entitlement to receive payment following receipt by the Employers of the Contractor’s Applications for Interim Payments No.’s [1] 4, 5 and 6:”
(Application 1 is no longer material).
“83 Such matters [the grounds upon which liability was disputed] might be germane if the contract conditions were other JCT or alternative institutional standard forms, where applications in respect of interim statement or payments, employ terminology such as “amounts due”. That description (without qualification by the introduction of further clauses) arguably allows an employer to abate amounts otherwise due on the basis of defective works or works not carried out, without even having to issue a withholding notice.
84. However, that is not the case in the contract between the Parties, which incorporated the JCT With Contractor’s Design 1998 Edition Form.
85. Uniquely, I believe, at least among JCT Forms, the With Contractor’s Design include the term as condition 30.3.5.
‘Where the Employer does not give any written notice pursuant to clause 30.3.3 and/or to clause 30.3.4 the Employer shall pay the contractor the amount stated in the Application for Interim Payment.’
86. It is clear from the Parties’ submissions that the Employer has not given written notice pursuant to clauses 30.3.3 and 30.3.4, in respect of any of the Applications for Interim Payments made by the Contractor.”
“90. Thus, in my view, clauses 30.3.3, 30.3.4 and 30.3.5 taken together impose an absolute imperative obligation on the Employer to pay the Contractor the amount stated in the Application for Interim Payment, in the absence of the written notices specified.
91. Those written notices have not been given by the Employer, thus I decide that the Employer shall pay to the contractor the amounts stated in Application Nos 4, 5 and 6 for Interim Payment.”
He decided that the Claimant was entitled to be paid £115,996.33 plus V.A.T. and interest which together amounted to £140,855.34, the sum for which summary judgment was sought.
1. That since the parties had failed to elect Alternatives ‘A’ and ‘B’, the whole of clause 30, and not only the provisions as to how and when the interim payments were to be made, fell away. Accordingly the express provision in clauses 30.3.3 and 30.3.4 as to the requirement of the employer to give notice, and clause 30.3.5 as to the effect of failure to give notice, fell by the wayside. Instead the provisions of the Scheme, not only as to how the amount of the interim payments was calculated and the time when they were due but also the provisions as to notice, and the effect of failure to give notice, were implied into the contract.
2. That both under the Act (ss110 and 111) and under the Scheme failure to give a notice within the stipulated time does not preclude the Employer from contending on an adjudication that the sums claimed are not “due under the contract” for the reasons upon which the Defendant wished to rely.
3. That by failing to appreciate that the contractual provisions of Clause 30 had been superseded by the provisions of the Scheme, the Adjudicator addressed himself to the wrong question and in so doing he exceeded his jurisdiction.
“If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) and (2) [Requirements as to how the amount of an interim payment is to be calculated and when it is to be made], the relevant provisions of the Scheme of Construction Contracts apply.”
Mr. Constable submitted that only the provisions as to how and when (i.e. those contained in clauses 30.1, 30.2A and 2B and 30.3.1) are substituted; all the other provisions of Clause 30 remain intact.
“(i) a decision of an adjudicator whose validity is challenged as to its factual or legal conclusions or as to procedural error remains a decision that is both enforceable and should be enforced;
(ii) a decision that is erroneous, even if the error is disclosed by the reasons, will still not ordinarily be capable of being challenged and should, ordinarily, still be enforced;
(iii) a decision may be challenged on the ground that the adjudicator was not empowered by the Act to make the decision, because there was no underlying construction contract between the parties or because he had gone outside his terms of reference;
(iv) the adjudication is intended to be a speedy process in which mistakes will inevitably occur. Thus, the Court should guard against characterising a mistaken answer to an issue, which is within an adjudicator’s jurisdiction, as being an excess of jurisdiction;
(v) an issue as to whether a construction contract ever came into existence, which is one challenging the jurisdiction of the adjudicator, so long as it is reasonably and clearly raised, must be determined by the Court on the balance of probabilities with, if necessary, oral and documentary evidence.”
“If he answered the right question in the wrong way, his decision will be binding. If he has answered the wrong question, his decision will be a nullity.”
Lord Justice Rix: I agree.
Lord Justice Potter: I agree.