Case No: QBENF 1999/0352/A2
IN THE SUPREME COURT OF JUDICATURE
COURT OF APPEAL
(CIVIL DIVISION) ON APPEAL
FROM THE HIGH COURT OF JUSTICE
QUEENS BENCH DIVISION -
Royal Courts of Justice
Strand, London, WC2A
2LL
Wednesday 23 February 2000
B e f o r e :
LORD JUSTICE
OTTON
LORD JUSTICE BUXTON
and
LADY JUSTICE
HALE
- - - - - - - - - - - - - - - - - - - - -
|
MRS KATHLEEN SAIGOL |
Respondent |
|
- and - |
|
|
CRANLEY MANSION LTD & ORS |
Appellant |
- - - - - - - - - - - - - - - - - - - - -
(Transcript of
the Handed Down Judgment of
Smith Bernal Reporting Limited, 180 Fleet
Street
London EC4A 2HD
Tel No: 0171 421 4040, Fax No: 0171 831
8838
Official Shorthand Writers to the Court)
- - - - - - - - - - - - - -
- - - - - - -
Mr Christopher Moger QC & Mr O Ticciati (instructed by Berrymans
Lace Mawer, London, Solicitors for the first Defendant/ Appellant)
Mr
Leolin Price QC & Mr Paul Stafford (instructed by Alan Taylor & Co,
London, Solicitors for the Respondent)
Mr A G M Cooper (instructed by
Kennedys, Solicitorson behalf of forth Defendant/Appellant)
- - - - - - - - - - - - - - - - - - - -
-
Judgment
As Approved by the
Court
Crown Copyright ©
LORD JUSTICE OTTON:
This is a judgment
of the Court to which each member has contributed.
This is an appeal
from a decision of His Honour Judge Thornton QC a Judge of the Technology and
Construction Court on the 15 February 1999 whereby he ordered:
1. The
Appellants to pay the Respondent £739,903 including interest.
2. The
appellants to pay the fourth defendant’s costs of and incidental to
defending the respondent’s claim in the consolidated proceedings (to be
taxed if not agreed).
Mrs Kathleen Saigol is the central figure in this tragic saga. In 1988
she was a BBC Television Producer and Researcher, living at 6 Cranley Mansion
with her two sons, Matthew aged 17 years and Pasha aged 7. In the previous year
her leasehold interest in her flat was valued at £475,000. Jackson Stops
advised that when the then contemplated works were complete, her flat would be
worth in the region £750,000. Her equity at that time was approximately
£180,000. She owed £295,000. She was servicing the interest from her
deposit account. As a result of a divorce settlement, she had deposits in a
bank account which on 31 December 1988 totalled approximately £100,000.
She was earning £25,000 a year in her career. She was in receipt of
maintenance of £25,000. She had £200,000 in capital. She intended to
spend about £130,000 on the renovation of her flat which she then intended
to sell. She was thus in a comfortable situation.
If the works which are
the subject matter of these proceedings had been performed properly, they would
have been completed in October 1988. The loan she needed to finance this work
was therefore intended for a limited period. If all had gone according to plan,
she would have enhanced her equity by at least £250,000. She would then
have been in a position to obtain another property in London where she would
continue to bring up her sons.
As a result of the gross incompetence of
those responsible for the refurbishment of the block of flats and her flat in
particular, her life has been ruined. She suffered severe and continuing damage
to her health, the indignity of bankruptcy, 11 years of litigation, a disrupted
family life, a nomadic existence, loss of her home and her professional career.
This state of affairs should never have come about. How it did must be
explained in some detail.
Cranley Mansion is a red brick, Edwardian block
of flats near Gloucester Road in South Kensington, London. There were seven
flats spread over six floors and a basement. Flat 6, acquired on a long lease
by Mrs Saigol in 1983 for £157,000, was the largest flat in the block and
extended to 3,400ft. over the top 5th and 6th floors with fine views over West
London. In 1986 the residents acquired the freehold and vested it in the newly
created Cranley Mansion Ltd., (“Cranley”) in which Mrs Saigol was a
19% shareholder. Cranley’s only asset, apart from the freehold itself,
was its ownership of the basement flat occupied by the caretaker under a service
licence. Mrs Saigol’s demise of Flat 6 did not include the external
envelope of the building, or any part of the building lying above the surfaces
of ceilings or below floor surfaces or any of the common parts.
By the
late 1980’s the block was seriously overdue for major structural
refurbishment. Particular needs included a new roof covering, cleaning and
repair of the external brickwork, the eradication of dry rot, and the
installation of a new lift. Mrs Saigol realised that if she were to make
structural alterations within her flat they would considerably enhance the value
of her property. The work contemplated included the construction of a new roof
terrace, the installation of a new roof lantern light and windows in the roof,
the stripping out of partitions and old wiring and the installation of plumbing
and electrical points ready for a new occupier. The proposed structural work
could only have been undertaken satisfactorily as part of, and in conjunction
with, the external structural refurbishment of the block. The work on her flat
was designed by Mr Richard Goldsbrough. This was to be done in two phases.
Phase 1 was largely a structural phase, and was to be undertaken in conjunction
with the external refurbishment of the common parts of the block. Phase 2 was
largely re-decoration work and the construction of a new internal staircase
within the flat. Mrs Saigol was liable to reimburse Cranley for 19% of the cost
of the common parts works; she was liable to pay 100% of the cost of her own
works. Cranley’s managing agents instructed Congreve Horner & Co.,
(“Congreve”) to prepare a specification for the common parts works.
All the work was included within one building contract, with Cosmur Construction
(London) Ltd., (“Cosmur”) as contractor and Congreve as supervising
officer. The contract was in the 1980 JCT Private Without Quantities Form and
the contract sum was £254,294.00 (ex VAT). It was signed on 21 January
1988. Work began on site on 25 January 1988 and was due to finish on 22
July.
Mr Goldsbrough was responsible for preparing the specification for
the personal work. Mr Johnson produced the combined specification and included
the relevant parts of Mr Goldsbrough’s specification. These were not
fully detailed, nor was the boundary between them clearly defined. The
relations between the parties were laid down in a series of letters written by
Congreve (dated 7 September 1987) and countersigned by Mr Goldsbrough to
indicate agreement.
Mr Johnson ran the project virtually single-handed.
He was a trainee surveyor who completed his examinations in 1988 and left
Congreve in September 1988 shortly before Mr Horner (a partner in Congreve)
certified practical completion. Mr Johnson’s role was pivotal in the
disastrous outcome of the project. He gave evidence and the Judge in assessing
his performance concluded that his manner was ‘overbearing, offensive and
extremely unhelpful. He was over-confident and unprepared to accept that he was
a trainee surveyor running single handed an unduly complex contract without
experience of such contracts’.
Mrs Saigol raised the money for her
share by means of a £400,000 loan facility from Dunbar Bank Plc and a
smaller overdraft facility with Lloyds Bank. Dunbar agreed to provide Mrs
Saigol 80% of sums certified by its own surveyor once he was satisfied that
Congreve’s valuation was correct. The certification procedure between
Congreve and Goldsbrough was unsatisfactory. What should have happened was that
before issuing an interim certificate Congreve ought to have sent a valuation to
Goldsbrough for him to check. If he was satisfied, the certificate could then
be issued, Dunbar would be informed and its own surveyor would then inspect and
report prior to release of the moneys. What actually happened was that Congreve
issued certificates and sent the certificate and valuation to Mr Goldsbrough
afterwards, on the basis that any comments he had would be taken on board before
the issue of the next certificate. This meant that Mrs Saigol could not be sure
of paying Cranley in time if Mr Goldsbrough did not give his unqualified
approval to Congreve’s certificate and valuation. There would be
particular difficulty where the final interim certificate was coupled with the
certificate of Practical Completion. This was precisely what
occurred.
The project soon got into difficulties. Mr Johnson formed the
view that it was highly undesirable that Mrs Saigol should continue to occupy
any part of the flat during the works. She declined to vacate and only did so
at short notice in mid-April because the dry rot eradication works proved more
extensive than Congreve had expected and made her flat uninhabitable. Cranley
agreed to pay for alternative accommodation until the flat was made habitable
again. Thereafter Cosmur had access to the flat on the 5th floor as well as the
6th floor. The 5th floor contained most of Mrs Saigol’s possessions which
she had not removed. Although Cosmur were entitled to enter the 5th floor from
the scaffolding, after the scaffolding was struck prematurely they entered by
the front door to use the flat for a range of other purposes not authorised by
the contractors and which incurred Mrs Saigol’s considerable displeasure.
Even so, the first four interim certificates were issued and paid.
On 21
July 1988 Mr Johnson said that Mrs Saigol’s flat was ready for her to move
back into and Cranley stopped paying for alternative accommodation. However,
Mrs Saigol claimed that the flat was uninhabitable and that she was entitled to
remain out of occupation at Cranley’s expense. She was said to have been
late in paying her share of the Interim Certificate 5. When Interim Certificate
6 was issued on 8 August, it should have been for a sum appreciably less than
that certified by Congreve and Mrs Saigol withheld her £35,495 share of it
until she was satisfied that progress was being achieved towards making her flat
habitable and accomplishing practical completion. The work was delayed and the
causes of that were highly contentious. In the event practical completion was
certified with effect from 21 September 1988 although it was eventually accepted
by Cranley that the works were not practically complete. There was a major
controversy as to how close to or far from such completion the works actually
were. By this date relationships between the principal personalities had
completely broken down.
Mrs Saigol attributes this breakdown to Cosmur
ceasing work without contractual justification with the work still incomplete
and with much defective work unremedied and to its subsequent failure to return
to site without contractual justification. She was critical of Mr
Johnson’s ability to manage the project, his failure to exercise any
effective influence over Cosmur and his detailing errors. She was also critical
of Mr Goldsbrough’s detailing errors.
All the other parties put the
blame for the breakdown fully at Mrs Saigol’s door. She was said to be
difficult and irascible in her dealings with all concerned. She vacillated and
changed her mind as to her requirements. She refused to pay large sums of money
which were due to Cranley for onward payment to Cosmur which arose out of
Interim Certificate 6 and 7. Cosmur contended that they had reasonably reached
the point where they were not prepared to do any more work in relation to either
the common parts work or the Flat 6 work.
Certificate 7, as well as
certifying practical completion, certified that Cosmur were entitled to be paid
a further £80,843. This included the release of half the retention sum.
It was later accepted that there was a substantial over-valuation by Congreve,
and Cosmur were not entitled to half the retention sums. This certificate
should have been for no more than £23,500 from which a set-off should have
been deducted of £6,500 (£3,500 liquidated damages to which Cranley
was entitled because of Cosmur’s delay, and a further £3,000 off as
the cost of cleaning the flat once the works were completed). Mrs Saigol
refused to pay her share of Certificate 7. The issue of the P.C. Certificate
and its accompanying valuation triggered the final breakdown between the parties
and placed Congreve in breach of contractual duties it owed to Cranley and Mrs
Saigol. The Certificate enabled Cosmur to treat its contract work as finished
and prevented Congreve from requiring Cosmur to complete all outstanding work
and to give an appropriate allowance for any work which could only be done from
the scaffolding which had been struck. Acting on the advice it received,
largely from Congreve, Cosmur adopted the stance that they were entitled to the
sum certified and that Mrs Saigol was wholly unjustified in not paying her
contributions to those sums in full. Cranley, again apparently on the advice of
Congreve, surprisingly took the view that until well into 1989, the only
appropriate course was to recover money from Mrs Saigol. At a meeting in
October 1988 Mrs Saigol indicated that she would pay her contribution to
Certificate 6 if Cosmur made her flat habitable and completed the snagging.
Cosmur had no intention of returning to site even if it was paid. No solution
was reached. The upshot of the breakdown soon operated to Mrs Saigol’s
disadvantage and was to lead to her losing her flat and to both her own and
Cranley’s insolvency. By the early part of 1989 she was unable to service
the substantial loan facility drawn down by her and provided by Dunbar and
Lloyds.
The Litigation
Writs soon began to fly. On
21 November 1988 Cranley issued forfeiture proceedings against Mrs Saigol for
the sums allegedly owing from her up to and including Certificates 6 and 7.
Dunbar joined the action at its own request as second defendant. In February
1989 Cosmur sued Cranley for the unpaid balance due under Certificates 6 and 7.
Cranley, on the advice of Congreve that Cosmur’s case against Cranley was
very strong, entered no defence so that Cosmur entered judgment by default. In
April the Master granted Cranley’s application for summary judgment
against Mrs Saigol for £8,648 and gave leave to defend the balance of the
claim. This Order was set aside in October when she was given leave to defend
the whole claim. In December 1989 Cranley had Cosmur’s default judgment
set aside and obtained leave to defend on condition that £50,154 was paid
into court. In January 1990 Cranley, in Cosmur’s action, served a Third
Party Notice on Mrs Saigol. Meanwhile, in September 1989, Dunbar had issued
possession proceedings against Mrs Saigol in the County Court which were later
transferred to the Chancery Division. By this time Mrs Saigol was defendant in
two sets of High Court proceedings and Third Party in another. Mrs Saigol made
various attempts to settle with Cranley. She commissioned reports from
surveyors and asked for meetings between them and Cranley’s surveyors.
Cranley instructed Congreve to meet Mrs Saigol’s representatives to
discuss the works but Congreve made no attempt to comply.
After carrying
out temporary repairs and cleaning at a cost of some £30,000 Mrs Saigol was
able to re-occupy and place the flat on the market. However, disaster was to
strike again. On 25 January 1990 a 4 tonne chimney stack (which had been part
of the contract works) collapsed onto the roof, making occupation of her flat
dangerous and forcing her and her son to vacate until the reinstatement was
completed in September 1990. The repairs were paid for by Cranley’s
building insurers who also paid for Mrs Saigol’s temporary accommodation.
Mrs Saigol returned for a short period thereafter no part of her claim could be
attributed to the chimney collapse.
The rent and other outgoings coupled
with the costs of repairing and cleaning, of experts and legal fees in three
separate proceedings severely undermined Mrs Saigol’s financial position
and used up much of the substantial capital she had from her divorce settlement
in her account with the Bank of Oman. She obtained legal aid in the Dunbar
action in March 1990 and in the Cosmur and Cranley actions in May 1990. The
chimney collapse effectively stopped the process of marketing the flat during
the reinstatement works and the debt owed to Dunbar increased. On 6 November
1990 Dunbar’s possession claim was determined by Mervyn Davies J who
ordered possession. Dunbar did not enforce the possession order for the time
being. The learned Judge also ordered trial of preliminary issues raised by Mrs
Saigol’s counterclaim in which she alleged Dunbar was in breach of an
implied term of the lending agreement because of the negligence by its quantity
surveyors in relation to Interim Certificates 1 to 5 (but not 6 or 7, for which
Dunbar had advanced no money during the works). It appears that no further
steps were taken to prosecute the counterclaim.
By the summer of 1991
Mrs Saigol and her children had moved home eight or nine times since leaving
Cranley Mansion in April 1988. On 19 August 1991 Mrs Saigol was adjudicated
bankrupt. Her claims in the three sets of proceedings vested in her Trustee,
and on 15 April 1992 he assigned them back to her on terms that she would
receive £25,000 out of the first £100,000 recovered, and any balance
remaining after payment of creditors. The principal creditor was Dunbar, who
had continued to charge interest after the bankruptcy. Dunbar repossessed the
flat in October 1991 and in the following month by a Consent Order in the
Cranley proceedings, Cranley granted Dunbar relief from forfeiture of the lease
of the flat on Dunbar’s payment to Cranley of £38,414 for rent and
service charge arrears, plus nearly £15,000 interest. Dunbar paid the
total to Cranley’s solicitors and debited that sum to Mrs Saigol’s
loan account. In June 1992 Dunbar sold the flat for £475,000 and after
applying the net proceeds to reducing Mrs Saigol’s debt, there was a
balance due of £393,909.
In August 1992, Mrs Saigol sought to join
Cranley, Congreve and Goldsbrough as defendants in the Cosmur action. In
January 1993 the proceedings brought by Cosmur and Cranley were ordered to be
consolidated with Mrs Saigol as plaintiff and she was given leave to make direct
claims against Congreve and Goldsbrough. Mrs Saigol’s claim against
Congreve came to be called the ‘personal proceedings’. All other
claims between the parties were to be made by way of RSC O.16, rule 8 Notices or
counterclaims. Thereupon Cranley served a contribution notice against Congreve
seeking an indemnity against Mrs Saigol’s claims against it. The notice
also sought damages against Congreve but no particulars of loss were given. Mrs
Saigol’s consolidated Statement of Claim was served in February 1993. By
its
defence Congreve denied that it owed Mrs Saigol any duty of care to
prevent physical damage to her flat or property, and denied it owed her any
substantive duty in tort or contract.
On 23 April 1993 a Consent Order
was made in the Dunbar proceedings whereby Mrs Saigol’s counterclaim was
dismissed in full and final settlement of all past, present and future claims of
whatever nature either party might have against the other, and it was declared
that Dunbar was debarred from proving in Mrs Saigol’s bankruptcy or
pursuing any claim against her after discharge.
On 15 June 1993
Cranley’s creditors (i.e. the lessees and shareholders but excluding Mrs
Saigol) approved a Company Voluntary Arrangement, and in July Mrs Saigol issued
an application in the Chancery Division to have the CVA revoked. In the same
month an Official Referee ordered all claims by or against Cranley to be stayed
pending the outcome of Mrs Saigol’s application. Ferris J. held that the
CVA was not binding on Cranley or any of its creditors. In September 1994
Cranley entered voluntary liquidation. Cosmur then obtained payment out of
court of £50,134 (plus interest) paid in by Cranley when Cosmur’s
default judgment was set aside. This meant that Cosmur had recovered all sums
certified by Congreve up to Certificate 7.
Meanwhile, and thereafter, the
consolidated proceedings moved on without Cranley. In August 1993 Congreve
obtained an order that there be a trial of preliminary issues on the question of
whether (and if so what) duties Congreve owed to Mrs Saigol in contract or in
tort. This trial took place over five days in January 1994, when it was found
that the contractual duties were so limited that Congreve was entitled to have
Mrs Saigol’s claim against it struck out.
Mrs Saigol appealed to
the Court of Appeal. Congreve argued that it was not fair, just and reasonable
for any tortious duty to be imposed on Congreve because the position was
governed by the letters of September 1987 and because Mrs Saigol was wholly
protected by Mr Goldsbrough and had ‘an adequate remedy’ against him
and, through Cranley, against Congreve regarding the common parts. The Court of
Appeal in July 1995 accepted this argument but found that the contractual duty
was wider than the Judge had found. Mrs Saigol’s claim against Congreve
was reinstated and her pleadings re-amended. The principal criticism of
Congreve was in relation to the issue of Certificate 7, and that the condition
of the flat as itemised in the Scott Schedule was due to Congreve’s
breaches.
On 1 December 1995, Cranley’s liquidator assigned
Cranley’s claim against Congreve to Mrs Saigol in exchange for a release
of her claim against it. In February 1996 Congreve successfully resisted her
application to carry on under RSC O.15, r.7(2), but this was granted by the
Court of Appeal on 7 May 1996. Mrs Saigol amended the grounds of
Cranley’s pleading against Congreve to add further heads of damage. These
proceedings came to be known as the ‘assigned
proceedings’.
Congreve amended their defence in the personal
proceedings and no longer claimed that Mr Goldsbrough was responsible for
inspecting and supervising the flat work. They maintained however that the
issue of Certificate 7 was fully justified, that the alleged incompleteness of
works referred to in the Scott Schedule was due to Mrs Saigol’s failure to
pay her share of Certificate 6, that the works were delayed by numerous
variations to the contract instructed by Mrs Saigol and that generally Mrs
Saigol’s loss was caused by her own negligence (including her failure to
follow the advice of Mr Goldsbrough to pay on the Certificates), her failure to
protect her belongings, honour agreements and to take advice. In June 1996 at a
pre-trial review, it was ordered that the trial be adjourned until 2 October
1996 as a priority fixture. In August Mrs Saigol’s expert became
seriously ill and had to withdraw from the case so the trial date was re-fixed
for the 14 April 1997 to allow a new expert to be instructed.
At the
trial before HHJ Thornton QC, the various allegations made by Congreve against
Mrs Saigol went both to her substance and credit. They were adopted by Cosmur
and Mr Goldsbrough. The Judge rejected them all, finding that they became
weaker with each passing day:
"The conclusion is that none of the
examples put forward as supporting the general proposition that Mrs
Saigol’s evidence was neither reliable nor credible was made out. The
reason for dealing with questions of credit at such length has been two-fold.
Firstly, in refuting these examples, it enables me to confirm my initial
assessment that Mrs Saigol was attempting to tell the truth but that the passage
of time led to occasional, but inconsequential, factual errors. On the major
questions, I was able to accept her evidence as both accurate and truthful.
Secondly, the wholesale attack on Mrs Saigol’s credit, which was so wholly
unjustified and unwarranted, pointed to the real possibility that
Congreve’s case was unreliable and tainted with the very unreasonableness
that it was alleged tainted Mrs Saigol’s case. Having seen Mr Johnson at
length giving both expert and factual evidence, I am driven to the conclusion
that that is a fair way of describing Congreve’s defence and its
concomitant attack on Mrs Saigol.
My overall conclusion as to Mr
Saigol’s evidence is that she attempted at all times to provide truthful
and accurate answers to the questions she had to answer for an extended period
lasting over 5 days in the witness box. I sought to keep in mind, in evaluating
her evidence, the fact that she had been through a 9-year ordeal of unimaginable
stress and that that could well have influenced adversely the accuracy of her
evidence. She had suffered her Flat being turned into a building site; the
bullying of the workmen who continuously misused the parts reserved for her; the
overbearing, offensive and extremely unhelpful manner of Mr Johnson; the
loneliness of combating the hostility of all others involved over the difficult
months following the collapse of the scheme; the loss of her family life for
several years; the loss of her Flat, capital and career; the suffering, for
several years, of depression and general ill health caused by the works and
their aftermath; bankruptcy; litigation of almost Byzantine complexity with an
interlocutory history of Jarndycian proportions; and the indignity of it
being suggested in cross-examination, conducted on instructions, of having
committed perjury, of obtaining money by deception and of maintaining bogus
claims. This has undoubtedly clouded Mrs Saigol’s recollection of some of
the detail but this absence was made good by the contents of the documents. Mrs
Saigol gave her evidence in a somewhat rambling and disjointed way, but that is
her general manner. I remained impressed by her general cheerfulness and
tenacity to battle through her adversities that she exhibited throughout her
evidence and I remained satisfied that, in instances where documentary support
was not available, I was able to rely on the general thrust of her evidence.
......
.... In my view, although this accounts for the nature and manner
of her answers to many questions, these feelings did not entail her giving
untruthful or misleading evidence. I was impressed at how, invariably, detail
recounted by Mrs Saigol or found in documents particularising her claim were
verified or corroborated by independent contemporary documentation."
The
trial Judge recorded that the trial proved unusually difficult to conduct for
both himself and all counsel involved. These difficulties were not caused by
any shortcomings in the way the parties’ respective cases were presented
but by the unusually detailed number of allegations required to be investigated
in circumstances where the events had occurred nine years previously, the
documentation was incomplete and the parties were confined by constraints in the
amount of pre-trial preparation that could be undertaken and in the length of
the trial with which they were all concerned. Moreover the diffuseness and lack
of direction of the pleadings, which was the result of the extraordinary
convoluted pre-trial history of the action, made everyone’s task even
harder. (Para 104). On Day 24 the Judge gave the following
ruling:-
"There are - - two stages to this case, and two questions of
causation. Stage 1 is a consideration, in general terms, of the cause of the
non-completion of the works – certainly of the works as envisaged by Mrs
Saigol. Stage 2, in the light of the findings of Stage 1, is to consider
whether the specific complaints of breach of duty and contract made against the
individual defendants are, in legal terms, causative of the causes identified at
Stage 1."
In the event, and in summary, the Judge found that Congreve
were in breach of their contract with Mrs Saigol, the issue of the Certificate
of Practical Completion and its valuation were pivotal in the breakdown of the
building contract, and Mrs Saigol reasonably refused to pay her share of the
sums certified in Certificates 6 and 7.
He also found that
Cranley’s proceedings against Mrs Saigol, for forfeiture of her lease, and
the disastrous state of Flat 6, made it impossible for her to sell the flat and
re-pay Dunbar. Dunbar’s claim for possession of the flat was held to be
caused by Congreve’s breach.
In the personal proceedings, the
Judge found that Congreve owed Mrs Saigol a contractual duty to consult with Mr
Goldsbrough over the issue of Certificate 7 which admittedly it breached. If he
had been consulted the Certificate would not have been issued. If it had been
withheld, then, notwithstanding the fact that the contract had all but broken
down in August 1988, Cosmur would have finished the work satisfactorily or
allowance would have been made for what it could not finish on the final
account. Accordingly Mrs Saigol was entitled to be put in the position she
would have been in had the contract been completed satisfactorily. She was not
bound to give credit for the further sum she would have had to pay to achieve
that result, since she had, in effect, already paid in full. Mrs Saigol was
entitled to damages to compensate her for the lesser of repair costs or
diminution in value of her flat, both to be assessed in October 1988 (when the
works ought to have been completed). Diminution in value was here used by the
learned Judge as shorthand for the difference between the value which the flat
would have had, had the works been satisfactorily completed, and the value it
actually had in the state in which it was left. He did not assess the
diminution in the value of the flat directly. Instead he assessed the
diminution in the value of Mrs Saigol’s interest in the flat combined with
Cranley’s interest in the building. He found this diminution was
£200,000. Since this was less than the total of the cost of repairs being
claimed in the personal and assigned proceedings taken together, he found
Congreve liable to pay this amount as damages. In the event, he awarded
£90,000 in the personal proceedings as representing the diminution in the
value of the flat and £110,000 in the assigned proceedings as representing
the diminution in value of Cranley’s freehold interest.
Accordingly
Mrs Saigol recovered:
1.