England and Wales Court of Appeal (Civil Division) Decisions
You are here:
BAILII >>
Databases >>
England and Wales Court of Appeal (Civil Division) Decisions >>
Rickards & Anor v Jones [2000] EWCA Civ 260 (13 October 2000)
URL: http://www.bailii.org/ew/cases/EWCA/Civ/2000/260.html
Cite as:
[2000] EWCA Civ 260
[
New search]
[
Printable RTF version]
[
Help]
Case No: B2/2000/0451
IN THE SUPREME COURT OF JUDICATURE
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM ABERYSTWYTH
COUNTY COURT
His Honour Judge Moseley
Royal Courts of Justice
Strand, London, WC2A 2LL
Date: Friday 13 October 2000
B e f o r e :
LORD JUSTICE MANCE
MRS JUSTICE SMITH
|
RICKARDS
AND ANOTHER
|
Appellant
|
|
-
and -
|
|
|
JONES
|
Respondent
|
- - - - - - - - - -
(Transcript of the Handed Down Judgment of
Smith Bernal Reporting Limited, 190 Fleet Street
London EC4A 2AG
Tel No: 020 7421 4040, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
- - - - - - - - - -
Mr. Bryan Thomas (instructed by Messrs Colin Taylor of Cardigan for the
Appellants)
Mr. Michael Pooles Q.C. (instructed by Messrs Morgan Cole of Cardiff
for the Respondent)
- - - - - - - - - - -
Judgment
As Approved by the Court
Crown Copyright
LORD JUSTICE MANCE:
1 This is an appeal by permission of HHJ Moseley QC against his order made
10
th April 2000, declaring that the defendant solicitors were not in
breach of duty to the claimants. The trial had taken place on the same day. It
was of a preliminary issue, whereby the "issue of breach of duty and of
negligence, and causation of damage and limitation, [was to] be tried before
the issue of quantum". Since it is acknowledged that the defendant solicitors
were negligent and in breach of duty in what must, on the judge's judgment,
have been immaterial respects, it is necessary to examine closely the nature
and causation of the claim actually advanced.
2 The claimants were and are husband and wife. I have the greatest sympathy
for them. The case arises out of their first and only house purchase in July
1993. For reasons which were not on any view their responsibility, it has
proved a disaster. The house is seriously defective, its builder is insolvent
and, for reasons requiring careful consideration, the National Housebuilders
Council ("NHBC") guarantee insurance on which they relied when purchasing has,
so far at least, proved valueless.
3 The claimants contracted by two contracts on 14
th July 1993 to
buy a plot of land at a cost of £10,000, and to buy the house to be (in
fact already) built on it at a cost of £30,250. The first contract was
with a Mr Davies and Mrs Rogers, the second with Mr Rogers, the builder. The
defendants, through their partner Mr Russell Jones, acted as the claimants'
solicitors. In answer to pre-contract enquiries on 12
th May 1993 the
vendors' solicitors represented that the property would be sold with the
benefit of NHBC cover, and that the relevant NHBC documentation would be
delivered on exchange of contracts. The claimants had worked in the building
trade and knew of the general significance and importance of NHBC cover.
Broadly, it involves a tri-partite contract, with a ten year period, under
which the builder gives various warranties and undertakings to a first
purchaser, each subsequent purchaser and any mortgagee in possession and the
NHBC undertakes to compensate each such purchaser and mortgagee if the builder
due to insolvency or fraud fails to complete the home in accordance with the
NHBC's requirements or fails to put right any defect reported in an initial
guarantee period of two years or any major damage caused by defect or
subsidence, settlement of heave in the remainder of the ten year period.
4 To make their purchase, the claimants required a £38,235 mortgage from
the Britannia Building Society. The society's instructions to the defendants as
solicitors included the following:
"
The N.H.B.C. SCHEME
9. Where the property is new or less than 10 years old please ensure that a
N.H.B.C. agreement was entered into at the time of construction and that the
benefit of the 10 year Protection Certificate will pass to the borrower and
that the certificate is with the title deeds."
5 Contracts were exchanged by telephone on 14
th July 1993, and,
because the claimants were anxious to move home, completion was agreed for
16
th July 1993. By letter dated 15
th July 1993 the
vendors' solicitors sent to the defendants the vendors' signed contract copy
and NHBC documentation including a Buildmark Book BM, an Offer of Cover BM1 and
an Acceptance Form BM. The letter was received by the defendants on
16
th July 1993, the day of completion. The NHBC documentation had,
clearly, been issued by NHBC, although no date of issue appeared upon it. It
identified the plot with its address as the "home" and the builder as A. B.
Rogers & Son. It gave a "Buildmark No." - DA123306 - and, as expressed on
the "Offer of Cover", a "NHBC Member No." - 66495 - for the builder. It came in
an envelope under cover of a page bearing like information, and stating, with
use of most emphatic capitals:
"TO BUILDER/BUILDER'S SOLICITOR
PLEASE PASS THIS ENVELOPE, UNOPENED, TO THE
PURCHASER'S SOLICITOR
BEFORE OR IMMEDIATELY AFTER EXCHANGE OF CONTRACTS
NOTE TO PURCHASER'S SOLICITOR
-
THIS ENVELOPE CONTAINS:
THE ACCEPTANCE FORM (BM2)
Please complete all sections of the form and return the Acceptance to NHBC
BEFORE LEGAL COMPLETION.
NHBC will then issue the Ten Year Notice when the house is finished.
If the postal address is not known before legal completion, please send it to
NHBC as soon as possible thereafter, quoting the Buildmark number, and the
purchaser's name."
6 The Offer of Cover stated:
"The Builder and the NHBC offer the First Purchaser of the Home and all
subsequent Purchasers the protection set out in the Buildmark Booklet which
accompanies this Offer. This Offer is subject to the condition overleaf.
To accept this Offer, please complete the Acceptance Form BM2 and return it to
NHBC. Your solicitor will have this form.
As soon as the Acceptance Form is received by the NHBC you will become entitled
to the cover set out in part B section 1 and part C section 1 of the Booklet.
You will become entitled to the cover set out in the rest of the Booklet only
after the issue of the Ten Year Notice. The Ten Year Notice will be issued once
the Acceptance Form has been received by the NHBC and the Home has been
completed.
Signed on behalf of the Builder and the NHBC"
7 There followed the signatures of the Chief Executive and the Secretary of
NHBC.
8 The Acceptance Form called for completion and return by the defendants as
the claimant purchasers' solicitors. As well as accepting the Offer of Cover,
it involved an undertaking to deliver the Offer to any subsequent purchaser. It
said at its foot:
"This Form will be acknowledged by the issue of the Ten Year Notice which will
be forwarded when the Home has been completed to NHBC's satisfaction. NO other
acknowledgement will be issued."
9 In its side margin it said in capitals:
"Please see the reverse of this form for important notes."
10 The reverse of the Offer of Cover and of the Acceptance Form were, we were
told, both in the same form, stating inter alia:
"
Condition
This Offer is made only to Purchasers who acquire or are to acquire:
(a) the freehold of the Home or a leasehold interest of 21 years of more of a
share in such freehold or leasehold interest, and
(b) the Home for use as a residence by themselves, their tenants or
licensees.
Notes to Purchases
1. This Offer is made by the NHBC and by the NHBC member who:
(a) is selling the Home to the First Purchaser; or
(b) is building the Home on the First Purchaser's own land; or
(c) is otherwise authorised in writing by the NHBC to make the Offer.
No other person can make the Offer. The NHBC member is described in this Notice
and in the Buildmark Booklet as the "Builder".
2. The Buildmark provides protection for Purchasers as set out in the Buildmark
Booklet. The NHBC cannot accept any other liability for the Home.
3. If the Ten Year Notice is not received within a few weeks after the Home has
been completed ask you solicitor/licensed conveyancer to check why. It may be
because the Acceptance Form has not been returned to the NHBC or because there
are outstanding defects which prevent the issue of the Notice. If there are
defects which prevent the issue of the Notice, your rights under the Buildmark
are set out in the Buildmark Notice."
11 In parts of the Booklet summarising, though not part of, the Buildmark
cover, it was explained that:
"Under the Buildmark the Builder is required to build your Home in accordance
with NHBC's Requirements. This work will be subject to the NHBC's system of
inspection and he must earn the NHBC's Ten Year Notice."
12 A later footnote in the same parts explained:
"The Builder is:
? the NHBC member who sold you your home or who built it on your land
? the person authorised by the NHBC to provide you with the Buildmark
His name and address are given on the Offer of Cover."
13 Far from acting as advised by the covering letter, Mr Jones, failed - for
reasons he could not explain - to complete or send off the Acceptance Form
until 22
nd September 1993. In response on 27
th September
1993, the NHBC advised Mr Jones that the builder had been removed from their
register and had ceased to be a member on 26
th March 1993. That,
they say, was after their issue of their documentation. The builder, they
said, was not thereafter entitled to pass on such documentation to vendors of
later sold houses. In a letter dated 8
th August 1996 the NHBC
assert, without particulars, that
"We always suggest to solicitors that such matters [i.e. the builder's
continuing entitlement to pass on such documentation] be confirmed with NHBC
when carrying out preliminary enquiries for a conveyance."
14 In a letter dated 3
rd December 1996 the NHBC said:
"Properties are required to be registered with NHBC by our members prior to
construction. It is at this point that they are allocated a Buildmark number
and documents are issued.
When a Builder comes off the NHBC register, they are formally reminded by
Recorded Delivery letter that they have no authority to deliver NHBC
documentation for homes that have not yet been sold (i.e. Contracts exchanged
or entered into), even those for which they have made an application for
inspection prior to the date of deletion.
The offer of cover you received for the above property clearly states that it
is subject to the conditions overleaf. The conditions show that the offer can
only be made by the NHBC member. A. B. Rogers & Son has not been a member
of NHBC since the 26
th March 1993.
We again reiterate that the above mentioned property has no warranty."
15 The delay until 1996 in pursuing the matter with the NHBC does not appear
to have been in any way the claimants' fault. Mr Jones appears not to have
informed the claimants of any problem with cover. By a curious coincidence, it
seems, the NHBC actually inspected the claimants' house after the claimants had
reported defects, so reassuring the claimants that NHBC was dealing with their
claim. In fact, NHBC had mistaken it for a next door house, on which a claim
had also arisen. Following the NHBC's letters in 1996, the claimants or, more
probably, their advisers concluded that the matter either had to be or should
be left there. They did not pursue NHBC further.
16 Instead they turned to the present defendants, as the claimants' former
solicitors. Until near trial, it does not appear to have been made clear that
the defendants had had the NHBC documentation prior to September 1993. At an
earlier stage, the Solicitors Indemnity Fund Limited, representing the
defendants, had by letter 20
th October 1998 been prepared to
approach the matter, though without admission, on the basis that Mr Jones
should have checked with the NHBC that the builder's registration still
continued. The Fund contended, that, since the builder was not registered, NHBC
cover could never have been achieved and that, even it had been a contractual
term that NHBC cover should be provided, the claimants would (if they had
learned before completion of its breach) have proceeded with the purchase and
have had no more than a claim for damages. That contention was not pursued
before us and seems without reality. The builder had through solicitors
confirmed that the NHBC documentation would be provided (in a manner which may
well have given rise to a collateral contract) and had on any view represented
that he could provide it. If NHBC cover could not be provided and the claimants
had known this, then (a) the claimants could have rescinded and refused to
complete and (b) the mortgage monies would not have been forthcoming, so that
they could not in any event have completed.
17 The claimants' pleaded claim alleges breach of a duty of reasonable skill,
care and diligence owed in contract and/or tort. It pleads both that the
defendants should have obtained the NHBC documentation and obtained
confirmation from the NHBC of the builder's continuing registration or informed
the claimants if they had not done so before exchanging contracts on
14
th July 1993
and that they should have been obtained the
same or, in the absence of the same, have refused to permit completion two days
later. The nature of the causation and loss pleaded is important:
"13. The said breach of contract and/or negligence has caused the Plaintiffs to
suffer loss and damage as aforesaid. If the Plaintiffs had been informed that
the Property had no Buildmark guarantee they would not have proceeded with the
purchase. In addition the Plaintiffs suffered inconvenience, distress and
anxiety which caused the second Plaintiff who is aged 48 to suffer a depressive
illness. ...."
18 Neither party's pleadings address very directly the question of the NHBC's
liability or freedom from liability. But it is implicit in the claimants' claim
that the NHBC's denial of liability was justified, and there was no assertion
in the defendants' defence that the NHBC was liable.
19 However, when the matter came on for trial, the defendants' case was that
the Buildmark documentation was properly issued and that there was nothing to
suggest any change of circumstances or need to check on
subsisting
registration. This, we were told by Mr Pooles QC for the defendants, led to
discussion in front of the judge as to how far the defendants could go, bearing
in mind that they had not advanced any positive case that the NHBC was liable.
The defendants argued and it seems to have been accepted that they could
advance the case that, whatever might be the true effect of the NHBC
documentation, any reasonable solicitor would have believed that the NHBC
documentation constituted an open offer, capable of communication by a builder
to and acceptance by a purchaser's solicitors at any time, even after cessation
of the builder's registration. They submitted on this basis that they could not
have committed any breach of duty.
20 The judge's judgment was unreserved. It focuses for the most part on the
defendants' duty to send off, and their failure until 22
nd September
1993 to send off, the Acceptance Form. The judge observed that, whenever this
form had been sent off, the NHBC's stance would have been that there was no
offer to be accepted. In response to a submission that, if it had been sent off
promptly before completion, the claimants would have discovered the true facts
earlier and been able to refuse to complete the contract, the judge
acknowledged that the claimants could have treated the contract as repudiated
or at all events have rescinded it for misrepresentation. He went on:
"But the conclusion of the contract [
query: completion] left them, as I
see it, in no worse position than they were before. The position, it seems to
me, essentially is this: by sending off the completion [
sic: the judge no
doubt meant acceptance] document earlier, Mr Russell Jones would not have
secured for [the claimants] anything more valuable than that which in fact they
did receive, and secondly by sending it off later rather than earlier, he did
not lose for [the claimants] anything which they would have had, had he done it
earlier. I cannot see, in the circumstances, that Mr Jones was at fault in the
work that he did for [the claimants]. It seems to me that Mr Jones did
everything a reasonable solicitor would have done, other than send off the
acceptance form late; but sending off the acceptance form late did not, in my
view, alter [the claimants'] rights as against the parties, and so is of no
consequence."
21 This reasoning is puzzling and deficient. First, it is somewhat difficult
to reconcile with the scope of the preliminary issue, in so far as the judge
purports to decide that completion could have caused no recoverable loss. The
preliminary issue was confined to breach of duty, negligence and causation of
damage. The damage pleaded was completing a purchase which would not otherwise
have been completed. To what, if any, quantum of loss that led (although that
too could involve its own aspects of causation) appears to me to have been a
matter for another day. Secondly, if it was appropriate to make any assessment
whether completion caused, or was likely to cause, loss, in circumstances where
no NHBC cover could exist, then an affirmative answer seems obvious. After all,
completion involved the claimants in disbursing some £40,000 and acquiring
without NHBC cover a house which could and did prove a disaster for them.
Finally, if the defendants had some subtle argument that the claimants could
after completion still have rescinded for misrepresentation and would have been
able to recover the price from the builder before his insolvency, it was
neither pleaded nor investigated - and would seem most unlikely to have force,
not least because it seems to have been the defendants's own continuing
defaults that meant that the claimants remained in ignorance of the problem
about NHBC cover for some years.
22 Unfortunately for the claimants, a claim on the basis identified by the
judge faces another obstacle which the judge did not identify. That is that,
even if the Acceptance Form had been sent off immediately it was received on
16
th July 1993, completion would have taken place before the NHBC
received it, let alone had any chance to reply denying cover. Before us,
counsel for the claimants had effectively to accept that the fact that
completion occurred could not be attributed to any delay in sending off the
Acceptance Form. Further, I see no valid criticism of the defendants for not
obtaining the NHBC documentation earlier than they did, so as to be able to
send it off earlier. It was received in accordance with the procedure
contemplated by NHBC in NHBC's covering letter, and the Law Society's own
Conveyancing Handbook speaks of delivery of such documentation "on exchange of
contracts". Here, it is true, the gap between contract and completion was
unusually short, but, even if the documentation had been received in person on
14
th July 1993 and the Acceptance Form sent off to NHBC on the same
day, NHBC's reply would not have reached the defendants before completion on
16
th July 1993.
23 The only relevant criticism that may therefore be made of the defendants is
that they should, by telephone contact, have confirmed with NHBC between
contract and completion that the offer was available for acceptance, or (to put
the same point in a different way, in the light of NHBC's subsequent attitude)
that the builder remained at the date of contract or completion a "NHBC member"
entitled to pass on the offer. It is the case that the NHBC documentation gave
NHBC's telephone number, though in this different context:
"For claims advice, please ring (0905) 795111".
24 So there would have been no difficulty in telephoning NHBC. One can presume
that if this had been done then NHBC would have taken the same attitude as
subsequently and asserted that Mr Rogers' lack of continuing registration
invalidated the offer which he had purported to pass on.
25 This brings me to what I consider was the core issue in the case, with
which the judge never dealt. Should the defendants as reasonable solicitors
have telephoned NHBC to confirm the validity of the offer? The claimants submit
that, normally, the gap between contract and completion would be sufficient to
allow time for NHBC either to send a Ten Year Notice, so positively confirming
cover, or at least to reply rejecting cover, if there was any problem. But,
they submit, where as here the gap was very short, the solicitors should
anticipate the possibility of some problem and should avert it by the simple
step of telephoning the NHBC to confirm cover.
26 The defendants' response is to ask: why should they have done? They assert
that any reasonable solicitor would, or a reasonable solicitor certainly could,
have regarded NHBC's offer in its documentation as an open and continuing
offer; and as holding out the builder as a NHBC member with authority to pass
it on to a first purchaser. Why should a solicitor think that the offer, or
authority to pass it on, might depend upon the builder member, through whom it
was to be communicated and whose name and membership number appeared on it,
remaining a member at the date of contract or completion? Their case is that a
reasonable solicitor would know nothing of any private limitation or
termination of authority as between NHBC and the builder and could disregard it
as irrelevant; and that, as against a first purchaser, if NHBC wished to limit
the builder's ability to communicate such an offer after termination of his
NHBC membership, it was on the face of it for NHBC either (a) to ensure that on
termination it recovered from the builder any documentation issued prior to
such termination or alternatively (b) in or against the event that it could not
achieve this, to include in the offer or covering letter a condition making it
clear that the continuing validity of the offer (or, which amounts to the same
thing) of the builder's authority to communicate it on depended upon the
builder continuing to be registered with NHBC at the time of sale.They point
out that nothing in the Law Society's Conveyancing Handbook, which summarises
the NHBC scheme and its implications for solicitors, or in any other
conveyancing work suggests any potential problem about, or any duty upon
solicitors to consider, the continuing validity of an NHBC offer or the
continuing membership of the builder member referred to in such an offer.
27 The defendants' response highlights another unsatisfactory aspect of the
way in which this case has proceeded. It seems, as I have stated, to have been
agreed that it was open to the defendants to argue that the NHBC documentation
was in terms which gave no reason for them as reasonable solicitors to approach
NHBC for any confirmation, although not open to them to advance any positive
case that the offer was open for acceptance and that NHBC remained on risk (a
case which would if open have had further implications for issues of causation
and quantum). However, when considering whether the defendants failed to act
with reasonable skill, care and diligence, the permissible argument and the
impermissible case, appear to me, on the particular facts of this case, to be
almost indistinguishable. The NHBC documentation does not involve an esoteric
offer or esoteric or elaborate terms, requiring skill or legal knowledge which
an ordinary reasonable solicitor might lack. Mr Pooles sought to reinforce the
distinction between the permissible and impermissible arguments by arguing that
the NHBC might be free from liability for some unforeseen reason which a
reasonable solicitor could not in 1993 have been expected to contemplate. But,
if the communication of NHBC's offer depended upon the builder continuing to be
registered, the reason, I would have thought, is that a reasonable reader would
understand from the offer that it, or authority to pass it on, depended upon
the builder remaining a NHBC member at the time of sale: see
Investors'
Compensation Scheme Ltd. v. West Bromwich B.S. [1998] 1 WLR 896. If so,
then one would expect any reasonable solicitor to realise that this was its
meaning. If, on the other hand, NHBC's offer was unconditional and authorised
the named builder member to communicate NHBC's offer, without making such
authority dependant upon such membership subsisting throughout some unspecified
period between issue of the documentation and its communication to a first
purchaser, then it is difficult to see why any ordinary solicitor should think
it necessary to telephone NHBC to eliminate the possibility that NHBC might
have, and wish to assert, a contrary view. We were told that unspecified
passages in Bowstead on Agency were referred to below. One may surmise that
they may have included those dealing with the subject of apparent authority and
determination of authority - if so that again underlines the extent to which
the permissible and impermissible arguments tend to merge on the issue of
negligence.
28 When confronted with propositions along the lines outlined in the previous
paragraph, Mr Thomas for the claimants submitted that, in the absence of any
contrary plea, we should proceed, as against the defendants, on the basis that,
under the relevant documentation, NHBC cover depended upon the builder's
membership subsisting at the time of sale. Alternatively, he submitted that the
judgment should be set aside in view of its inadequacies, and the case should
if necessary be remitted for retrial to enable his clients to join the NHBC. Mr
Pooles urged us on the other hand to address the limited issue which remained
and which the judge did not address, whether a solicitor would or could
reasonably have regarded the NHBC offer as one which it was open to the builder
to communicate and open to the defendants, on behalf of the claimants, to
accept.
29 In these less than satisfactory circumstances, I have come to the
conclusion that, before attempting to grapple further with the problems raised
by this case, we should take some steps to try to encourage its overall
resolution. It is a matter of regret that all the relevant persons or bodies
involved, including the NHBC, are not before the court. But the procedures of
alternative dispute resolution ("ADR") do not depend upon commencement of
proceedings. I consider that we should adjourn further proceedings in this
court and stay delivery of any final judgment for a limited period, to enable
the parties to take such serious steps as they may be advised to resolve their
disputes by ADR, both as between themselves and, although the NHBC is not
formally involved in proceedings, in relation to the NHBC. Mr Pooles sought to
discourage us from such a step on the basis that the NHBC was most unlikely to
participate, in the absence of any proceedings and after so long a period since
claims were first made against it and since they were last pursued against it
in 1996. I do not take so pessimistic a view. This order is of course only
directed to the parties to this appeal. This court has no jurisdiction over the
NHBC, but it seems to me that not only the present parties, but also the NHBC
may, in the light of this judgment, consider that ADR has something to offer
which it would be worth each of them exploring. If ADR procedures lead to
resolution of this appeal, that will be a happy outcome. If they do not, the
appeal should be restored for judgment. In the latter situation, if ADR
procedures have in the meanwhile had the incidental effect of further
elucidating NHBC's grounds for denial of cover, that may also assist
consideration of the issue, what a reasonable solicitor would have understood
about the availability of NHBC cover and the builder's ability to communicate
the NHBC offer.
30 We should hear counsel on the precise terms of the order, but I set out a
draft of the terms which I have presently in mind:
1. The claimants and defendants shall within two weeks of today's date
identify, and shall (forthwith) invite the NHBC to identify within the like
period, the names of three neutral individuals, or of one or more bodies or
panels, available to conduct ADR procedures in this case within eight weeks of
today's date.
2. They shall within three weeks of today's date in good faith endeavour to
agree, both between themselves and with the NHBC, the identity of a neutral
individual or panel to conduct such ADR procedures.
3. The parties shall take such serious steps as they may be advised, both
between themselves and with the NHBC, to resolve any disputes by ADR procedures
by the end of November 2000.
4. If the case is not finally settled by the end of November 2000, or if prior
to that date ADR procedures or steps towards such procedures come finally to an
end, the parties shall inform the court by letter within seven days or by
6
th December 2000 (whichever is the earlier) as to the position,
and, without prejudice to matters of privilege, as to why such steps have
failed; and both parties shall in that event also have liberty to submit in
writing to the court within seven days or by 6
th December 2000
(whichever is the earlier) any further submissions about the basis on which the
NHBC offer could or could not have been treated as open for communication
through the builder at the time of sale of the property to the claimants; if
either party wishes to address oral submissions on this or any other aspect,
the matter shall be restored for oral submissions in court before judgment as
soon as possible and in any event (unless the court otherwise orders) before
the end of Michaelmas Term 2000.
Mrs. Justice Smith
31 I agree.
Order: Proceedings adjourned and judgment stayed pending the ADR scheme.