British
and Irish Legal Information Institute
Freely Available British and Irish Public Legal Information
[
Home]
[
Databases]
[
World Law]
[
Multidatabase Search]
[
Help]
[
Feedback]
Court of Justice of the European Communities (including Court of First Instance Decisions)
You are here:
BAILII >>
Databases >>
Court of Justice of the European Communities (including Court of First Instance Decisions) >>
Commission v SNUA (Law governing the institutions) [1999] EUECJ C-69/97 (27 April 1999)
URL: http://www.bailii.org/eu/cases/EUECJ/1999/C6997.html
Cite as:
[1999] EUECJ C-69/97
[
New search]
[
Help]
IMPORTANT LEGAL NOTICE - The source of this judgment is the web site of the Court of Justice of the European Communities. The information in this database has been provided free of charge and is subject to a Court of Justice of the European Communities disclaimer and a copyright notice. This electronic version is not authentic and is subject to amendment.
JUDGMENT OF THE COURT (Fifth Chamber)
27 April 1999 (1)
(Arbitration clause - Breach of contract)
In Case C-69/97,
Commission of the European Communities, represented by Paolo Stancanelli, of
its Legal Service, and Jean-Francis Pasquier, a national civil servant on secondment
to that service, acting as Agents, assisted by Alberto Dal Ferro, of the Vicenza Bar,
with an address for service in Luxembourg at the office of Carlos Gómez de la
Cruz, of its Legal Service, Wagner Centre, Kirchberg,
applicant,
v
SNUA Srl, a company incorporated in Pordenone, Italy, represented by Andrea
Guarino, of the Rome Bar, and Ezio Trampus, of the Trieste Bar, with an address
for service in Luxembourg at the Chambers of Alain Lorang, 51 Rue Albert 1er,
defendant,
APPLICATION by the Commission of the European Communities under Article
181 of the EC Treaty for an order requiring SNUA Srl, first, to reimburse an
advance payment of ECU 195 397 made by the Commission for the completion of
an integrated system for the collection and recycling of solid waste at a private
plant, together with interest at the rate of ECU 43.09 per day of late payment from
1 April 1988 and, second, to pay the Commission the sum of ECU 60 000 by way
of compensation for the damage suffered,
THE COURT (Fifth Chamber),
composed of: J.-P. Puissochet (Rapporteur), President of the Chamber, P. Jann,
C. Gulmann, D.A.O. Edward and L. Sevón, Judges,
Advocate General: A. La Pergola,
Registrar: H.A. Rühl, Principal Administrator,
having regard to the Report for the Hearing,
after hearing oral argument from the parties at the hearing on 25 June 1998,
after hearing the Opinion of the Advocate General at the sitting on 15 October
1998,
gives the following
Judgment
- By application lodged at the Registry of the Court on 18 February 1997, the
Commission of the European Communities applied to the Court under an
arbitration clause, in accordance with Article 181 of the EC Treaty, claiming that
SNUA Srl (hereinafter 'SNUA') should be ordered, first, to reimburse an advance
payment of ECU 195 397 made by the Commission for the completion of an
integrated system for the collection and recycling of solid waste at a private plant,
together with interest at the rate of ECU 43.09 per day of late payment from 1
April 1988 and, second, to pay the Commission the sum of ECU 60 000 by way of
compensation for the damage suffered.
- On 8 January 1988 the European Economic Community, represented by the
Commission, entered into Contract No BM 441/86 with SNUA (hereinafter 'the
Contract') under Council Regulation (EEC) No 3640/85 of 20 December 1985 on
the promotion, by financial support, of demonstration projects and industrial pilot
projects in the energy field (OJ 1985 L 350, p. 29). In return for financial assistance
from the Community, SNUA undertook, under the terms of the Contract, to carry
out a programme of work between June 1987 and August 1988 as described in an
annex to the Contract.
- In the event of SNUA being unable to begin the work on the date provided for, it
was required under Clause 4.3.1 of the Contract to give the Commission at least
two weeks' prior notice and to propose a new date which the Commission had 30
days to accept or reject. If the date was rejected, the Contract was terminated
automatically and the advances received had to be repaid.
- Under Clause 4.3.2 of the Contract, SNUA was also required - within three months
of signature of the Contract, and thereafter every six months - to submit progress
reports to the Commission containing statements of expenditure.
- Clause 8 provided: 'the Commission may unilaterally terminate the contract in the
event of the contractor's non-performance of any of its obligations thereunder, in
particular if it fails to comply with the stipulations made in Clause 4.3 thereof;
termination shall take effect on expiry of a period of one month after notice has
been served by registered letter with acknowledgment of receipt, where non-performance persists'. Clause 8 further provided that, in those circumstances, 'the
contractor shall immediately repay to the Commission any amounts advanced by
way of financial assistance, together with interest payable from the date of receipt
of such funding. Interest shall be payable at the European Investment Bank's rate
applicable as at the date of the Commission's decision on the award of funding for
the project.'
- Under Clause 13 of the Contract, the contracting parties agreed 'to refer to the
Court of Justice of the European Communities all disputes concerning the validity,
interpretation or application of the Contract'. Clause 14 provided that the contract
was to be governed by Italian law.
- On 26 January 1988 the Commission made a payment of ECU 195 397 to SNUA,
representing an advance of 30% of the maximum Community contribution to the
project.
- It is common ground that SNUA did not carry out any work in return for that
payment until 7 December 1994, that is, almost seven years after the Contract was
signed.
- In the meantime, the Commission served notice on SNUA four times seeking
confirmation that work had begun, and informing it that the Contract would
otherewise be terminated automatically: notice was served on 15 March 1989
setting a deadline of 10 April 1989; on 12 July 1990 setting a deadline of 30
September 1990; on 10 July 1991 setting a deadline of 15 August 1991; and lastly,
on 18 September 1991, requiring that the project be put into operation by 31
December 1991, failing which the Contract would be terminated on that date. It
was not until 5 November 1992 that the Commission, having received no reply from
SNUA following the last notice, informed it that the Contract had been terminated
and that reimbursement of the advance was due.
- SNUA for its part thrice requested extensions of the deadline, namely on 6 March
1989, 24 September 1990 and 22 August 1991, pointing out on each occasion that
it was not responsible for the delay and that it was, rather, due to 'strong local
opposition' to the site initially chosen for the project, which could be overcome
only by means of a decision of the autonomous region of Friuli-Venezia-Giulia
granting permission for work to commence. The decision enabling the project to
be implemented at a different site from that initially anticipated was not taken until
15 July 1993.
- After the Commission had terminated the Contract automatically, SNUA failed to
respond to the demands for reimbursement of the advance served on it on 25
January 1994, 2 June 1994 and 15 February 1995.
Termination of the Contract
- The Commission claims that under Clause 8 of the Contract, termination took
effect on 31 December 1991 since SNUA had not, despite several extensions of
time, fulfilled its obligations under Clause 4.3 though it had been put on notice to
do so in the proper way. The fact that the deadline for commencement of the
works was repeatedly extended so as to enable SNUA to deal with an obstacle
beyond its control did not mean the Commission had waived its right to rely on the
automatic termination clause - quite the reverse, the clause having been referred
to in each of the letters sent to SNUA.
- SNUA contends first of all that the provision in Clause 8 of the Contract is purely
stylistic as regards its effect on termination under Italian law since, under Article
1456 of the Italian Civil Code as interpreted by the Corte Suprema di Cassazione,
automatic termination can occur only where express provision has been made for
it by the parties for non-performance of a specified obligation. Clause 8, which is
worded in general terms, and which, as stated at paragraph 5 of this judgment,
concerns non-performance 'of any of [the contractor's] obligations, in particular if
it fails to comply with the stipulations made in Clause 4.3', does not satisfy that
criterion.
- Second, SNUA points out that it cannot incur blame in respect of circumstances
over which it was unable to exercise any control. In that connection, it relies on the
fact that the Friuli-Venezia-Giulia autonomous region had confirmed that the
company's diligence was not in issue since the delay was the result of local political
opposition to the project which ultimately forced the authorities to opt for a new
site. The Commission itself acknowledged that as this was a case involving force
majeure no fault could be ascribed to SNUA, and that an express termination
clause which was subject to the condition that one of the parties should be held
responsible for non-performance could not in any event be relied upon against it.
- According to SNUA, the Contract could therefore be terminated only in
accordance with the procedure set out in Articles 1453 and 1454 of the Italian Civil
Code. The notices served by the Commission on SNUA could not, on that basis,
operate to terminate the Contract unless a specific application for termination had
been made to the court to enable it to assess whether the period granted to the
defaulting party was sufficient and to determine the extent and seriousness of the
breach. It was also for the Commission, in that context, to establish the defaulting
party's liability.
- Since no formal application for termination of the Contract was made, SNUA
considers that the Commission cannot claim reimbursement of the sums paid, one
of the consequences of termination.
- It must be observed in that connection that, since the Commission's right to
terminate the Contract unilaterally is based on the combined provisions of Clauses
4.3 and 8 thereof, the outcome of the dispute depends on the legal effects
attributed to those clauses.
- Where proceedings are brought before it pursuant to an arbitration clause, the
Court must resolve the dispute on the basis of the national law applicable to the
contract (see, in particular, Case 426/85 Commission v Zoubek [1986] ECR 4057,
paragraph 4). In this case, as stated at paragraph 6 of this judgment, the applicable
national law is Italian law.
- Further, a document such as the Contract at issue must be interpreted in the light
of its context. In that connection, the decision to grant funding to SNUA was made
pursuant to Regulation No 3640/85 which provides, inter alia, at Article 7(2) that
funding is to be granted in return for undertakings from the recipients, who must
keep the Commission properly informed as to progress in fulfilling those
undertakings.
- In that context, it would seem that Clause 8 of the Contract is clearly intended to
allow the Commission, on the basis of an objective criterion, unilaterally to dissolve
the relationship with the contractor, in particular if the latter fails to perform the
obligations set out in Clause 4.3.
- Under Italian contract law, such a provision need not be considered invalid. Indeed,
Article 1456 of the Italian Civil Code allows contracting parties expressly to agree
that a contract is to be terminated automatically in the event of non-performance
of a specified obligation. The requirement laid down by the Corte Suprema di
Cassazione that the obligation must be specified in order for that provision to apply
may be considered to be satisfied by the reference in Clause 8 to the obligations
set out in Clause 4.3 of the Contract, which relates to the reports which the
contractor must submit to the Commission under Article 7(2) of Regulation No
3640/85. Therefore, in the case of breach of the obligations set out in Clause 4.3,
the fact that the Contract is subject to Italian law does not prevent Clause 8 from
bringing the Contract to an end.
- With reference to SNUA's argument that it cannot be held responsible for the non-performance of contractual obligations, it is apparent from Clause 8 of the Contract
that it is not a prerequisite for automatic termination that the contractor should be
at fault, only that certain contractual obligations should not have been performed,
irrespective of the cause or origin of such non-performance.
- Whilst it is true that the case-law of the Corte Suprema di Cassazione requires that,
in order to bring express termination clauses which are subject to Article 1456 of
the Italian Civil Code into effect, it must be possible to attribute responsibility for
non-performance to the contractor in default, the fact remains that, under Article
1322 of the Code, the parties' right freely to determine the terms of the Contract
within the limits set by the law is recognised as forming part of the principle of
freedom of contract. It does not therefore preclude the parties to a contract from
deciding to insert therein a termination clause which is not subject to the condition
that the contractor must be responsible for non-performance, by way of derogation
from the usual format of contracts under Italian law.
- In this case, it is quite clear that the parties intended to make provision for specific
methods of terminating the Contract given, inter alia, the particular nature of
relations between the Community and the company in receipt of funding under
Regulation No 3640/85 and the Commission's ability in practice to monitor
implementation of the work schedule, which depends to a large degree on the
reports which the contractor must submit to it under Clause 4.3.
- The Commission was therefore justified in relying on Clause 8 to terminate the
Contract automatically.
- In that connection, the letter sent to SNUA by the Commission on 18 September
1991 fulfils the conditions set out in Clause 8 of the Contract and thus constitutes
proper notice of termination, even though it does not refer expressly to Clause 8
and allows SNUA a period of more than one month to act.
Reimbursement of the advance payment
- Under Clause 8.3 of the Contract, SNUA is obliged to reimburse the advance paid,
in the amount of ECU 195 397, which is uncontested.
Interest
- Under Clause 8.3 of the Contract, interest is payable from the date of receipt of
the advance payment at the rate set by the European Investment Bank as at the
date of the Commission's decision on the award of funding.
- Consequently, the Commission considers that interest is payable from 1 April 1988.
It observes that the decision to grant funding was taken on 11 November 1986 and
that the rate of interest applicable at the time was 8.05%, so that the interest due
amounts to ECU 43.09 per day of late payment until the date of final settlement.
- Since SNUA has not challenged this point in any way and there is nothing in the
documents before the Court to cast doubt on that assessment, the Commission's
claim for payment of interest in the amount specified must be upheld.
- As regards the amount of the principal sum and interest, the reference to ecus
must, pursuant to Article 2(1) of Council Regulation No 1103/97/EC of 17 June
1997 on certain provisions relating to the introduction of the euro (OJ 1997 L 162,
p. 1), be replaced by a reference to euros, at the rate of one euro to one ecu.
Compensation for damage
- Relying on Article 1453 of the Italian Civil Code, the Commission also claims that
SNUA should be ordered to pay the sum of ECU 60 000 by way of compensation
for the damage which the Commission is alleged to have suffered on account of the
non-performance of the Contract, consisting in the unjustified immobilisation of
Community funds which could have been used for other projects, waste of human
resources and damage to its credibility.
- SNUA contends that, since it was not at fault, it cannot be made liable.
- The Commission challenges SNUA's contention that it was not at fault and claims
that due care under the contract should at least have prompted SNUA to advise
the Commission that there was a risk of non-performance.
- It is appropriate to point out in that connection that where the Court's jurisdiction
is based on an arbitration clause, it is restricted solely to hearing claims brought
under the contract concluded with the Community or that are directly connected
with the obligations arising from that contract (see Commission v Zoubek, cited
above, paragraph 11).
- The provision in Article 1453 of the Italian Civil Code, to the effect that a
contracting party has the right to request the defaulting party to make good the
damage in any event, applies, on its own wording, regardless of the procedure by
which termination is effected. The Commission is therefore entitled to rely on that
provision, which is applicable to the Contract by virtue of Clause 14.
- In order to determine the merits of that claim, a distinction must be drawn between
the period prior to termination of the Contract and the period subsequent thereto.
- So far as concerns the first period, it was open to the Commission under the
combined provisions of Clauses 4.3 and 8 of the Contract to draw the proper
inferences in good time as to the consequences of the contractor's failure to honour
its contractual undertakings and to terminate the contractual relationship early and
unilaterally. In any event, the Commission itself points out that it was under no
obligation to grant extensions of time. That being so, the Commission cannot expect
the defendant to assume responsibility for damage which is the result of the
former's own decisions or inaction.
- So far as concerns the period following termination of the Contract, the situation
is different by reason of the fact that the contractor was at fault in refusing to
accede to the claims for reimbursement. However, as regards, first of all, the
unwarranted immobilisation of Community funds, it should be noted that the
default interest due from the defendant must have the effect of reversing any
financial damage suffered by the Community on account of the delay in payment;
second, so far as concerns the loss of funding suffered by other prospective
contractors, the Commission cannot be allowed to rely on damage potentially
suffered by third parties.
- As regards the alleged misuse of Commission staff during the judicial stage of the
dispute, it should be noted that the expenses incurred by the parties for the
purpose of these proceedings are not, in any event, of such a nature that they may
be regarded as constituting damage distinct from the burden of costs.
- Lastly, as regards the other damage alleged, the Commission has failed to establish
satisfactorily or with the requisite precision that such damage was in fact caused.
- The Commission's claim for compensation must therefore be rejected.
Costs
43. Under Article 69(2) of the Rules of Procedure, the unsuccessful party is to be
ordered to pay the costs if they have been applied for in the successful party's
pleadings. Since SNUA has been unsuccessful in its pleadings, it must be ordered
to pay the costs.
On those grounds,
THE COURT (Fifth Chamber),
hereby:
1. Orders SNUA Srl to pay to the Commission of the European Communities
the sum of EUR 195 397 together with interest at a rate of EUR 43.09 per
day of late payment as from 1 April 1988 until final settlement of the debt;
2. Dismisses the remainder of the action;
3. Orders SNUA Srl to pay the costs.
PuissochetJann
Gulmann
EdwardSevón
|
Delivered in open court in Luxembourg on 27 April 1999.
R. Grass
J.-P. Puissochet
Registrar
President of the Fifth Chamber
1: Language of the case: Italian.