JUDGMENT OF THE COURT (Sixth Chamber)
19 June 2003 (1)
(Public contracts - Directive 89/665/EEC - Review procedures concerning the award of public contracts - Article 1(3) - Persons to whom review procedures must be available - Definition of interest in obtaining a public contract)
In Case C-410/01,
REFERENCE to the Court under Article 234 EC by the Bundesvergabeamt (Austria) for a preliminary ruling in the proceedings pending before that court between
Fritsch, Chiari & Partner, Ziviltechniker GmbH and Others
and
Autobahnen- und Schnellstraßen-Finanzierungs-AG (Asfinag),
on the interpretation of Article 1(3) of Council Directive 89/665/EEC of 21 December 1989 on the coordination of the laws, regulations and administrative provisions relating to the application of review procedures to the award of public supply and public works contracts (OJ 1989 L 395, p. 33), as amended by Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts (OJ 1992 L 209, p. 1),
THE COURT (Sixth Chamber),
composed of: J.-P. Puissochet, President of the Chamber, R. Schintgen (Rapporteur), V. Skouris, F. Macken and J.N. Cunha Rodrigues, Judges,
Advocate General: J. Mischo,
Registrar: M.-F. Contet, Principal Administrator,
after considering the written observations submitted on behalf of:
- the Austrian Government, by M. Fruhmann, acting as Agent,
- the French Government, by G. de Bergues and A. Bréville-Viéville, acting as Agents,
- the Commission of the European Communities, by M. Nolin, acting as Agent, assisted by R. Roniger, Rechtsanwalt,
having regard to the Report for the Hearing,
after hearing the oral observations of Fritsch, Chiari & Partner, Ziviltechniker GmbH and Others, represented by S. Wurst, Rechtsanwalt, the Austrian Government, represented by M. Fruhmann, the French Government, represented by S. Pailler, acting as Agent, and the Commission, represented by M. Nolin, assisted by R. Roniger, at the hearing on 16 January 2003,
after hearing the Opinion of the Advocate General at the sitting on 25 February 2003,
gives the following
Legal context
Community provisions
1. The Member States shall take the measures necessary to ensure that, as regards contract award procedures falling within the scope of Directives 71/305/EEC, 77/62/EEC and 92/50/EEC, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the provisions set out in the following articles and, in particular, Article 2(7), on the grounds that such decisions have infringed Community law in the field of public procurement or national rules implementing that law.
...
3. The Member States shall ensure that the review procedures are available, under detailed rules which the Member States may establish, at least to any person having or having had an interest in obtaining a particular public supply or public works contract and who has been or risks being harmed by an alleged infringement. In particular, the Member States may require that the person seeking the review must have previously notified the contracting authority of the alleged infringement and of his intention to seek review.
1. The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers to:
(a) take, at the earliest opportunity and by way of interlocutory procedures, interim measures with the aim of correcting the alleged infringement or preventing further damage to the interests concerned, including measures to suspend or to ensure the suspension of the procedure for the award of a public contract or the implementation of any decision taken by the contracting authority;
(b) either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure;
(c) award damages to persons harmed by an infringement.
...
6. The effects of the exercise of the powers referred to in paragraph 1 on a contract concluded subsequent to its award shall be determined by national law.
Furthermore, except where a decision must be set aside prior to the award of damages, a Member State may provide that, after the conclusion of a contract following its award, the powers of the body responsible for the review procedures shall be limited to awarding damages to any person harmed by an infringement.
National legislation
1. The B-VKK shall be competent:
(1) until such time as the contract is awarded, to reconcile any differences of opinion between the awarding body and one or more candidates or tenderers concerning the application of the present federal law or its implementing regulations.
...
6. A request for the B-VKK to take action made under paragraph 1(1) must be submitted to the directors of the Commission as soon as possible after the difference of opinion comes to light.
7. If the B-VKK does not take action following a request from the awarding body, it must inform that body immediately it does take action.
8. The awarding body may not award the contract until four weeks after ... it has been informed in accordance with paragraph 7, failing which the tendering procedure shall be declared void. ...
1. The Bundesvergabeamt is responsible on application for carrying out a review procedure in accordance with the following provisions.
2. To preclude infringements of this Federal Law and of the regulations implementing it, the Bundesvergabeamt is authorised until the time of the award:
(1) to adopt interim measures and
(2) to set aside unlawful decisions of the contracting authority.
3. After the award of the contract or the close of the contract award procedure, the Bundesvergabeamt is competent to determine whether, on grounds of infringement of this Federal Law or of any regulations issued under it, the contract has not been awarded to the best tenderer. ...
Where an undertaking claims to have an interest in the conclusion of a contract within the scope of this Federal Law, it may apply for the contracting authority's decision in the contract award procedure to be reviewed on the ground of unlawfulness, provided that it has been or risks being harmed by the alleged infringement.
The main proceedings and the questions referred for a preliminary ruling
1. Is Article 1(3) of Directive 89/665 ... to be interpreted as meaning that the review procedure must be available to any undertaking which has submitted a bid, or applied to participate, in a public procurement procedure?
2. In the event that the answer to Question 1 is no:
Is the abovementioned provision to be understood as meaning that an undertaking only has or had an interest in a particular public contract if, in addition to its participating in the public procurement procedure, it takes or took all steps available to it under national law to prevent the contract from being awarded to another bidder and so to secure the award of the contract to itself?
The jurisdiction of the Court
The questions referred
Costs
36. The costs incurred by the Austrian and French Governments and by the Commission, which have submitted observations to the Court, are not recoverable. Since these proceedings are, for the parties to the main proceedings, a step in the proceedings pending before the national court, the decision on costs is a matter for that court.
On those grounds,
THE COURT (Sixth Chamber),
in answer to the questions referred to it by the Bundesvergabeamt by order of 8 October 2001, hereby rules:
Article 1(3) of Directive 89/665/EEC of 21 December 1989 on the coordination of the laws, regulations and administrative provisions relating to the application of review procedures to the award of public supply and public works contracts, as amended by Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts, precludes an undertaking which has participated in a public procurement procedure from being considered as having lost its interest in obtaining that contract on the ground that, before bringing a review procedure under that directive, it failed to apply to a conciliation commission, such as the Bundes-Vergabekontrollkommission established by the Bundesgesetz über die Vergabe von Aufträgen (Bundesvergabegesetz) 1997 (1997 Austrian Federal Law on Public Procurement).
Puissochet Schintgen Skouris
Macken Cunha Rodrigues
|
Delivered in open court in Luxembourg on 19 June 2003.
R. Grass J.-P. Puissochet
Registrar President of the Sixth Chamber
1: Language of the case: German.