England and Wales Court of Appeal (Civil Division) Decisions
You are here:
BAILII >>
Databases >>
England and Wales Court of Appeal (Civil Division) Decisions >>
Ahmad Al-Naimi (t/a Buildmaster Construction Services) v Islamic Press Agency Incorporated [2000] EWCA Civ 17 (28 January 2000)
URL: http://www.bailii.org/ew/cases/EWCA/Civ/2000/17.html
Cite as:
[2000] 1 Lloyd's Rep 522,
[2000] EWCA Civ 17
[
New search]
[
Printable RTF version]
[
Help]
Case No: QBENI 1998/1646/A2
IN THE SUPREME COURT OF JUDICATURE
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM HIGH COURT OF JUSTICE
TECHNOLOGY AND CONSTRUCTION COURT
His Honour Judge Bowsher QC
Royal Courts of Justice
Strand, London, WC2A 2LL
Friday, 28 January 2000
B e f o r e :
LORD JUSTICE WALLER
LORD JUSTICE CHADWICK
- - - - - - - - - - - - - - - - - - - - -
|
AHMAD
AL-NAIMI
(T/A BUILDMASTER CONSTRUCTION SERVICES)
|
Claimant/Appellant
|
|
-
and -
|
|
|
ISLAMIC
PRESS AGENCY INCORPORATED
|
Defendant/
Respondent
|
- - - - - - - - - - - - - - - - - - - - -
(Transcript of the Handed Down Judgment of
Smith Bernal Reporting Limited, 180 Fleet Street
London EC4A 2HD
Tel No: 0171 421 4040, Fax No: 0171 831 8838
Official Shorthand Writers to the Court)
- - - - - - - - - - - - - - - - - - - - -
Michael Black Esq QC, Mr Rupert Higgins (instructed by Messrs Bowling
& Co for the Claimant/Appellant)
John Randall Esq QC, Mr Piers Stansfield (instructed by Messrs Masons
for the Defendant/Respondent)
Judgment
As Approved by the Court
Crown Copyright ©
Friday, 28 January 2000
JUDGMENT
LORD JUSTICE WALLER:
This is an appeal from the decision of His Honour Judge Bowsher QC in the
Technology and Construction Court of 2 October 1998 whereby he stayed the
claimant's action under
section 9 of the
Arbitration Act 1996. In so doing he
refused to decide whether the matters the subject matter of the action were
covered by the arbitration agreement relied on by the defendants. The appeal
raises a point as to the proper approach of the court to an application under
section 9 of the 1996 Act particularly in the light of the change in the law
brought about by the same Act as to an arbitrator's powers to decide his own
jurisdiction.
The claimant carries on business as a building contractor. The defendant
occupies a large property at East Burnham in Buckinghamshire which in 1996 it
wished to convert into offices and accommodation. The defendant retained as
its advisor Mr Kassim of ASK Planning who has sworn the affidavits in this
matter on behalf of the defendant.
On 12 July 1996 the claimant entered into a building contract with the
defendant in the form JCT Agreement for Minor Building Works 1980 Edition to
carry out certain works under the supervision of ASK Planning as Contract
Administrator.
The works were described as the alteration and refurbishment of the so-called
"Block B", of Crown House, and were shown and described in drawings, a
Specification and a Supplementary Priced Schedule. The supplementary priced
schedule stated that it should be read with certain documents including the
drawings, and listed the items of work. It provided that "The list forms part
of the contract and represents the formally priced work by the Contractor up to
and including all first fixes and some second fix." The price for the works
identified was £141,750.
By Article 4 it was agreed so far as material as follows :-
"If any dispute or difference as to the construction of this Agreement or any
matter or thing of whatsoever nature arising thereunder or in connection
therewith . . . shall arise between the Employer or the Architect/the Contract
Administrator on his behalf and the Contractor either during the progress or
after the completion or abandonment of the Works or after the determination of
the employment of the Contractor it shall be and is hereby referred to
arbitration in accordance with clause 9."
It is common ground that the claimant carried out further works other than
those identified in the schedule and as part of what is described as "the
second fix". It is the claimant's case that those works were carried out under
a separate contract made orally, which did not contain any of the terms of the
JCT form including the Arbitration Clause. It is on that basis that he has
brought this action as opposed to commencing arbitration.
It is right to say that when matters began to go sour as between the parties,
those conducting the correspondence on the part of the claimant pursued the
matter as if there were simply one contract relying on JCT terms as applying to
the works asserted now to have been concluded under the separate oral contract.
It seems likely that it would have been a matter of indifference to the
claimant as to whether the matter went to arbitration, or was the subject of
proceedings in court, but for the fact that he could not get Legal Aid to
conduct the arbitration. It is convenient at the outset to put the question of
legal aid on one side.
Section 31 of the
Legal Aid Act 1988 provides:-
"(1) Except as expressly provided by this Act or regulations under it -
(a) . . .
(b) the rights conferred by
this Act on a person receiving advice, assistance
or representation under it shall not affect the rights or liabilities of other
parties to the proceedings or the principles on which the discretion of any
court or tribunal is normally exercised."
Thus, as was common ground before us, it is the duty of the court to resolve
any issue as between the parties without regard to the fact that one of them is
legally aided; (see in the Arbitration context albeit in the context of the
1950 Act this principle was confirmed in
Edwin Jones v Thyssen (Great
Britain) Ltd (1991) 57 BLR 116).
Approach to application for stay under section 9
The judge in this case was dealing with the matter under the Rules of the
Supreme Court. It is by those rules which this court must judge whether the
judge erred in the exercise of his discretion. If this court was to be of the
view that he did err, then this court should act under the new CPR although I
am doubtful whether in the context of an application under
section 9 the
approach will be very different.
Under the old rules, and in the context of a dispute as to whether there was a
contract, and in particular a contract that contained an arbitration clause,
His Honour Judge Humphrey Lloyd QC considered how the court should approach a
section 9 application in
Birse Construction Ltd v St David Ltd [1999] BLR 194. His decision was reversed on appeal (see Transcript Friday 5 November
1999), but I do not understand his suggestions as to approach, save conceivably
on one aspect, to have been criticised. The reversal resulted (a) from the
fact that the parties had failed to make clear to him, that they were not
agreed that he should decide the question whether there was an arbitration
agreement on the affidavit evidence alone, and (b) because the majority thought
that without that agreement, it would be an illegitimate exercise of discretion
in that case, to decide to determine, and then to determine the question
whether there was a contract upon affidavit evidence, which showed a genuine
dispute of relevant fact; (see Pill LJ at page 4 and Aldous LJ at page 7). His
approach must of course be read with that last point in mind.
I find that what he had to say about the approach to a
section 9 application
very helpful, and both Counsel before us suggested that it provided useful
guidance. It is particularly helpful to note his attitude to the situation in
which what is in dispute is not whether a clause exists at all but as to
precisely what is covered by that clause. I will set out the relevant passage
in full:-
"It is common ground that the following courses are open to me:
1. To determine, on the affidavit evidence that has been filed, that an
arbitration agreement was made between the parties, in which case the
proceedings will be stayed in accordance with
section 9 of the 1996 Act since
article 5 and clause 41 of the JCT Conditions contain an arbitration agreement;
2. To stay the proceedings but on the basis that the arbitrator will decide
the question of whether or not there is an arbitration agreement since
section
30 of the
Arbitration Act 1996 provides -
(1) Unless otherwise agreed by the parties, the arbitral tribunal may rule
on its own substantive jurisdiction, that is, as to -
(a) whether there is a valid arbitration agreement,
. . .
(c) what matters have been submitted to arbitration in accordance
with the arbitration agreement.
(2) Any such ruling may be challenged by any available arbitral
process of appeal or review or in accordance with the provisions of
this Part.
Sub section (2) is a reference to provisions such as
section 67 which states -
(1) A party to arbitral proceedings may (upon notice to the other
parties and to the tribunal) apply to the court -
(a) challenging any award or the arbitral tribunal as to its
substantive jurisdiction; . . .
3. Not to decide the question immediately but to order an issue to be tried.
RSC Order 73, rule 6(2) provides -
Where a question arises as to whether an arbitration agreement has been
concluded or as to whether the dispute which is the subject matter of the
proceedings falls within the terms of such agreement, the court may determine
that question or give directions for its determination, in which case it may
order the proceedings to be stayed pending the determination of that question.
4. To decide that there is no arbitration agreement and to dismiss the
application to stay.
Mr Darling for the plaintiff contended that there should be no stay of the
proceedings unless the court was satisfied that there was clearly an
arbitration agreement. I do not consider that the position is that clear cut.
The circumstances of the application must be taken into account. I accept that
if it is clear on the evidence that a contract did or did not exist then the
court should so decide for it cannot be right either to direct an issue
pursuant to Order 73, rule 6(2) or to leave the "dispute" to be determined by
an arbitral tribunal. The dominant factors must be the interests of the
parties and the avoidance of unnecessary delay or expense. Where the rights
and obligations of the parties are clear the court should enforce them. Unless
the parties otherwise agree
section 30 of the
Arbitration Act 1996 now permits
an arbitral tribunal to decide questions of jurisdiction where it might not
previously have been competent to do so. It is not mandatory and, contrary to
a suggestion made by Mr Palmer, the existence of the power does not mean that a
court must always refer a dispute about whether or not an arbitration agreement
exists to the tribunal whose competence to do so is itself disputed. The Act
does not require a party who maintains that there is no arbitration agreement
to have that question decided by an arbitral tribunal. Indeed RSC Order 73,
rule 6 in making express provision for a decision as to whether there is an
arbitration agreement suggests that normally a court would first have to be
satisfied that there is an arbitration agreement before acting under
section 9
(and that a dispute about such a matter falls outside section 9). There will
however be cases where it would be right to defer the decision, particularly,
for example, if the determination of whether or not a contract was made also
embraces the determination of the scope of the contract and its ingredients.
In some cases it would be better for the court to act under Ord 73 r6; in other
cases it may be appropriate to leave the matter to be decided by an arbitrator.
The latter course is likely to be adopted only where the court considers that
it is virtually certain that there is an arbitration agreement or if there is
only a dispute about the ambit or scope of the arbitration agreement. One of
the matters that a court is bound to take into account is the likelihood of the
challenge to an award on jurisdiction under
section 67 or, under
section 69, on
some important point of law connected to the existence of the agreement for
which leave to appeal might be given (if it is plainly discernible at that
early stage), eg its proper law, since it cannot be in the interests of the
parties to have to return to the court to get a definitive answer to a question
which could and should be decided by the court before the arbitrator embarks
upon the meat of the reference. Such a course would mean that the arbitral
proceedings would not be conducted without unnecessary delay or expense. On
the other hand the court must bear in mind that it must not act so as to
deprive the party of the benefit of the contract that it has made whereby
disputes are to be referred to arbitration. The recent case of
Azov
Shipping Co v Baltic Shipping Co [1999] 1 Lloyd's Rep 68 (which was not
cited to me) supports the approach that the court ought to decide questions
relating to the existence or the terms of the arbitration agreement for there
may otherwise be a real danger that there will be two hearings: the first
before the arbitrator under
section 30 of the
Arbitration Act 1996 and the
second before the court on a challenge under
section 67."
I would entirely support the above approach in relation to an application under
Order 73 rule 6(2) subject only to the point ultimately made by the Court of
Appeal. If the court decides that it is the court which should determine
whether the matters the subject of the action are the subject of an arbitration
clause, unless the parties were agreed that the matter should be resolved on
affidavit, then, if there is a triable issue, directions should be given for
trying that issue. It may be helpful to add that the equivalent of Order 72
rule 6(2) now appears in the CPR Part 49 paragraph 6.2 in almost identical
terms, and it would seem that the approach should thus be the same. It is
right to point out that under the CPR the court has a wider discretion to rule
what evidence it needs to decide any particular point (see Part 32.1).
However, it seems unlikely, in the absence of agreement that issues should be
tried on witness statements alone, that a court, which (a) formed the view that
there were triable issues relating to facts material to the jurisdiction
question; (b) had an application before it to cross-examine the makers of those
statements; and (c) had decided that the court should resolve the matter as
opposed to an arbitrator, would do other than direct a trial of the issue.
The only other point I would make so far as the above approach is concerned is
that it must not be overlooked that the court has an inherent power to stay
proceedings. I would in fact accept that on a proper construction of
section 9
it can be said with force that a court should be satisfied (a ) that there is
an arbitration clause and (b) that the subject of the action is within that
clause, before the court can grant a stay under that section. But a stay
under the inherent jurisdiction may in fact be sensible in a situation where
the court cannot be sure of those matters but can see that good sense and
litigation management makes it desirable for an arbitrator to consider the
whole matter first. If, for example, the court thinks that it would take a
trial with oral evidence to decide whether matters the subject of the action
were actually within the scope of an arbitration clause, but that it was likely
that on detailed inquiry the subject matter of the action will be found to be
covered by the arbitration clause; and particularly if an arbitration was bound
to take place in relation to some issues between the parties, and where having
explored the details necessary to found jurisdiction, it would only be a short
step to deciding the real issues, it will often be sensible for the court not
to try and resolve that question itself but leave it to the arbitrator.
It is true that since the matter goes to jurisdiction there is a risk that the
matter might come back to the court under
section 67, but since costs and time
are, in the example given, going to be expended on matters that relate to
jurisdiction and once the tribunal who hears that evidence will be in a strong
position to move quickly on to resolve the main issues- the risk will often be
worth taking. This seems to me in accordance with the spirit of the 1996 Act
and in particular
sections 30, and 32(2).
That as it seems to me was the view that Judge Bowsher took in this case, and
but for one factor, I would not in any way criticise his decision. The one
factor is that the parties had agreed that the issue whether the arbitration
clause applied to the matters the subject of the action should be determined by
the court on the affidavit evidence.
I of course accept that there may be situations when despite that agreement the
court may simply feel that it cannot resolve the issue without hearing the
witnesses. But it also seems to me that the court should be looking for the
most economical way of deciding what is after all, a dispute about where the
real disputes should be resolved. On an application under
section 9 a court is
bound to have to consider the affidavit evidence, and to spend time in so
doing. There is bound to be argument about the strength or otherwise of the
case as to whether the arbitration clause covers the subject matter of the
action in considering what course to take. It thus also seems to me that in
the interest of good litigation management and the saving of costs, the court
should see whether it can resolve that point on the affidavit evidence.
Certainly it should try and do so if both parties are agreed that they would
like the matter resolved on the affidavits. I would add that in addition, if
the parties do not come agreed, as in the instant case, depending on how
important any factual disputes appear to be to the ultimate resolution of the
disputes as to jurisdiction, it may be worth exploring whether they would
agree, or even in some circumstances where the disputes on fact seem
immaterial, using the powers under CPR 32.1.
On the application before Judge Bowsher both sides wanted the judge to resolve
the matter on the affidavits. Before us in the Court of Appeal once again both
sides wanted the court to resolve the matter on the affidavits. Thus it was
that there came a request from neither side to cross examine any deponent on
their affidavit. It seems to me that if it is the wish of both parties that a
point on jurisdiction should be resolved on the affidavits, it must be in their
interest for the court to try and do so in order that further time and money is
not spent either before the arbitrator fighting about jurisdiction with a
possible reference back to the court at some later stage, or by directing a
trial of the issue.
In my view in this case it is possible to resolve the question of jurisdiction
on the affidavits, and I would thus say that Judge Bowsher was wrong not to
grasp that nettle. The factual disputes are in reality very small, and it is
possible to form a clear conclusion as to what would be likely to be the
position if a full trial of the jurisdiction issue were ordered.
The common ground is as follows. The claimant originally quoted with others
for the works to carried out to Crown House Block B. The quotes were for first
and second fix works, but tenderers were told that they should quote separately
for the second fix because decisions had not yet been taken as to the choice of
materials for the second fix. Thus the quotes for the second fix were simply
to give indications as to the prices from the different tenderers. In his
quote the claimant did quote for certain finishing items in the second fix.
The defendants originally contracted with one of the other tenderers, and that
contract excluded second fix and finishes. That contract was terminated and a
contract was then signed with the claimant. This contract was not limited to
first fix. The contract was dated 12 July 1996 and under it the appellant
agreed to carry out certain works described as "first fix and part second
fix".
In July and August the claimant and Mr Omar on behalf of the defendants went on
what are termed "shopping trips" to select high quality items for the finishes
i.e. the second fix. The claimant says he went on those so as to impress Mr
Omar and in the hope that he would be asked to carry out the remaining second
fix works. During August Mr Omar started to finalise his choices and,
according to the claimant, he was asked at that stage to provide his prices for
those items. The claimant accepts that he was then asked to do the second fix
items. He concluded that it was Mr Kassim's intention that he should do the
second fix works as and when it became possible in each part of the building
(paragraph 11 of claimant's affidavit). The claimant required payment in
advance in order to purchase the more expensive items and it was in that
context that Mr Kassim produced an interim payment certificate dated 25
September 1996 which albeit it had the same job number as those certificates
otherwise produced in relation to Crown House, and was otherwise in the JCT
form of such certificates, referred to a "Second fix negotiated contract" and
not to the 12 July 1996 Contract. The certificate was produced in response to
an invoice dated 25/9/96 from the appellant which referred to "second face
[sic]" (page 85), and the appellant produced a second invoice also referring to
"second fase [sic]" for payment in advance. On 10 October 1996 Mr Kassim
produced a further interim certificate again referring to "Second fix
negotiated contract". The claimant does not suggest that a fresh negotiation
of some completely new overall contract for the second fix was negotiated, but
relies on the above documents as being consistent only with a separate
"negotiated contract."
There have also been produced by the defendants some Architects instructions
issued in accordance with the terms of the first contract but covering matters
said to be the subject of the second fix. The claimant asserts that these were
not received .
The claimant finally relies on a document by which Mr Kassim summarised for Mr
Omar's benefit the payments due to the claimant distinguishing between the
first fix contract and the "second fix negotiated contract", but that really
does not take the claimant very far having regard to the fact that the "final
account" issued to the claimant and signed by Mr Kassim purported to be issued
in accordance with the JCT contract dated 12 July 1996 covered all the works
carried out by the claimant at Crown House Block B. Not only did the claimant
not object to that form of final account, but when his adviser Mr Turnbull for
Bucknall Austin wrote making claims, he made those claims on the basis that
there was simply one contract of 12 July 1996, and he copied that letter to the
claimant himself [see the letter of 8 January 1997 page 147].
From 8 January for some four months all correspondence was conducted on the
basis that there was one contract and indeed the detailed claim ultimately put
in on 27
March 1997 was also put in on the basis of there being one
contract.
Only just prior to these proceedings being launched was there a change of heart
in a letter dated 6 May 1997 when Mr Turnbull asserted that re-examination of
the contract documentation indicated that the JCT form only applied to the
First Fix contract.
I accept that it is possible to divide the contract into two phases. The
second phase was being negotiated item by item at the conclusion of the works
on Crown House Block B, which explains the interim certificates issued for
advance payments. But even those certificates are only consistent with the JCT
form applying to the items, and the obvious and only realistic conclusion is
that the claimant agreed to carry out the extra works as an extension of the
original contract. Accordingly the terms of that contract, including the
arbitration provision, applied to the remainder of the second fix, and thus to
the works the subject of the present proceedings.
In my view this appeal ought to be dismissed but it ought to be made clear that
the decision of the court is that the arbitration clause in the contract of 12
July 1996 covers the matters raised in the statement of claim and that that
issue has accordingly been resolved in favour of the defendant.
Chadwick LJ: The issue between the parties is whether the
additional works - that is to say the second-fix works over and above those
described in the schedule to the JCT agreement dated 12 July 1986 - carried out
by the appellant at the respondent's property were carried out under the terms
of that agreement or under a separate contract, made orally between them. It is
common ground that if the additional works were carried out under the terms of
the JCT agreement, then the underlying claim in the action is the subject of an
arbitration agreement and the action must be stayed under
section 9 of the
Arbitration Act 1996; but that, if the additional works were carried out a
separate oral contract, there is no basis for a stay of the action.
The judge declined to decide that issue. He took the view that that issue
should, itself, be decided by arbitration. He said this:
13. Both counsel urged upon me that I should decide upon those contentions
raised between the parties and that I should do so by reference to the
affidavits and exhibits before me. Counsel for the plaintiff submitted that for
the defendants to be entitled to a stay of the proceedings, the burden was on
the defendants to show that there is a relevant arbitration clause: he further
submitted that it is for the Court to decide whether the arbitration clause is
relevant, and to do so the Court must decide the issues raised in the
affidavits. I did not understand the defendants to dissent from those
propositions.
14. If I were to embark upon the task of making such decisions, I would only do
so after hearing oral evidence to enable me to decide on the conflicts in the
documentary evidence. If that were my task, there would be no difficulty about
adjourning this hearing for the deponents to be cross-examined on their
affidavits.
15. I am clear that I should not decide those disputes laid before me by
counsel. Counsel are asking me to decide disputes concerning the construction
of the agreement of 12 July 1996 and also to decide disputes as to "matter(s)
... arising thereunder or in connection therewith", namely, for example,
whether certain items of work fell within the description of work the subject
of the contract of 12 July, 1996 as properly construed. Those disputes are
disputes which the parties have agreed shall be submitted to arbitration, and
they are not therefore matters for me to decide.
For my part, I think that the judge is saying, in those paragraphs, that he
should decline to decide the dispute raised on the affidavits because that is a
dispute which must be referred to arbitration in accordance with the
arbitration agreement. If so, then I would hold that he adopted a wrong
approach. The correct approach, as it seems to me, is that set out by His
Honour Judge Humphrey Lloyd QC in his judgment in
Birse Construction Ltd v
St David Ltd [1999] BLR 194, at pages 196-7, delivered after the judgment
of His Honour Judge Bowsher QC in the present case. In a case where the issue
is whether the underlying dispute is subject to an arbitration agreement at all
the court has a choice whether to decide that issue itself, or to stay
proceedings while that that issue is referred to arbitration. Judge Humphrey
Lloyd's judgment in
Birse contains, as it seems to me, a most useful
analysis of the factors which should influence the court in making that choice.
I agree with Lord Justice Waller that, if the court decides that the
proceedings should be stayed so that the issue can be referred to arbitration,
the better view is that it is acting under the inherent jurisdiction rather
than under
section 9 of the 1996 Act.
If the judge had a choice, then it was clearly material for him to take into
account whether the issue was one which could be determined on affidavit
evidence without oral evidence. I agree with Lord Justice Waller that it would
be a rare case in which it could be appropriate for the court to resolve issues
of fact on written evidence alone unless invited to take that course by both
parties; although I would not rule out the possibility that such a case might
arise. I agree, also, that the court must be entitled to decline an invitation
(although made with the support of both parties) to embark on the task of
resolving issues of fact without the advantage of oral evidence in a case where
it thinks oral evidence is necessary. But, where both parties ask the court to
decide the issue in a summary way, the court should, I think, meet that request
if it properly can.
This, in my view, was such a case. I think that the judge was wrong to take the
view that the issue between the parties was one which could not be decided
without cross-examination on the affidavits. The documents pointed so clearly
to the conclusion that there was, in this case, a single contract to be carried
out in two phases - rather than two distinct contracts - that there was no
realistic chance that the court would come to a different conclusion after
hearing oral evidence.
To my mind, the documents which provide compelling evidence of the true nature
of the arrangement are (i) the final account dated 18 November 1996 together
with the letter from the Contract Administrator dated 26 November 1996, (ii)
the payment certificate issued by the Contract Administrator on 26 November
1996, (iii) the letter dated 8 January 1997 from the appellant's Contract
Advisers, Bucknall Austin, and (iv) the claim put in by Bucknall Austin on 27
March 1997 on behalf of the appellant. The assertion, in a subsequent letter
from Bucknall Austin dated 6 May 1997 that "re-examination of the contract
documentation appears to indicate that the terms of the JCT Agreement for Minor
Building Works relate solely to the First Fix Contract and that no express
terms were agreed in relation to the Second Contract" carries no conviction. It
is inconsistent with the way in which the matter had been dealt with by the
Contract Administrator (without objection from their client) in November 1996
and with the way in which they themselves had dealt with the matter in the five
months since they were first instructed in January 1997. The true nature of the
arrangement was that there was a single contract on the terms of the JCT
Agreement of 12 July 1996, initially for fixed price works (the first phase),
which was subsequently extended, as the appellant had always hoped and intended
that it would be, to cover a second phase of works to be done on an on-cost
basis.
For those reasons, and for the reasons given by Lord Justice Waller, I am
satisfied that the arbitration agreement extends to the matters claimed in the
action; and that, on that ground, the action ought to be stayed under
section 9
of the
Arbitration Act 1996. It follows that the appeal should be dismissed;
but with the indication, proposed by Lord Justice Waller, that the issue left
open by the judge has been decided by this Court in favour of the respondent.
Order: Appeal dismissed with costs; Section 18 order subject to
confirmation of contribution; legal aid assessment.
(Order does not form part of approved judgment).