JUDGMENT OF THE COURT
24 September 2002 (1)
I - Legal framework and factual background I - 4
A - Legal framework I - 4
B - Factual background I - 6
II - Procedure, forms of order sought and pleas in law raised before the Court of First Instance and the contested judgment I - 10
A - Procedure before the Court of First Instance I - 10
B - Forms of order sought and pleas in law raised before the Court of First Instance and the contested judgment I - 11
III - The appeals I - 14
A - Admissibility of the appeal brought by Falck I - 14
Arguments of the parties I - 14
Findings of the Court I - 15
B - The request that certain documents produced by ACB and Falck be removed from the case-file I - 16
Arguments of the parties I - 17
Findings of the Court I - 17
C - The substance of the appeals I - 17
1. The ground of appeal alleging a procedural irregularity adversely affecting the appellants' interests I - 18
Arguments of the parties I - 18
Findings of the Court I - 18
2. Breach of the rights of the defence by the Commission during the administrative procedure I - 19
Arguments of the parties I - 19
Findings of the Court I - 21
3. Classification and assessment of the measures at issue I - 23
(a) Effect of the aid at issue on intra-Community trade and competition I - 23
Arguments of the parties I - 23
Findings of the Court I - 24
(b) The applicable Steel Aid Code I - 26
Arguments of the parties I - 26
Findings of the Court I - 28
(c) The Commission's obligations as regards information to be obtained before determining the compatibility of aid I - 29
4. The Commission's decision requiring repayment of part of the aid paid to ACB and the manner of such repayment I - 30
(a) Observance of the principles of protection of legitimate expectations, good faith and sincere cooperation I - 30
Arguments of the parties I - 30
Findings of the Court I - 30
(b) The Commission's delay in taking action I - 31
Arguments of the parties I - 31
Findings of the Court I - 33
(c) Bases for calculating the interest to be applied I - 34
Arguments of the parties I - 34
Findings of the Court I - 36
(d) Application of a penalty and breach of the principle of proportionality I - 39
(i) The complaint that changes in the situation transformed the requirement to repay into a penalty I - 39
Arguments of the parties I - 40
Findings of the Court I - 40
(ii) The complaint that the lack of a genuine examination of the compatibility of the aid transforms the requirement to repay into a penalty I - 41
Arguments of the parties I - 41
Findings of the Court I - 42
(iii) The complaint that errors and confusion over the various aids and the amounts to be repaid transformed the requirement to repay into a penalty I - 42
(iv) The complaint that the application of an excessive rate of interest for the repayment of the aid transformed the requirement of such repayment into a penalty I - 42
Arguments of the parties I - 42
Findings of the Court I - 42
IV - Costs I - 43
(State aid - ECSC scheme - Rights of the recipient of aid - Scope: no necessity that trade and competition be affected - Applicability of different aid codes over time - Rate of interest to be applied for the repayment of incompatible aid)
In Joined Cases C-74/00 P and C-75/00 P,
Falck SpA, established in Milan (Italy), represented by G. Macrì, M. Condinanzi and F. Colussi, avvocati, with an address for service in Luxembourg,
and
Acciaierie di Bolzano SpA, established in Bolzano (Italy), represented by B. Nascimbene, avvocato, with an address for service in Luxembourg,
appellants,
APPEALS against the judgment of the Court of First Instance of the European Communities (Fifth Chamber, Extended Composition) of 16 December 1999 in Case T-158/96 Acciaierie di Bolzano v Commission [1999] ECR II-3927,
the other parties to the proceedings being:
Commission of the European Communities, represented by V. di Bucci and K.-D. Borchardt, acting as Agents, with an address for service in Luxembourg,
defendant at first instance,
and
Italian Republic, represented by U. Leanza, acting as Agent, assisted by D. Del Gaizo, avvocato dello Stato,
intervener at first instance,
THE COURT,
composed of: G.C. Rodríguez Iglesias, President, P. Jann, F. Macken, N. Colneric and S. von Bahr (Presidents of Chambers), D.A.O. Edward, A. La Pergola, J.-P. Puissochet (Rapporteur), M. Wathelet, V. Skouris and J.N. Cunha Rodrigues, Judges,
Advocate General: S. Alber,
Registrar: L. Hewlett, Principal Administrator,
having regard to the Report for the Hearing,
after hearing oral argument from the parties at the hearing on 4 December 2001, at which Falck SpA was represented by G. Macrì and M. Condinanzi, Acciaierie di Bolzano SpA by B. Nascimbene, the Italian Republic by M. Fiorilli, avvocato dello Stato, and the Commission by V. Di Bucci,
after hearing the Opinion of the Advocate General at the sitting on 21 February 2002,
gives the following
I - Legal framework and factual background
A - Legal framework
'1 Article 4 of the ECSC Treaty provides:
The following are recognised as incompatible with the common market for coal and steel and shall accordingly be abolished and prohibited within the Community, as provided in this Treaty:
...
(c) subsidies or aids granted by States, or special charges imposed by States, in any form whatsoever.
2 The first and second paragraphs of Article 95 of the ECSC Treaty provide as follows:
In all cases not provided for in this Treaty where it becomes apparent that a decision or recommendation of the Commission is necessary to attain, within the common market in coal and steel and in accordance with Article 5, one of the objectives of the Community set out in Articles 2, 3 and 4, the decision may be taken or the recommendation made with the unanimous assent of the Council and after the Consultative Committee has been consulted.
Any decision so taken or recommendation so made shall determine what penalties, if any, may be imposed.
3 In order to meet the restructuring needs of the steel sector, the Commission relied on the provisions of Article 95 of the Treaty in order to establish, from the beginning of the 1980s, a Community scheme under which the grant of State aid to the steel industry could be authorised in certain specific cases. That scheme has been subject to successive adjustments in order to deal with the economic difficulties of the steel industry. The series of decisions adopted in this regard are commonly termed Steel Aid Codes.
4 Commission Decision No 257/80/ECSC of 1 February 1980 establishing Community rules for specific aids to the steel industry (OJ 1980 L 29, p. 5) is the First Steel Aid Code. It was in force until 31 December 1981. It was replaced by Commission Decision No 2320/81/ECSC of 7 August 1981 establishing Community rules for aids to the steel industry (OJ 1981 L 228, p. 14), as amended by Commission Decision No 1018/85/ECSC of 19 April 1985 (OJ 1985 L 110, p. 5, hereinafter referred to as the Second Code), which remained in force until 31 December 1985.
5 The Third Steel Aid Code (Commission Decision No 3484/85/ECSC of 27 November 1985 establishing Community rules for aid to the steel industry (OJ 1985 L 340, p. 1, hereinafter the Third Code) was applicable between 1 January 1986 and 31 December 1988. The Fourth Steel Aid Code (Commission Decision No 322/89/ECSC of 1 February 1989 establishing Community rules for aid to the steel industry (OJ 1989 L 38, p. 8)) was in force between 1 January 1989 and 31 December 1991.
6 The Fifth Steel Aid Code, established by Commission Decision No 3855/91/ECSC of 27 November 1991 establishing Community rules for aid to the steel industry (OJ 1991 L 362, p. 57, hereinafter the Fifth Code), was in force from 1 January 1992 to 31 December 1996. It was replaced on 1 January 1997 by Commission Decision No 2496/96/ECSC of 18 December 1996 establishing Community rules for State aid to the steel industry (OJ 1996 L 338, p. 42), which constitutes the Sixth Steel Aid Code.'
B - Factual background
'7 The applicant, Acciaierie di Bolzano ... is an undertaking manufacturing special-steel products, which are listed in Annex I to the ECSC Treaty under code No 4400 and are therefore covered by the rules laid down in that Treaty. Until 31 July 1995 ACB was controlled by the steel group Falck SpA, a company incorporated under Italian law ... . At that date, however, the applicant company was sold to the company Valbruna Srl.
8 By letter of 5 July 1982 the Commission notified the Italian Government that it had decided to authorise the system of regional aid created by Law No 25/81 of the Autonomous Province of Bolzano of 8 September 1981 on financial assistance for industry (Provincial Law No 25/81). In that letter the Commission pointed out, however, that it also had to rule on the sectoral application of National Law No 675 of 12 August 1977 adopting measures for the coordination of industrial policy and the restructuring, reconversion and development of the sector (1/a) (hereinafter Law No 675/77), which was applicable in this regard, and that it therefore reserved the right to determine the conditions on which that regime would apply to the Province of Bolzano in the light of the decision it adopted at the national level. It also stated that the authorities in Bolzano had to comply fully with the rules and Community codes on the granting of aid to the steel industry.
...'
- a loan of ITL 13 206 000 million, of which 6 321 000 million were paid in March 1988 and 987 million in January 1989;
- a non-repayable grant of ITL 6 919 000 million, of which only 3 750 000 million, according to the contested decision, were paid; and
- a loan and a non-repayable grant amounting, according to the contested decision, to ITL 987 million and 650 million.
'The interest subsidy on a loan granted in December 1987 by the Province of Bolzano in Italy to the Bolzano steelworks under Provincial Law No 25 of 8 September 1981 is illegal State aid because it was made available without prior authorisation from the Commission and, furthermore, is incompatible with the common market pursuant to Commission Decision No 3484/85/ECSC [the Third Code]'.
'Article 1
The aid granted to Acciaierie di Bolzano under Provincial Law No 25/81 is illegal as it was not notified before being granted. Such aid measures are incompatible with the common market pursuant to Article 4(c) of the ECSC Treaty.
Article 2
Italy shall, acting in accordance with the provisions of Italian law relating to the recovery of amounts owed to the State, recover the aid paid to Acciaierie di Bolzanofrom 1 January 1986 under Provincial Law No 25/81 by Decisions Nos 7673 of 14 December 1987, 2429 of 2 May 1988 and 4158 of 4 July 1988. In order to abolish the effects of the aid, interest shall be charged on the amount of aid from the date of payment to the date of repayment. The rate shall be that used by the Commission to calculate the net grant equivalent of regional aid in the period in question.
...'
II - Procedure, forms of order sought and pleas in law raised before the Court of First Instance and the contested judgment
A - Procedure before the Court of First Instance
B - Forms of order sought and pleas in law raised before the Court of First Instance and the contested judgment
III - The appeals
A - Admissibility of the appeal brought by Falck
Arguments of the parties
Findings of the Court
B - The request that certain documents produced by ACB and Falck be removed from the case-file
Arguments of the parties
Findings of the Court
C - The substance of the appeals
1. The ground of appeal alleging a procedural irregularity adversely affecting the appellants' interests
Arguments of the parties
Findings of the Court
2. Breach of the rights of the defence by the Commission during the administrative procedure
Arguments of the parties
- ACB was adversely affected by not having been able to raise certain matters during the administrative procedure, when it did not have the opportunity to do so;
- the evidence offered by ACB concerning the use made of the aid was accepted by the Court of First Instance, but the contested judgment found that, in any event, only the Commission may grant a derogation from the prohibition of aid provided for in Article 4(c) of the Treaty.
Findings of the Court
3. Classification and assessment of the measures at issue
(a) Effect of the aid at issue on intra-Community trade and competition
Arguments of the parties
Findings of the Court
'The provisions of this Treaty shall not affect the provisions of the Treaty establishing the European Coal and Steel Community, in particular as regards the rights and obligations of Member States, the powers of the institutions of that Community and the rules laid down by that Treaty for the functioning of the common market in coal and steel.'
(b) The applicable Steel Aid Code
Arguments of the parties
Findings of the Court
(c) The Commission's obligations as regards information to be obtained before determining the compatibility of aid
4. The Commission's decision requiring repayment of part of the aid paid to ACB and the manner of such repayment
(a) Observance of the principles of protection of legitimate expectations, good faith and sincere cooperation
Arguments of the parties
Findings of the Court
(b) The Commission's delay in taking action
Arguments of the parties
Findings of the Court
(c) Bases for calculating the interest to be applied
Arguments of the parties
Findings of the Court
(d) Application of a penalty and breach of the principle of proportionality
(i) The complaint that changes in the situation transformed the requirement to repay into a penalty
Arguments of the parties
Findings of the Court
(ii) The complaint that the lack of a genuine examination of the compatibility of the aid transforms the requirement to repay into a penalty
Arguments of the parties
Findings of the Court
(iii) The complaint that errors and confusion over the various aids and the amounts to be repaid transformed the requirement to repay into a penalty
(iv) The complaint that the application of an excessive rate of interest for the repayment of the aid transformed the requirement of such repayment into a penalty
Arguments of the parties
Findings of the Court
IV - Costs
192. In the present case, since the appellants, so far as each is concerned, essentially failed in their pleas and the Commission applied for costs against them, they must be ordered to pay the costs and the Italian Republic must be ordered to bear its own costs.
On those grounds,
THE COURT
hereby:
1. Sets aside the judgment of the Court of First Instance of 16 December 1999 in Case T-158/96 Acciaierie di Bolzano v Commission in so far as it rejected the plea alleging that the Commission's belated claim for repayment entailed an infringement of the principle of legal certainty;
2. Dismisses the remainder of the appeals;
3. Dismisses the action for annulment brought by Acciaierie di Bolzano SpA before the Court of First Instance;
4. Orders Falck SpA and Acciaierie di Bolzano SpA to respectively pay the costs in Cases C-74/00 P and C-75/00 P;
5. Orders the Italian Republic to bear its own costs in Cases C-74/00 P and C-75/00 P.
Rodríguez Iglesias JannMacken
Colneric von Bahr Edward
La Pergola PuissochetWathelet
Skouris Cunha Rodrigues
|
Delivered in open court in Luxembourg on 24 September 2002.
R. Grass G.C. Rodríguez Iglesias
Registrar President
1: Language of the case: Italian.