JUDGMENT OF THE COURT (Second Chamber)
2 December 2004 (1)
(Appeal - Fisheries - Community financial aid - Reduction of the aid - Council Regulation (EC, Euratom) No 2988/95 - Articles 1 and 3 - Limitation period)
In Case C-226/03 P,APPEAL under Article 56 of the Statute of the Court of Justice, brought on 22 May 2003, José Martí Peix SA, established in Huelva (Spain), represented by J.R. García-Gallardo Gil-Fournier and D. Domínguez Pérez, avocats,applicant,
the other party to the proceedings being:Commission of the European Communities, represented by S. Pardo Quintillán, acting as Agent, and J. Guerra Fernández, avocat, with an address for service in Luxembourg,THE COURT (Second Chamber),
after hearing the Opinion of the Advocate General at the sitting on 7 September 2004,
gives the following
-Throughout the period for which aid is granted by the Community, the authority or agency appointed for the purpose by the Member State shall send to the Commission on request all supporting documents and all documents showing that the financial or other conditions imposed for each project are satisfied. The Commission may decide to suspend, reduce or discontinue aid, in accordance with the procedure laid down in Article 47: - if the project is not carried out as specified, or - if certain conditions imposed are not satisfied, or - if the beneficiary, contrary to the particulars given in his application and incorporated in the decision granting aid, has not begun the work within one year from the date of notification of the decision, or has not, before the end of this period, supplied satisfactory assurances that the project will be carried out, or - if the beneficiary does not complete the work within a period of two years from the start of the project, except in cases of force majeure. Decisions shall be notified to the Member State concerned and to the beneficiary.The Commission shall take steps to recover any sums unduly paid.-
-Article 1 1. For the purposes of protecting the European Communities- financial interests, general rules are hereby adopted relating to homogenous checks and to administrative measures and penalties concerning irregularities with regard to Community law.2. -Irregularity- shall mean any infringement of a provision of Community law resulting from an act or omission by an economic operator, which has, or would have, the effect of prejudicing the general budget of the Communities or budgets managed by them, either by reducing or losing revenue accruing from own resources collected directly on behalf of the Communities, or by an unjustified item of expenditure.-Article 31. The limitation period for proceedings shall be four years as from the time when the irregularity referred to in Article 1(1) was committed. However, the sectoral rules may make provision for a shorter period which may not be less than three years.In the case of continuous or repeated irregularities, the limitation period shall run from the day on which the irregularity ceases. In the case of multiannual programmes, the limitation period shall in any case run until the programme is definitively terminated.The limitation period shall be interrupted by any act of the competent authority, notified to the person in question, relating to investigation or legal proceedings concerning the irregularity. The limitation period shall start again following each interrupting act.However, limitation shall become effective at the latest on the day on which a period equal to twice the limitation period expires without the competent authority having imposed a penalty, except where the administrative procedure has been suspended in accordance with Article 6(1).-
-11 In October 1991 the company José Martí Peix SA (hereinafter -the applicant-) submitted to the Commission, through the Spanish authorities, an application for Community financial aid under Regulation No 4028/86, for a project to create a joint Spanish-Angolan fisheries enterprise. That project provided for the transfer, with a view to fishing activities, of three vessels - the Pondal, the Periloja and the Sonia Rosal - to the joint enterprise created by the applicant, the Portuguese company Iberpesca - Sociedades de Pesca Ltda and an Angolan partner, Empromar N-Gunza. 12 By decision of 16 December 1991 (hereinafter -the aid decision-) the Commission granted the project referred to in the preceding paragraph (project SM/ESP/17/91, hereinafter -the project-) Community aid for a maximum amount of ECU 1 349 550. That decision provided that the Kingdom of Spain would supplement the Community aid by an aid payment of ECU 269 910. 13 In November 1992 the joint enterprise, named Ibermar Empresa de Pesca Ltda, was created and registered in Luanda, Angola. In December 1992 the three vessels of the joint enterprise were registered at the port of Luanda. 14 By decision of 12 May 1993, in response to an application by the applicant, the Commission adopted a decision amending the decision to grant assistance. The amendment took the form of replacing the third country partner, Empromar N-Gunza, by the company Marang, Pesca and Industrias de Pesca Ltda. 15 On 18 May 1993 the Commission received via the Spanish authorities an application for payment of the first instalment of the aid, dated 10 May 1993. That application was accompanied by a set of documents and certificates relating to the creation of the joint enterprise, the registration of the vessels at the port of Luanda, their removal from the Community register and the obtaining of the required fishing licences. 16 On 24 June 1993 the Commission paid 80% of the aid. 17 On 20 May 1994 the applicant sent the Spanish authorities an application for payment of the balance of the aid. It attached to that application a first periodic progress report on activity, for the period from 20 April 1993 to 20 April 1994. That report stated, inter alia: -Our long-term objectives have had to be modified owing to the sinking of the Pondal on 20 July 1993. We immediately asked the Angolan authorities responsible for fisheries to replace it by another vessel of our fleet, but at the time of drafting this report we have not yet obtained the authorisation for that substitution ...-. 18 The Commission received the application referred to in paragraph 17 on 7 September 1994 and paid the balance of the aid on 14 September 1994. 19 On 6 November 1995 the Commission received the second periodic progress report, dated 19 June 1995, for the activity period from 20 May 1994 to 20 May 1995. That report referred to the sinking of the Pondal on 20 July 1993 and described the difficulties encountered in replacing that vessel, owing to the reluctance of the Angolan authorities. 20 By letter of 20 December 1996 the Commission, since it had not received the third periodic progress report, requested information on that subject from the Spanish authorities, which replied by letter of 22 January 1997 that the report was being drafted. 21 On 20 February 1997 the Spanish authorities received a letter from the applicant, dated 31 January 1997, in which it described the management difficulties experienced by the joint enterprise, caused by the demands made by the Angolan partner and, on the basis of those difficulties, sought a change in third country for the vessels Periloja and Sonia Rosal. In that letter, the applicant notified the transfer of those two vessels to the joint enterprise Peix Camerún SARL and applied for authorisation to present the third periodic progress report on activity in the context of the latter enterprise. 22 By letter of 4 February 1997 received by the Commission on 5 March 1997, the Spanish authorities forwarded the requests made by the applicant, with the relevant documentation, and declared themselves in favour of those requests. 23 On 4 April 1997 the Commission replied to the Spanish authorities that the third periodic activity report should have been submitted in September 1996 and that, consequently, that report must be presented following on from the preceding reports and not in the new perspective proposed by the applicant. 24 By letter of 18 June 1997 the Commission asked the Spanish authorities to send the third periodic activity report as soon as possible. 25 In September 1997 the third periodic activity report, covering the period from 20 May 1995 to 20 May 1996, was received by the Commission. In it mention was made of the conduct of the Angolan partner which prevented the pursuit of normal fishing activities. It was stated that the most recent landings of fish from Angola took place in March 1995 and that, in the light of the difficulties arising from that conduct, the Community partners had decided to sell their shares in the joint enterprise to the Angolan partner and to repurchase the vessels which had been transferred to the project. The report mentioned that, after their repurchase, the vessels had been transferred by the applicant to a Nigerian port, where they had undergone repairs until 1996. 26 By letter of 6 March 1998 the applicant, in reply to a request by the Spanish authorities on 26 February 1998, provided the latter with clarifications as regards the implementation of the project. That letter stated that the joint enterprise-s vessels had left Angolan waters during the first quarter of 1995. The documents annexed to that letter showed that the Community shipowners sold their shares in the joint enterprise to the Angolan partner on 3 February 1995. 27 By letter of 26 June 1998 the Commission asked the Spanish authorities to provide information concerning the state of the project. In reply to that letter, on 2 July 1998 those authorities sent the Commission the applicant-s letter of 6 March 1998. Pre-litigation procedure 28 In a letter of 26 July 1999 addressed to the applicant and to the Spanish authorities, Mr Cavaco, Director-General of the Fisheries Directorate of the Commission (DG XIV), announced that, in accordance with Article 44(1) of Regulation No 4028/86, the Commission had decided to reduce the aid initially granted to the project on the ground that, in contrast to the requirements laid down in that regulation and by Regulation No 1956/91, the joint enterprise had not exploited for three years the fisheries resources of the third country mentioned in the decision to grant assistance. As regards the vessel Pondal, that letter stated that it was possible to deduce from the documents received by the Commission that the vessel had been exercising its activities from 20 April to 20 July 1993 - that is, for three months - when it sank, which justified a reduction in aid of ECU 160 417. Nevertheless, it added that the Commission-s calculation was subject to obtaining information establishing that that sinking constituted a case of force majeure. As regards the Periloja and Sonia Rosal, it stated that the information available to the Commission showed that those two vessels had exercised their activities in Angolan waters on behalf of the joint enterprise from 20 April 1993 to 20 April 1994 and from 20 May 1994 to 3 February 1995, the date the applicant sold its shares in the joint enterprise, namely for a total period of 21 months, which justified a reduction in the aid of ECU 114 520. In total, the planned reduction therefore amounted to ECU 274 937, the reimbursement of which the Commission intended to claim from the applicant, which had been paid the whole of the aid beforehand. The letter stated that, failing formal agreement to the proposed solution by the applicant within 30 days, the Commission would continue with the procedure for reducing the aid. 29 On 5 October 1999 the applicant sent the Commission its comments on the latter-s letter of 26 July 1999. In essence, it provided information seeking to establish that the sinking of the Pondal was a case of force majeure and stated that it had tried to replace it by another vessel of its fleet but had not been able to do so because of the conduct of the Angolan authorities. As regards the Periloja and Sonia Rosal, it explained that the difficulties caused by the Angolan partner had obliged it to transfer the activity of those vessels to Cameroonian waters. It pointed out that this change had been notified to the Spanish authorities in January 1997. It stressed that the formal requirements for creating and operating the joint enterprise had been satisfied and that its activities had envisaged supplying the Community market by priority. 30 On 9 November 1999 a meeting took place between the Commission and the applicant. 31 Following that meeting, the applicant sent the Commission a statement of observations on 18 February 2000 in which it pleaded that the facts complained of by the Commission were time-barred and that the Commission had acted in breach of the principles of due care and of good administration. 32 By letter of 25 May 2000 addressed to the applicant and to the Spanish authorities, Mr Smidt, Director-General of the Fisheries Directorate of the Commission, stated that a reading of the documents provided by the applicant on 5 October 1999 had indicated that the sinking of the Pondal occurred on 13 January 1993, and not on 20 July 1993 as the applicant had informed the Commission, and that in those circumstances the absence of any reference to that sinking in the application for payment of the first instalment of the aid presented by the applicant in May 1993 and the statement in the first and second periodic reports on the activities of the joint enterprise that the sinking took place on 20 July 1993 constituted irregularities of such a kind as to warrant discontinuing the part of the aid relating to the vessel in question. Since that part of the aid amounted to ECU 525 000 and the Commission confirmed its position as set out on 26 July 1999 as regards the two other vessels belonging to the joint enterprise, that letter proposed to take the total amount of the reduction of the aid to ECU 639 520. The letter also set out the Commission-s objections as regards the applicant-s claims concerning the time-bar on the proposed measures of reduction and recovery. It stated that if the applicant had not, within 30 days, notified its agreement to the proposed solution or provided information likely to warrant a change in the Commission-s position, the Commission would continue the reduction and recovery procedures. 33 On 10 July 2000, the applicant sent the Commission its observations on the latter-s letter of 25 May 2000. In essence, it stated that the Pondal sank on 13 January 1993 but that it was not removed from the Angolan register until 20 July 1993, which explained why the sinking was not mentioned in the application for payment of the first instalment of the aid and the reference to the latter date in the first periodic report on activity. As regards the two other vessels, it maintained that it was established that it had notified the change of third country to the Spanish authorities in January 1997. It also claimed it had acted in good faith in the matter. 34 On 19 March 2001 the Commission adopted a decision reducing the aid granted to the project to EUR 710 030 and ordering the applicant to reimburse it the amount of EUR 639 520 --.
-81 First, as regards the sinking of the Pondal, it should be observed that the irregularity established, correctly, in the contested decision consists in the fact that the applicant at first concealed that sinking and subsequently communicated an incorrect date for it. The actions for which the applicant is criticised in relation to the sinking of the Pondal must be considered to constitute a continuous irregularity within the meaning of the second subparagraph of Article 3(1) of Regulation No 2988/95, in that they were identical in substance - that is, an infringement by the applicant of its duty to provide information and act in good faith as regards that sinking. It must therefore be held, in accordance with that same provision, that as regards the irregularity concerning the Pondal, the limitation period began to run -from the day on which the irregularity ceases-. 82 In that regard, although, admittedly, the applicant indicated the occurrence of the sinking of the Pondal in the first periodic report on the activity of the joint enterprise, sent to the Spanish authorities on 20 May 1994, it admitted at the hearing that it was only in its document of 5 October 1999, which contained its comments on the Commission-s letter of 26 July 1999, that it first informed the Commission of the exact date of that sinking, namely 13 January 1993, and not 20 July 1993 as it had stated until then. In those circumstances, it must be held that the irregularity linked to the applicant-s breach of its duty to provide information and to act in good faith as regards the sinking of the Pondal ended on 5 October 1999. The applicant cannot in those circumstances rely on the limitation period as regards the facts found in the contested decision concerning that vessel. - 91 The alleged facts as regards the Periloja and Sonia Rosal must be considered to constitute a continuous irregularity within the meaning of the second subparagraph of Article 3(1) of Regulation No 2988/95, since they continued until 20 May 1996, the date which, according to the third periodic report on the activity of the joint enterprise, marks the end of the compulsory triennial period of activity for that enterprise and on which the irregularity definitively took the form claimed in the contested decision, namely the failure by those two vessels to engage in activities in Angolan waters for 15 of the 36 months making up the abovementioned period. In those circumstances, the limitation period of four years must, in accordance with the same provision of Regulation No 2988/95, be considered as having run -from the day on which the irregularity ceases- - in this case, 20 May 1996. 92 By virtue of the third subparagraph of Article 3(1) of Regulation No 2988/95 the limitation period is interrupted by any act of the competent authority notified to the person in question, relating to investigation or legal proceedings concerning the irregularity. 93 In the present case, on 26 July 1999 the Commission sent the applicant a letter informing it of the commencement of a reduction procedure linked to irregularities concerning, inter alia, the activity of the vessels Periloja and Sonia Rosal. It is clear from Article 44(1) of Regulation No 4028/86 (-) that the Commission is the competent authority, within the meaning of the provision referred to in the preceding paragraph, to reduce the aid granted on the basis of that regulation. Moreover, the letter of 26 July 1999 must, as the applicant itself states (-), be considered to refer to proceedings concerning the abovementioned irregularities. In those circumstances, it must be considered as an act interrupting the limitation period within the meaning of the third subparagraph of Article 3(1) of Regulation No 2988/95. 94 Accordingly, even if, on the basis of a literal reading of the first subparagraph of Article 3(1) of Regulation No 2988/95, the limitation period of four years laid down in that provision is considered to run, in respect of a continuous irregularity, from the day on which that irregularity ceased even when the competent authority does not learn of that irregularity until later, as in the present case, the sending of the letter of 26 July 1999, which took place before the expiry of the period of four years, which began on 20 May 1996, interrupted that period and caused a new period of four years to run as from 26 July 1999. It follows that, at the time when the contested decision was adopted, the facts constituting the irregularity as regards the Periloja and Sonia Rosal were not time-barred. 95 In the light of the foregoing considerations, the plea relating to the limitation period must be rejected.-
- declare this appeal admissible; - annul the judgment under appeal; - order the Commission to pay the totality of the costs incurred before both the Court and the Court of First Instance.
- dismiss the appeal in part as manifestly inadmissible or, in the alternative, as unfounded; - for the remainder dismiss the appeal as unfounded; - in the alternative, if the appeal plea raised by the appellant were to be upheld hold the allegations in the fifth part of the Commission-s pleading to be substantiated (non-applicability of Article 3 of Regulation No 2988/95 to the irregularities in this case) and dismiss the action for annulment as unfounded; - order the applicant to pay the costs of both proceedings.
The second limb of the single plea: the vessels Sonia Rosal and Periloja
The first limb of the single plea: the vessel Pondal
The second allegation
The first allegation