JUDGMENT OF THE COURT (Sixth Chamber)
17 September 1998 (1)
(Failure by a Member State to fulfil obligations - Public works contracts - Directives 89/440/EEC and 93/37/EEC - Failure to publish a contract notice - Application of negotiated procedure without justification)
In Case C-323/96,
Commission of the European Communities, represented by Hendrik van Lier, Legal Adviser, acting as Agent, with an address for service in Luxembourg at the office of Carlos Gómez de la Cruz, of its Legal Service, Wagner Centre, Kirchberg,
applicant,
v
Kingdom of Belgium, represented by Michel Flamée, of the Brussels Bar, acting as Agent, with an address for service in Luxembourg at the Belgian Embassy, 4 Rue des Girondins,
defendant,
APPLICATION for a declaration that, by failing to publish a contract notice in the Official Journal of the European Communities both for the overall project and for each of the lots relating to the construction of the premises of the Vlaamse Raad, and by failing to apply the award procedures laid down in Council Directive 89/440/EEC of 18 July 1989, amending Directive 71/305/EEC concerning
coordination of procedures for the award of public works contracts (OJ 1989 L 210, p. 1), and in Council Directive 93/37/EEC of 14 June 1993 concerning the coordination of procedures for the award of public works contracts (OJ 1993 L 199, p. 54) and, more specifically, by having awarded Lot No 4 by negotiated procedure without justification, the Kingdom of Belgium has failed to fulfil its obligations under those directives and, more specifically, Articles 7 and 11 of Directive 93/37,
THE COURT (Sixth Chamber),
composed of: H. Ragnemalm, President of the Chamber, G.F. Mancini, P.J.G. Kapteyn, J.L. Murray and K.M. Ioannou (Rapporteur), Judges,
Advocate General: S. Alber,
Registrar: H. von Holstein, Deputy Registrar,
having regard to the Report for the Hearing,
after hearing oral argument from the parties at the hearing on 5 February 1998, during which the Commission was represented by Henrik van Lier and the Belgian Government by Philippe Colle and Katelijne Ronse, of the Brussels Bar,
after hearing the Opinion of the Advocate General at the sitting on 19 March 1998,
gives the following
- by failing to publish a contract notice in the Official Journal of the European Communities (hereinafter 'OJEC'), both for the overall project and for each of the lots relating to the construction of the premises of the Vlaamse Raad, and
- by failing to apply the award procedures laid down in Council Directive 89/440/EEC of 18 July 1989, amending Directive 71/305/EEC concerning coordination of procedures for the award of public works contracts (OJ 1989 L 210, p. 1), and in Council Directive 93/37/EEC of 14 June 1993 concerning the coordination of procedures for the award of public works
contracts (OJ 1993 L 199, p. 54) and, more specifically, by having awarded Lot No 4 by negotiated procedure without justification,
the Kingdom of Belgium has failed to fulfil its obligations under those directives and, more specifically, Articles 7 and 11 of Directive 93/37.
Facts
The pre-litigation procedure
Directive 93/37
'For the purpose of this Directive:
...
(b) "contracting authorities" shall be the State, regional or local authorities, bodies governed by public law, associations formed by one or several of such authorities or bodies governed by public law;
...
...
(e) "open procedures" are those national procedures whereby all interested contractors may submit tenders;
(f) "restricted procedures" are those national procedures whereby only those contractors invited by the contracting authority may submit tenders;
(g) "negotiated procedures" are those national procedures whereby contracting authorities consult contractors of their choice and negotiate the terms of the contract with one or more of them;
...'
'1. The provisions of this Directive shall apply to public works contracts whose estimated value net of VAT is not less than ECU 5 000 000.
...
3. Where a work is subdivided into several lots, each one the subject of a contract, the value of each lot must be taken into account for the purpose of calculating the amounts referred to in paragraph 1. Where the aggregate value of the lots is not less than the amount referred to in paragraph 1, the provisions of that paragraph shall apply to all lots. Contracting authorities shall be permitted to depart from this provision for lots whose estimated value net of VAT is less than ECU 1 000 000 provided that the total estimated value of all the lots exempted does not, in consequence, exceed 20% of the total estimated value of all lots.'
'1. In awarding public works contracts the contracting authorities shall apply the procedures defined in Article 1(e), (f) and (g), adapted to this Directive.
2. The contracting authorities may award their public works contracts by negotiated procedure, with prior publication of a contract notice and after having selected the candidates according to publicly known qualitative criteria, in the following cases:
...
3. The contracting authorities may award their public works contracts by negotiated procedure without prior publication of a contract notice, in the following cases:
(a) in the absence of tenders or of appropriate tenders in response to an open or restricted procedure in so far as the original terms of the contract are not substantially altered and provided that a report is communicated to the Commission at its request;
(b) when, for technical or artistic reasons or for reasons connected with the protection of exclusive rights, the work may only be carried out by a particular contractor;
(c) in so far as is strictly necessary when, for reasons of extreme urgency brought about by events unforeseen by the contracting authorities in question, the time-limit laid down for the open, restricted or negotiated procedures referred to in paragraph 2 cannot be kept. The circumstances invoked to justify extreme urgency must not in any event be attributable to the contracting authorities;
(d) for additional works not included in the project initially considered or in the contract first concluded but which have, through unforeseen circumstances, become necessary for the carrying out of the work described therein, on condition that the award is made to the contractor carrying out such work:
- when such works cannot be technically or economically separated from the main contract without great inconvenience to the contracting authorities, or
- when such works, although separable from the execution of the original contract, are strictly necessary to its later stages.
However, the aggregate amount of contracts awarded for additional works may not exceed 50% of the amount of the main contract;
(e) for new works consisting of the repetition of similar works entrusted to the undertaking to which the same contracting authorities awarded an earlier contract, provided that such works conform to a basic project for which a first contract was awarded according to the procedures referred to in paragraph 4.
As soon as the first project is put up for tender, notice must be given that this procedure might be adopted and the total estimated cost of subsequent works shall be taken into consideration by the contracting authorities when
they apply the provisions of Article 6. This procedure may only be adopted during the three years following the conclusion of the original contract.
4. In all other cases, the contracting authorities shall award their public works contracts by the open procedure or by the restricted procedure.'
'2. Contracting authorities who wish to award a public works contract by open, restricted or negotiated procedure referred to in Article 7(2), shall make known their intention by means of a notice.
...
9. The notices referred to in paragraphs 2, 3 and 4 shall be published in full in the Official Journal of the European Communities and in the TED data bank in the original languages. A summary of the important elements of each notice shall be published in the other official languages of the Community, the original text alone being authentic.'
Directive 89/440
The application
and 93/37. It is apparent from the documents before the Court that Directive 89/440 was in force when the first tendering procedure was initiated and that Directive 93/37 was in force when the procedure relating to Lot No 4 was initiated. Furthermore, it should be recalled that Directive 93/37 repealed and replaced Directive 71/305, including the provisions which amended it, inter alia those in Directive 89/440.
'(a) contracts awarded in the fields referred to in Articles 2, 7, 8 and 9 of Directive 90/531/EEC or fulfilling the conditions in Article 6(2) of that Directive;
(b) works contracts which are declared secret or the execution of which must be accompanied by special security measures in accordance with the laws, regulations or administrative provisions in force in the Member State concerned or when the protection of the basic interests of the Member State's security so requires'.
- by failing to publish a contract notice in the OJEC both for the overall project and for each of the lots relating to the construction of the premises of the Vlaamse Raad, and
- by failing to apply the award procedures laid down in Directive 71/305, as amended by Directive 89/440, and Directive 93/337 and, more specifically, by awarding Lot No 4 by negotiated procedure without justification,
the Kingdom of Belgium has failed to fulfil its obligations under those directives and, more specifically, under Articles 7 and 11(2) and (9) of Directive 93/37.
Costs
45. Under Article 69(2) of the Rules of Procedure, the unsuccessful party is to be ordered to pay the costs. Since the Kingdom of Belgium has been unsuccessful, it must be ordered to pay the costs.
On those grounds,
THE COURT (Sixth Chamber)
hereby:
1. Declares that,
- by failing to publish a contract notice in the Official Journal of the European Communities both for the overall project and for each of the lots relating to the construction of the premises of the Vlaamse Raad, and
- by failing to apply the award procedures laid down in Council Directive 71/305/EEC of 26 July 1971 concerning the coordination of procedures for the award of public works contracts, as amended by Council Directive 89/440/EEC of 18 July 1989, and Council Directive 93/37/EEC of 14 June 1993 concerning the coordination of procedures for the award of public works contracts and, more specifically, by having awarded lot No 4 by negotiated procedure without justification,
the Kingdom of Belgium has failed to fulfil its obligations under those directives and, more specifically, under Articles 7 and 11(2) and (9) of Directive 93/37;
2. Orders the Kingdom of Belgium to pay the costs.
Ragnemalm Mancini Kapteyn
MurrayIoannou
|
Delivered in open court in Luxembourg on 17 September 1998.
R. Grass H. Ragnemalm
Registrar President of the Sixth Chamber
1: Language of the case: Dutch.