Commission v Italy (Law relating to undertakings) [1997] EUECJ C-43/97 (17 July 1997)
URL: http://www.bailii.org/eu/cases/EUECJ/1997/C4397.html
Cite as:
[1997] EUECJ C-43/97
[
New search]
[
Help]
IMPORTANT LEGAL NOTICE -
IMPORTANT LEGAL NOTICE - The source of this judgment is the web site of the Court of Justice of the European Communities. The information in this database has been provided free of charge and is subject to a Court of Justice of the European Communities disclaimer and a copyright notice. This electronic version is not authentic and is subject to amendment.
JUDGMENT OF THE COURT (Sixth Chamber)
17 July 1997(1)
(Failure to fulfil obligations - Directive 93/36/EEC - Failure to transpose within
the prescribed period)
In Case C-43/97,
Commission of the European Communities, represented by Paolo Stancanelli, of
its Legal Service, acting as Agent, with an address for service in Luxembourg at the
office of Carlos Gómez de la Cruz, of its Legal Service, Wagner Centre, Kirchberg,
applicant,
v
Italian Republic, represented by Professor Umberto Leanza, Head of the Legal
Department in the Ministry of Foreign Affairs, acting as Agent, assisted by Ivo M.
Braguglia, Avvocato dello Stato, with an address for service in Luxembourg at the
Italian Embassy, 5 Rue Marie-Adélaďde,
defendant,
APPLICATION for a declaration that, by failing to adopt within the prescribed
period the laws, regulations and administrative provisions necessary to comply with
Council Directive 93/36/EEC of 14 June 1993 coordinating procedures for the
award of public supply contracts (OJ 1993 L 199, p. 1) and by failing to notify those
provisions, the Italian Republic has failed to fulfil its obligations under the first
subparagraph of Article 34(1) of that directive,
THE COURT (Sixth Chamber),
composed of: G.F. Mancini, President of the Chamber, J.L. Murray, G. Hirsch,
H. Ragnemalm (Rapporteur) and R. Schintgen, Judges,
Advocate General: C.O. Lenz,
Registrar: R. Grass,
having regard to the report of the Judge-Rapporteur,
after hearing the Opinion of the Advocate General at the sitting on 12 June 1997,
gives the following
Judgment
- By application lodged at the Court Registry on 3 February 1997, the Commission
of the European Communities brought an action under Article 169 of the EC
Treaty, seeking a declaration that, by failing to adopt within the prescribed period
the laws, regulations and administrative provisions necessary to comply with Council
Directive 93/36/EEC of 14 June 1993 coordinating procedures for the award of
public supply contracts (OJ 1993 L 199, p. 1) and by failing to notify those
provisions, the Italian Republic has failed to fulfil its obligations under the first
subparagraph of Article 34(1) of that directive.
- Under the first subparagraph of Article 34(1) of Directive 93/36, Member States
were to bring into force the laws, regulations and administrative provisions
necessary to comply with the directive before 14 June 1994 and immediately to
inform the Commission thereof.
- On 9 August 1994, not having been informed of the measures taken to transpose
Directive 93/36 and not having any other information from which it was possible
to conclude that the Italian Republic had fulfilled its obligations, the Commission
gave the Italian Government notice to submit its observations within two months.
- On 25 October 1995, not having received any reply, the Commission sent the
Italian Government a reasoned opinion, requesting it to adopt the necessary
measures within a period of two months from that notification.
- The Commission did not receive any reply from the Italian authorities and
therefore brought the present action.
- The Italian Republic does not deny that it has failed to fulfil its obligations as set
out in the application and merely states that it will shortly adopt measures to
remedy the situation. It states that under the draft 1995/1996 Community Law,
currently before the Italian Parliament, responsibility is to be delegated to the
Government for transposing Directive 93/96 into national law by means of a
legislative decree which will be adopted as soon as the 1995/1996 Community Law
enters into force.
- Since Directive 93/96 has not been transposed within the period laid down therein,
the Italian Republic must be found to have failed to fulfil its obligations as
contended by the Commission.
- That conclusion cannot be called into question by the Italian Government's
argument that the failure with which it is charged is of minor importance inasmuch
as the basic provisions concerning procedures for the award of public supply
contracts have long formed part of the national legal system as a result of the
implementation of Council Directive 77/62/EEC of 21 December 1976 coordinating
procedures for the award of public supply contracts (OJ 1977 L 13, p. 1), as
amended on several occasions.
- The Italian Government does not deny that Directive 93/96 imposes new
obligations on the Member States, which they were to implement by 14 June 1994
at the latest.
- Contrary to what the Commission claims, however, the Court does not have to take
account of the failure to notify the laws, regulations or administrative provisions
necessary to comply with the directive, since the Italian Republic did not adopt
those provisions within the period prescribed in the reasoned opinion (see Case
C-147/94 Commission v Spain [1995] ECR I-1015, paragraph 7).
- It must therefore be found that, by failing to adopt within the prescribed period the
laws, regulations and administrative provisions necessary to comply with Directive
93/36, the Italian Republic has failed to fulfil its obligations under the first
subparagraph of Article 34(1) of that directive.
Costs
- Under Article 69(2) of the Rules of Procedure, the unsuccessful party is to be
ordered to pay the costs. Since the Italian Republic has been unsuccessful, it must
be ordered to pay the costs.
On those grounds,THE COURT (Sixth Chamber)
hereby:
- Declares that, by failing to adopt within the prescribed period the laws,
regulations and administrative provisions necessary to comply with Council
Directive 93/36/EEC of 14 June 1993 coordinating procedures for the award
of public supply contracts, the Italian Republic has failed to fulfil its
obligations under the first subparagraph of Article 34(1) of that directive;
- Dismisses the remainder of the application;
- Orders the Italian Republic to pay the costs.
ManciniMurray
Hirsch
Ragnemalm Schintgen
|
Delivered in open court in Luxembourg on 17 July 1997.
R. Grass
G.F. Mancini
Registrar
President of the Sixth Chamber
1: Language of the case: Italian.