England and Wales Court of Appeal (Civil Division) Decisions
You are here:
BAILII >>
Databases >>
England and Wales Court of Appeal (Civil Division) Decisions >>
Byrne & Anor v Hall Pain & Foster (A Firm) & Ors [1998] EWCA Civ 1939 (11 December 1998)
URL: http://www.bailii.org/ew/cases/EWCA/Civ/1998/1939.html
Cite as:
[1999] WLR 1849,
[1998] EWCA Civ 1939,
[1999] 1 WLR 1849,
[1999] PNLR 565
[
New search]
[
Printable RTF version]
[Buy ICLR report:
[1999] 1 WLR 1849]
[
Help]
Case
No: QBENI 98/0784/1
IN
THE SUPREME COURT OF JUDICATURE
COURT
OF APPEAL (CIVIL DIVISION)
ON
APPEAL FROM MR JUSTICE LAWS
Royal
Courts of Justice
Strand,
London, WC2A 2LL
Date:
Friday 11th December 1998
B
e f o r e :
LORD
JUSTICE SIMON BROWN
LORD
JUSTICE OTTON
and
LORD
JUSTICE SCHIEMANN
-
- - - - - - - - - - - - - - - - - - - -
|
BYRNE
AND BYRNE
|
Appellants
|
|
-
and -
|
|
|
HALL
PAIN & FOSTER (a Firm) & Ors
|
Respondents
|
-
- - - - - - - - - - - - - - - - - - - -
(Handed
down transcript of
Smith
Bernal Reporting Limited
180
Fleet Street, London EC4A 2HD
Tel:
0171 421 4040 Fax: 404 1424
Official
Shorthand Writers to the Court)
-
- - - - - - - - - - - - - - - - - - - -
Mr
P McCormick (instructed by Anderton & Co., Portsmouth for the Appellants)
Mr
A Parsons (instructed by Grindeys, Stoke-on-Trent for the Respondents)
-
- - - - - - - - - - - - - - - - - - - -
J
U D G M E N T
(As
approved by the court)
©Crown
Copyright
LORD
JUSTICE SIMON BROWN:
This
appeal raises a short point concerning the date of accrual of the cause of
action, for the purposes of the applicable six year limitation period, in
relation to a claim in tort for damages for professional negligence brought by
a purchaser of property against a firm of valuers. More particularly the
question raised is whether the cause of action accrues when contracts are
exchanged or when the purchase is completed. Laws J below held in the
defendants’ favour that time begins to run when contracts are exchanged
so that the plaintiffs’ action fell to be struck out as statute barred.
The plaintiffs now appeal by leave of the single Lord Justice.
With
that brief introduction let me set out the few material facts and indicate the
circumstances in which the point comes before the court.
The
plaintiffs proposed to purchase a residential flat in Portsmouth. Their
mortgagees commissioned a valuation report from the first defendant firm. On
2nd June 1988 the second defendant, a chartered surveyor employed by the first
defendants, inspected the property and prepared a written report. The
plaintiffs did not seek an independent report for themselves. It is pleaded
on their behalf (and for present purposes their pleaded case must be assumed
factually correct) that they relied on the first defendants’ report
commissioned by the building society. So relying on it, they exchanged
contracts to purchase the lease of the flat on 8th July 1988. Completion took
place a fortnight later on 22nd July 1988. Thereafter defects in the property
came to light. They were defects which the plaintiffs say should have been
detected when the second defendant inspected the flat and accordingly should
have been described in the report. That not having been done, the
plaintiffs’ case is that the defendants’ valuation report was
negligently made, and in purchasing the flat in reliance upon it they have
suffered loss. Prominent amongst the defects which they say should have been
discovered and revealed by the report were problems relating to condensation
and/or water penetration. Although it is difficult to discover from the
plaintiffs’ pleadings precisely how they put their claim for damages, Mr
McCormick tells us that the measure of damage sought is the difference between
the price paid for the property (£38,500) and its value as it should have
been described (which he asserts to have been some £26,000).
The
plaintiffs’ writ was issued on 18th July 1994, that is to say more than
six years after exchange but less than six years after completion. The
primary limitation period is all-important here. The plaintiffs acknowledge
that they cannot take advantage of the extended period under s.14A of the 1980
Act: all the relevant facts were known to them well before 19th July 1991
(three years prior to the issue of the writ).
Having
pleaded that the plaintiffs’ claim is barred by s.2 of the 1980 Act, the
defendants applied under RSC order 18 r.19 for the action to be struck out.
On 15th January 1998 the district judge refused the application, concluding
that the law was not sufficiently clear to justify striking out the claim as
frivolous, vexatious or an abuse of process. On 7th April 1998 Laws J allowed
the defendants’ appeal. On the substantive issue he held that:
"...
the plaintiffs’ cause of action in this case accrued at exchange of
contract. On that date the plaintiffs by their irrevocable commitment to the
purchase of the flat suffered damage by virtue of the defendants’
putative negligence sufficient to crystallise or complete their cause of action."
As
to the procedural objection that the case is not sufficiently clear to justify
striking out the action under order 18 r.19 - see paragraph 18/19/11 at page
349 of the Supreme Court Practice (1999 Vol.1) - Laws J said this:
"...
the argument would mean that merely because the law is doubtful or difficult I
should decline to decide the point on this strike-out appeal. Were I to take
that course, the case would go to trial and the trial judge would have to
decide it. That cannot possibly be right. The question, from what date time
runs in this case, is discrete and specific. I am clearly in as good a
position to decide it as would be the trial judge, and it is in the
parties’ interest that I do so. As I understand it, it has never been
the law that because a strike-out application may turn on a difficult legal
point, that itself requires the court to refuse the application. Indeed some
of the common law’s seminal cases, such as
Donoghue
v Stevenson
and
Dorset
Yacht,
were decided on such applications or as preliminary points before trial. The
right approach is for the court to proceed on the footing that all the factual
allegations made by the plaintiff are true and then decide whether the
plaintiffs’ case is arguably sustainable. If at law it is doomed to
failure, it should be struck out."
Although
before this court the plaintiffs have returned to the procedural point (which,
indeed, they were given express leave to argue), Mr McCormick has been content
to rely upon his written argument and not to press the matter in oral
submission. His essential contention is that the order 18, r.19 procedure is
inappropriate to resolve a difficult and novel point of law of general public
interest. For my part I would reject this contention. No doubt it is more
conventional to decide such points by way of preliminary issue under order 33
r.3. Given, however, that no evidence was required, that would have brought
no possible advantage. In short, I find myself in full agreement with Laws
J’s view upon this question. It is also, I believe, supported by what
Lord Templeman said in
Williams
& Humbert v W & H Trade Marks
[1986] AC 368 at 436. I accordingly turn to the central point at issue.
It
is perhaps surprising that this point has not previously been decided.
Whilst, however, both sides can point to various dicta in the authorities
suggesting one conclusion rather than the other, neither can point to a case
where the distinction between exchange and completion was, as it is here,
decisive.
It
is convenient to start by noting what Jackson and Powell on Professional
Negligence (4th Edition 1997) have to say upon the issue. Paragraph 1-114
reads:
"Where
a person purchases property in reliance on a survey report which fails to
disclose material defects, the courts have repeatedly held that the measure of
damages is the difference between the price paid and the value of the property
as it ought to have been described. Quite consistently with this approach,
Judge Hawser QC held in
Secretary
of State for the Environment v Essex Goodman & Suggitt
[1986] 1 WLR 1432 that the cause of action accrued when the plaintiffs acted in
reliance on the survey report (and became irrevocably committed to lease the
property in question). In the case of a house purchaser, the cause of action
would normally accrue when contracts are exchanged. This approach was adopted
in
Horbury
v Craig Hall & Rutley
[1991] CILL 692."
Strongly
though that paragraph appears to support the defendants’ argument, there
are these comments to be made about it. First and most obviously, neither of
the cases there referred to binds us: both were decided by official referees (
Horbury
by Judge Bowsher QC). Second, it appears from consideration of the facts of
those cases that in any event it probably mattered not whether time started to
run at exchange or completion: the real issue in
Essex
Goodman
was whether it started to run from some later date entirely i.e. when physical
damage occurred, and in
Horbury
(where the proposition that time ran from exchange went by concession) the
issue was whether the plaintiffs could rely on s.14A of the 1980 Act.
Those
comments notwithstanding, the defendants are entitled to point to this passage
in Judge Hawser’s judgment at page 74:
"In
my judgment, the submissions of counsel for the third defendants correctly
state the law in cases where the duty is simply that of taking reasonable care
to ensure that the damage is reported to the client. In my opinion, this is
such a case. If the damage had not occurred at the date of the report, the
third defendants would not be liable at all. If it was then in existence and
reasonably discoverable, they would have been liable immediately the plaintiffs
committed themselves to the lease."
Judge
Hawser there was evidently accepting the defendants’ central submission
that the plaintiffs’ cause of action accrues at the point when they
become irrevocably committed to the lease.
Emmet
on Title (Vol. 1, release 34, paragraph 1.065) adopts the same approach, also
in reliance on
Essex
Goodman
:
"In
principle, time runs in respect of a negligent survey as from the date of
reliance on the report (e.g. by exchanging contracts) not from the occurrence
or discovery of damage or defects."
I
next pass briefly to a small group of cases relied on by Mr McCormick for the
language in which the judgments are expressed, the language of completion.
Perry
v Sidney Phillips & Son
[1982] 1 WLR 1297 was a Court of Appeal decision affirming a line of authority
to the effect that in ordinary cases involving the purchase of property at a
price in excess of its market value as a result of wrong advice the measure of
damage “is simply the difference between what the plaintiff paid for the
property and its value at the date when he obtained it” (per Oliver LJ at
page 1304). He “obtained it” at completion, submits Mr McCormick.
Westlake
v Bracknell District Council
[1987] 1 EGLR 161 was the decision of a Deputy High Court judge that in a
surveyor’s negligence case time started to run when the property was
purchased and not some eight years later when the plaintiffs issued their writ:
"It
is clear that the plaintiffs have suffered damage by reason of this negligence
because they have bought a house which has proved to be unsaleable by reason of
the defective floor. This state of affairs came into existence as soon as
they completed their purchase in July 1975 which is the date at which I find
that the cause of action accrued."
Sullivan
v Layton Lougher & Co
[1995] 49 EG 127 was another Limitation Act case concerning an eight year delay
between purchase and writ. The negligence there was that of the
plaintiff’s solicitor in failing to advise him that the lease in
question, having already been extended under the Leasehold Reform Act 1967,
could not be further extended. Leggatt LJ said that:
"...
time ran from completion and not from any subsequent date, with the result that
it had run in favour of the defendants by the time the writ was issued."
In
none of these three cases did any issue arise requiring the court to determine,
as between exchange and completion, the date at which the cause of action
accrued.
I
come finally to two decisions of the House of Lords which, it is suggested,
contain important conflicting dicta on the point. First,
Smith
v Bush
[1990] AC 831 where, at page 852, Lord Templeman said this:
"Mr
Hague [counsel for the surveyors] also submitted that there was no contract
between a valuer and a purchaser and that, so far as the purchaser was
concerned, the valuation was ´gratuitous,’ and the valuer should not
be forced to accept a liability he was unwilling to undertake. My Lords, all
these submissions are, in my view, inconsistent with the ambit and thrust of
the Act of 1977. The valuer is a professional man who offers his services for
reward. He is paid for those services. The valuer knows that 90 per cent.
of purchasers in fact rely on a mortgage valuation and do not commission their
own survey. There is great pressure on a purchaser to rely on the mortgage
valuation. Many purchasers cannot afford a second valuation. If the
purchaser obtains a second valuation the sale may go off and then both
valuation fees will be wasted. Moreover, he knows that mortgagees, such as
building societies and the council, in the present case, are trustworthy and
that they appoint careful and competent valuers and he trusts the professional
man so appointed. Finally, the valuer knows full well that failure on his
part to exercise reasonable skill and care may be disastrous to the purchaser.
If, in reliance on a valuation, the purchaser contracts to buy for £50,000
a house valued and mortgaged for £40,000 but, in fact worth nothing and
needing thousands more to be spent on it, the purchaser stands to lose his home
and to remain in debt to the building society for up to £40,000."
Smith
v Bush
,
of course, is the very case which established the potential liability in tort
of the mortgagees’ valuers to the purchaser - the foundation of the
plaintiffs’ claim in the present action - and, submits Mr Parsons for the
defendants, Lord Templeman can be seen pointing to exchange rather than
completion as the stage when the cause of action arises. Not so, argues Mr
McCormick: Lord Templeman was there using the term “contracts to
buy” as an omnibus expression encompassing either exchange or completion;
it mattered not which it was: what mattered was that a duty of care should be
held to exist because of the purchaser’s likely reliance on the
mortgagees’ valuation. I accept Mr McCormick’s submission:
essentially the case was concerned with the duty of care rather than damage;
certainly it was not directed to the question of when, as between exchange and
completion, damage is first sustained.
The
second House of Lords decision is the authority upon which Mr McCormick
principally relies,
Nykredit
Plc v Edward Erdman Ltd
[1997] 1 WLR 1627, and in particular the following passage from Lord
Nicholls’ speech at page 1630:
"Accrual
of a cause of action: actual damage
As
every law student knows, causes of action for breach of contract and in tort
arise at different times. In cases of breach of contract the cause of action
arises at the date of the breach of contract. In cases in tort the cause of
action arises, not when the culpable conduct occurs, but when the plaintiff
first sustains damage. Thus the question which has to be addressed is what is
meant by ´damage’ in the context of claims for loss which is purely
financial (or economic, as it is sometimes described).
In
Forster
v Outred & Co.
[1982] 1 WLR 86, 94, Stephenson LJ recorded the submission of Mr Stuart-Smith QC:
´What
is meant by actual damage? Mr Stuart-Smith says that it is any detriment,
liability or loss capable of assessment in money terms and it includes
liabilities which may arise on a contingency, particularly a contingency over
which the plaintiff has no control; things like loss of earning capacity, loss
of a chance or bargain, loss of profit, losses incurred from onerous provisions
or covenants in leases. They are all illustrations of a kind of loss which is
meant by ´actual’ damage. It was also suggested in argument ...
that ´actual’ is really used in contrast to ´presumed’ or
´assumed.’ Whereas damage is presumed in trespass and libel, it is
not presumed in negligence and has to be proved. There has to be some actual
damage.’
Stephenson
LJ, at p.98, accepted this submission. I agree with him. I add only the
cautionary reminder that the loss must be relevant loss. To constitute actual
damage for the purpose of constituting a tort, the loss sustained must be loss
falling within the measure of damage applicable to the wrong in question.
Take
first a simple case which gives rise to no difficulty. A purchaser buys a
house which has been negligently overvalued or which is subject to a local land
charge not noticed by the purchaser’s solicitor. Had he known the true
position the purchaser would not have bought. In such a case the
purchaser’s cause of action in tort accrues when he completes the
purchase. He suffers actual damage by parting with his money and receiving in
exchange property worth less than the price he paid.
In
the ordinary way the purchaser in this example will not know of the negligence
of his valuer or solicitor when completing the purchase. Despite this his
cause of action arises at the date of completion and time begins to run for
limitation purposes."
There,
submits Mr McCormick, Lord Nicholls is in terms addressing the question as to
when damage is first sustained by a purchaser so that his cause of action in
tort accrues against the negligent valuer, and his answer is “when he
completes the purchase”, which is when he “suffers actual damage by
parting with his money”.
This
to my mind is undoubtedly the high-water mark of the appellants’
argument. Completion rather than exchange is the concept three times
referred to by Lord Nicholls at the conclusion of that passage.
In
my judgment, however, the argument fails. For the purposes of Lord
Nicholls’ illustration in
Nykredit
it mattered not, any more than in all the other cases cited, whether time ran
from completion or exchange. The issue in
Nykredit
was when the plaintiff bank’s cause of action had arisen, and the
decision was that it arose when a relevant and measurable loss had first been
revealed. There, since the borrower had defaulted at once and the amount lent
had at all times exceeded the value of the property, that had been at or about
the time of the loan transaction. The critical point to note, however, is
that the action there was by a lender complaining that in reliance on the
defendant’s negligence he had made a bad loan, whereas the present action
is by a purchaser the essence of whose complaint is that he bought a bad
property. Because it is altogether less certain whether and when loss will be
suffered by badly-advised lenders than in the case of badly-advised purchasers,
the cases are treated differently. The contrast was, indeed, struck by Lord
Nicholls himself shortly after the passage above quoted:
"More
difficult is the case, where, as a result of negligent advice, property is
acquired as security. In one sense the lender undoubtedly suffers detriment
when the loan transaction is completed. He parts with his money, which he
would not have done had he been properly advised. In another sense he may
suffer no loss at that stage because often there will be no certainty he will
actually lose any of his money: the borrower may not default. Financial loss
is possible, but not certain. Indeed, it may not even be likely. Further,
in some cases, and depending on the facts, even if the borrower does default
the overvalued security may still be sufficient."
This
is also the answer to such submissions as Mr McCormick makes in reliance upon
passages in the judgments of the Court of Appeal in
UBAF
Limited v European American Banking Corporation
[1984] QB 713 and
First
National Bank Plc v Humberts
[1995] 2 All ER 673. Both of those were lending cases and both, indeed, were
discussed as such in
Nykredit.
Let
me return to Lord Nicholls’ illustration of the house purchaser. The
central point which I apprehend was there being made is that the purchaser is
on any view damaged by purchasing in reliance upon a negligent over-valuation.
But for that he “would not have bought.” No more would he have
exchanged contracts to buy. “He suffers actual damage by parting with
his money and receiving in exchange property worth less than the price he
paid.” But I can see no distinction in principle between “parting
with his money and receiving in exchange property” at completion and, as
will generally occur on exchange, paying a deposit and becoming committed to
pay the balance on completion. True, it is not until completion that the
purchaser receives the property in the sense of the legal estate in the
property. On exchange, however, he obtains a very real interest in the
property and, for example, must insure it.
In
the last analysis
Nykredit
to my mind assists the defendants’ argument rather than the
plaintiffs’. Lord Nicholls, like Stephenson LJ in
Forster
v Outred
,
accepted Mr Stuart-Smith’s formulation of the meaning of actual damage.
One looks, therefore, for “any detriment, liability or loss”
including “liabilities which may arise on a contingency” and
“losses incurred from onerous provisions or covenants in leases”
subject only to the loss being “a relevant loss” i.e. one
“falling within the measure of damage applicable to the wrong in
question.” Here, I repeat, the plaintiffs on exchange became
irrevocably committed to acquiring the lease, a lease worth less than they
reasonably believed, and one which they would not have committed themselves to
acquire but for the defendants’ negligent report. That, as it seems to
me, plainly resulted in “actual (as opposed to potential or prospective)
loss or damage of a kind recognised by the law”, as Saville LJ expressed
it in
First
National Commercial Bank Plc v Humberts
at page 676.
In
my judgment it is no answer to this to say that not every exchange results in
completion so that the plaintiffs might perhaps in the event have escaped from
their commitment without loss. The fact is that they did not do so and there
was no reason to suppose that they would. Nor does it seem to me any answer
to say that property prices could have increased between exchange and
completion sufficiently to outweigh the depreciating effect of the unrevealed
defects. Mr McCormick submits that the loss crystallises only at completion
and it is the market value of the property at that date that one must compare
with the price paid. I see no good reason why. By the same token that he
would ignore any movement in the property market after completion, I would
ignore it after exchange. The valuation in the report will necessarily relate
more closely to that of the property at exchange than at completion; by
exchange the purchase price will be fixed and agreed; and by his commitment to
the transaction at exchange the purchaser will effectively have locked himself
into the property market at that point.
In
advancing this appeal Mr McCormick took the Court to a great range of further
authorities dealing with speculative damage, physical damage, recurrent damage,
and many other aspects of damage. Suffice it to say that none of them to my
mind provide the least help in resolving the point presently at issue. This
is a case of tortiously induced economic loss. For the reasons given, which
in substance are the same as those given by the judge below, I too would hold
that the cause of action in these cases accrues when contracts are exchanged.
I would accordingly dismiss this appeal.
LORD
JUSTICE OTTON:
A
tort is only actionable on proof of damage; there is no cause of action, and
time does not begin to run for limitation purposes until some damage actually
occurs. Thus in cases of negligence time runs from the date of damage, not
from the negligent act or omission. However, the cause of action
‘accrues’ when the damage occurs not when it is discovered by the
plaintiff. In
Cartledge
v E Jopling & Sons Ltd
[1963] AC 758 the plaintiff was exposed over a number of years to noxious dust
caused by breach of statutory duty and as a result contracted pneumoconiosis.
The plaintiff could not prove that a breach had occurred during the 6 years
(the then limitation period) preceding his writ. Although the disease had not
revealed itself until later the plaintiff had in fact suffered actionable
injury to his lungs
within
the 6 year period. The House of Lords held that his claim was statute-barred.
Until
1983 the Courts proceeded on the basis that economic loss occurred at (and the
limitation period began to run from) the date when the damage was reasonably
discoverable (see
Sparham-Souter
v Town Developments
[1976] QB 858 C.A.) However, in
Pirelli
General Cable Works Ltd v Faber & Ptners
[1983] 2AC 1 the House of Lords held that a cause of action in tort for
negligent advice given by an engineer in relation to the design of the chimney
accrued (and the limitation period began) when the damage occurred (i.e. when
there were cracks in the chimney) - rather than when the damage was reasonably
discoverable. Thus the action became time barred even though the plaintiff
owner neither knew of the cracks nor could reasonably have been expected to
discover them within the 6 year period.
Their
Lordships recognised that its rejection of the discoverability test for when
time started to run could cause injustice to plaintiffs who could be deprived
of their cause of action before they knew of its existence.
They
were not prepared to overrule
Cartledge
& Jopling.
They indicated that this unsatisfactory situation could only be remedied by
statute so as to remove the injustice of plaintiffs being statute-barred before
they had the means of knowing of their causes of action for personal injury,
death or other negligently-caused damage such as economic loss. They called
for a legislative solution.
Section
1 and 2 of the Latent Damage Act 1986 amended the Limitation Act 1980 so that
by s 14A(1) of the 1980 Act the limitation period for negligent latent damage
(other than for personal injury) was made more favourable to plaintiffs by
extending it to either 6 years from when the cause of action
“accrues” or 3 years from the date of the plaintiff’s
“knowledge” whichever is the longer (with an absolute long-stop of
15 years from the defendant’s breach of duty). Unlike the regime for
personal injury and death there is no discretion to disapply any of these time
limits.
This
reform was not confined to defectively designed or constructed buildings.
Latent pure economic loss caused by the negligent advice of a solicitor falls
within its provisions (see
Forster
v Outred & Co
[1982] 1 WLR 86).
In
the instant case the plaintiffs could not avail themselves of the
“knowledge” protection. To bring themselves within s 14A (b) they
had to show that they did not have “the knowledge required for bringing
an action for damages in respect of the relevant damage” until, at the
earliest, 19 July 1991 (3 years prior to the date of issue of the writ). From
their own evidence they were well aware of serious defects in the flat well
before July 1991; they began to suffer problems with damp and water penetration
from the winter of 1988 onwards.
Thus
the critical question arose as to when their cause of action arose. There can
be little doubt that the negligent act or omission occurred on the occasion of
the inspection on 2 June 1988. The plaintiffs were informed of the valuation
shortly afterwards. The communication of the valuation to the plaintiffs still
did not amount to a tort. Their cause of action arose when they acted on it
and thereby suffered damage. This occurred, in my judgment, when they signed
and then exchanged contracts. For all intents and purposes they were
irrevocably bound to complete the purchase whenever that event took place,
whether immediately after exchange or at the date agreed between them. From
the moment that they exchanged the plaintiffs acquired an interest in the
property (it matters not for the purposes of this case whether this was
technically an equitable rather than a legal interest). They acquired an
immediate and binding obligation to insure the property.
None
of the remote events which might have led to rescission of the contract of
sale, or completion not to take place, occurred. Thus completion was only a
formality. Both the seller and the plaintiffs could have held the other to the
deal and enforced their rights by a suit for specific performance. On exchange
they acquired a lease which was worth less than they were led to believe by the
report and upon the strength of which they agreed to purchase.
I
can find no inconsistency between this approach and the previous decisions
where lenders have sued in negligence for negligent valuation. Applying the
principles set out above the tort is not complete until the lender suffers
damage. This can occur (for example) when the borrower defaults. Until then
the lender had not suffered any “actual (as opposed to potential loss or
damage of a kind recognised by the law” per Saville LJ in
FNCB
plc v Humberts
[1995] 2 AER 673 (at p.676).
Accordingly
I too would dismiss the appeal.
LORD
JUSTICE SCHIEMANN: I agree with both judgments.
Order: Appeal
dismissed with costs; application for
leave
to appeal in the House of Lords refused.