FIFTH SECTION
CASE OF
SEDMINEK v. SLOVENIA
(Application no.
9842/07)
JUDGMENT
STRASBOURG
24 October 2013
This judgment will become final in the circumstances set out
in Article 44 § 2 of the Convention. It may be subject to editorial
revision.
In the case of Sedminek v. Slovenia,
The European Court of Human
Rights (Fifth Section), sitting as a Chamber composed of:
Mark Villiger, President,
Angelika Nußberger,
Boštjan M. Zupančič,
Ann Power-Forde,
Ganna Yudkivska,
Helena Jäderblom,
Aleš Pejchal, judges,
and Claudia Westerdiek, Section Registrar,
Having deliberated in private on 1 October 2013,
Delivers the following judgment, which was adopted on that
date:
PROCEDURE
The case originated in an application (no.
9842/07) against the Republic of Slovenia lodged with the Court under Article
34 of the Convention for the Protection of Human Rights and Fundamental
Freedoms (“the Convention”) by a Slovenian national, Mr Milan Sedminek (“the
applicant”), on 13 February 2007.
The Slovenian Government (“the Government”) were
represented by their Agent, Mrs T. Mihelič Žitko, State Attorney.
On 4 January 2011 the application was
communicated to the Government.
THE FACTS
I. THE CIRCUMSTANCES OF THE CASE
The applicant was born in 1955 and lives in Polzela.
On 21 August 1996 the applicant bought business
premises from company I. Shortly afterwards, he learned that the premises were
in fact smaller than had been agreed in the contract.
A. Contentious proceedings (Ref. No. P 1179/98)
On 14 September 1998 the applicant
instituted civil proceedings against company I. before the Celje District Court,
claiming reimbursement of the corresponding part of the purchase price
exceeding the payment for the actual size of the premises.
Hearings were held on 26 November 2001 and
19 December 2001. On the latter date the court decided to appoint a
construction expert and adjourned the main hearing so that an expert opinion could
be obtained. Both parties agreed that I.U. would be appointed as expert.
On 23 January 2002 the Celje District Court
appointed I.U. as the construction expert. On 21 February 2002 notification
of the appointment and a summons to retrieve the case file were sent to I.U.
Two attempts to serve the court’s correspondence on I.U. were made, but he
failed to collect them from the post office. The correspondence was finally
served on him on 24 May 2002.
After I.U. had failed to retrieve the case file,
despite being reminded to do so by the Court in letters dated 17 July and
15 November 2002 respectively, the Celje District Court appointed another
construction expert, J.A, on 12 February 2003. The applicant filed a request
to have J.A. excluded from the case on grounds of partiality.
On 25 April 2003 the court granted the
applicant’s request to have J.A. excluded and appointed a new expert, F. J.
On 5 May 2003 F. J. informed the court that
owing to medical reasons he would not be able to fulfil his appointment. On the
same date the court appointed V. T. as expert.
On 30 June 2003 V. T. submitted his expert
opinion.
On 29 September 2003 the court held a main
hearing at which the parties proposed that the expert opinion be supplemented
by further information. The main hearing was for that reason adjourned.
On 4 December 2003 V.T. informed the court
that there was no need to supplement his opinion.
On 12 January 2004 a main hearing was held.
The parties agreed to obtain additional project documentation from company S.
After having obtained the documentation from
company S., the applicant informed the court that he would not be requesting a
main hearing with regard to the submitted documentation.
On 2 April 2004 the Celje Distric Court delivered
its judgment and ordered company I. to pay 1,103,650 Slovenian tolars (SIT −
approximately 5,800 euros (EUR)) plus statutory default interest calculated from
1 September 1996.
B. Bankruptcy proceedings (Ref. Nos. St 19/2004 and St
1349/2008)
On 8 April 2004 the Celje District Court
decided to open bankruptcy (insolvency) proceedings against company I.
On 6 May 2004 the applicant lodged a claim in
the bankruptcy proceedings, seeking the amount payable under the Celje District
Court judgment of 2 April 2004.
After the opening of the bankruptcy proceedings,
247 creditors lodged claims in the total amount of SIT 2,320,682,457 (approximately
EUR 12,212,000).
On 7 July 2004 the applicant’s claim in the
amount of SIT 5,502,364 (approximately EUR 29,000) was acknowledged in the
bankruptcy proceedings.
On 7 February 2007 the receiver reported to
the applicant about the debts and assets of the estate, estimating that after
distribution to the priority creditors there would probably be nothing left to repay
the ordinary creditors.
On 9 July 2009 the Celje District Court
issued a decision on the distribution of the bankruptcy estate to the first ranking
(secured) creditors.
On 9 August 2010 the Celje District Court
issued a decision on the distribution of the bankruptcy estate to the next ranking
(preferential) creditors.
On 27 May 2011 the applicant lodged a
supervisory appeal with the Celje District Court. In the appeal, the applicant
complained about the length of both the contentious and bankruptcy proceedings.
He argued that if the contentious proceedings had been conducted within a
reasonable time, he would have been able to enforce his claim before the opening
of the bankruptcy proceedings. He further informed the court that he would be
willing to settle in the bankruptcy proceedings for 50% of the claim.
On 8 July 2011 the president of the Celje
District Court rejected the applicant’s supervisory appeal on procedural
grounds as unsubstantiated, since he had failed to give valid reasons as to why
he believed the court had been unnecessarily delaying the proceedings.
The bankruptcy proceedings are still pending.
II. RELEVANT DOMESTIC LAW AND PRACTICE
A. Act on the Protection of the Right to a Trial
without Undue Delay
The Act on the Protection of the Right to a
Trial without Undue Delay (Zakon o varstvu
pravice do sojenja brez nepotrebnega odlašanja, Official Gazette,
No. 49/2006 - “the 2006 Act”) became operational on 1 January 2007.
Under its sections 1 and 2, the right to a trial within a reasonable time
is guaranteed for parties to court proceedings, participants in non-contentious
proceedings and injured parties in criminal proceedings.
Section 3 of the 2006 Act provides for two
remedies to expedite pending proceedings - a supervisory
appeal (nadzorstvena pritožba) and
a motion for a deadline (rokovni predlog)
- and, after the case has been finally resolved, a claim for just satisfaction
in respect of damage sustained because of the undue delay (zahteva za pravično zadoščenje).
For a more detailed presentation of the relevant
domestic law see Žunič v. Slovenia, (dec.) no. 24342/04, §§ 16-26, 18 October 2007, and Žurej v. Slovenia (dec.), no. 10386/03, 16 March 2010.
B. Legislation and practice concerning bankruptcy
proceedings
The relevant provisions of the Compulsory Settlement,
Bankruptcy and Liquidation Act (Zakon o prisilni poravnavi, stečaju in
likvidaciji, Official Gazette 67/1933, in force until 15 January 2008)
read:
Section 11
“(2) Bankruptcy proceedings shall be conducted promptly.”
Section 84
“(1) The bankruptcy panel may, in order to protect the
interests of creditors in the bankruptcy proceedings, appoint a committee of
creditors.”
Section 137
“(1) Creditors shall register their claims with the bankruptcy panel
within two months of the notice of the opening of the bankruptcy proceedings being
published in the Slovenian Official Gazette.”
The relevant provisions of the Financial
Operations, Insolvency Proceedings and Compulsory Dissolution Act (Zakon o
finančnem poslovanju, postopkih zaradi insolventosti in prisilnem
prenehanju, Official Gazette, no. 126/2007, in force from 15 January
2008, operational from 1 October 2008) read:
Section 48: Principle of the promptness of proceedings
“(1) The court shall execute its procedural acts in insolvency
proceedings within the time-limits prescribed by this Act, provided that by
exercising its competencies of supervision over the receiver it makes efforts
to ensure that all the actions of the receiver executed in insolvency
proceedings are completed within the time-limits prescribed by this Act.
(2) Courts and other State bodies shall give priority
consideration to matters which involve the debtor in bankruptcy as a party to
proceedings, or the result of which affects the progress of bankruptcy
proceedings.”
Section 57: Obtaining the capacity ad processum of a
creditor
“(1) Creditors shall obtain entitlement to carry out procedural
acts in main insolvency proceedings by lodging their claims in the proceedings
within the time-limits prescribed in section 59...”
Section 76: The committee of creditors as the body of
creditors
“The committee of creditors shall be a body of creditors which
carries out procedural acts in insolvency proceedings which the law stipulates
are to be carried out by the committee of creditors, on behalf of all the creditors
subject to the proceedings.”
In practice, the bankruptcy proceedings are
divided into three stages. In the first stage, claims are registered and acknowledged
if they are not disputed by any of the other creditors within a certain time. It
is also determined whether any creditors have separate rights entitling them to
have assets excluded from the bankruptcy estate. In the second stage, the
receiver realises the estate by determining the value of the assets and realising
them through sales and recovery claims against third parties. In the third
stage, the bankruptcy estate is distributed amongst the creditors.
C. Domestic practice concerning the application of the
2006 Act in the context of bankruptcy proceedings
The Government submitted to the Court copies of
four domestic decisions dated 8 May 2008 (Dec. no. Su Np 3/2008), 28 November
2008 (Dec. No. Su Np 99/2008), 1 April 2010 (Dec. No. Su Np 25/2010) and 29 September
2010 (Dec. No. Su Np 64/2010) concerning supervisory appeals of parties in
bankruptcy and compulsory dissolution proceedings. All four supervisory appeals
were dismissed by the presidents of the competent courts as unfounded.
THE LAW
I. ALLEGED VIOLATION OF ARTICLE 6 § 1 OF THE
CONVENTION
The applicant complained that the length of contentious
and bankruptcy proceedings had been incompatible with the “reasonable time”
requirement in Article 6 § 1 of the Convention, which reads as follows:
“In the determination of his civil rights
and obligations ... everyone is entitled to a ... hearing within a reasonable
time by [a] ... tribunal ...”
A. Admissibility
1. Exhaustion of domestic remedies
The Government raised an objection, arguing that
the applicant had not exhausted the domestic remedies available to him.
The Court considers that the question whether
the requirement that an applicant must exhaust domestic remedies has been
satisfied in the instant case is closely linked to the complaint concerning the
existence of an effective remedy within the meaning of Article 13 of the
Convention. It therefore considers that this objection raised by the Government
under Article 6 § 1 of the Convention should be joined to the merits of the
complaint under Article 13.
2. Compliance with the six-month rule
The Government raised a further objection,
arguing that since the contentious proceedings before the Celje District Court
had terminated on 2 April 2004 and the applicant had lodged his application
to the Court on 13 February 2007, the application concerning these
proceedings had been lodged after the expiry of the six-month time-limit. They
argued that the bankruptcy proceedings, even though serving as a venue for enforcing
the judgment given in favour of the applicant in the contentious proceedings,
could not be considered as a continuation, since they and the bankruptcy
proceedings were two separate sets of proceedings, conducted under different
procedural laws. Moreover, the actions of the parties in one set of proceedings
did not have any effect on the other.
In the case of Di Pede v. Italy (26 September
1996, § 22, Reports of Judgments and Decisions 1996-IV), the Court
found that it was not for it to decide on the basis of national law whether the
proceedings in the course of which the applicant tried to enforce his claim
were autonomous; but with reference to the Convention whether, and if so when, the
rights asserted by the applicant actually became effective. The latter moment
therefore constitutes determination of a civil right and therefore a final
decision within the meaning of Article 35 § 1 of the Convention (see Silva
Pontes v. Portugal, 23 March 1994, § 33, Series A no. 286-A).
The Court notes that under Slovenian law, once bankruptcy proceedings are
opened against a company, those proceedings are the only venue for the
creditors to enforce their claims against that company. The Court therefore
considers that in the present case the determination of the applicant’s “civil
rights” within the meaning of Article 6 § 1 of the Convention began in the
contentious proceedings and continued in the bankruptcy proceedings. It would
be only after the final decision in the bankruptcy proceedings that the dispute
over the applicant’s right to reimbursement of the corresponding part of the
purchase price would be resolved (see Sukobljević v. Croatia,
no. 5129/03, § 37, 2 November 2006).
The Government’s objection as to the
inadmissibility of the complaints concerning the contentious proceedings on the
basis of the six-month rule must therefore be dismissed.
3. Conclusion
The Court notes that this part of the application
is not manifestly ill-founded within the meaning of Article 35 § 3 (a) of
the Convention and that it is not inadmissible on any other grounds. It must
therefore be declared admissible.
B. Merits
1. The parties’ submissions
The applicant argued, in particular, that owing to
the delays in the initial contentious proceedings against company I. he would
probably never be able to enforce his claim, since shortly after the Celje
District Court had issued its judgment, bankruptcy proceedings were opened
against company I. These are still pending but it appears that there will be nothing
left in the estate to repay him.
The Government argued that bankruptcy
proceedings were complex and intricate by nature and that in the present case
247 creditors had registered claims. The process of realising the debtor’s
estate was very complex and cumbersome, in particular on account of the difficulties
encountered in selling property; the inadequate management of the debtor
resulting in unclear accounting books; and difficulties in selling shares the
debtor owned in other companies, which were not traded on organised markets.
Furthermore, company I.’s activities were primarily in the construction
industry, which had been particularly affected by the economic crisis in
Slovenia, as were those of its business partners and debtors, which further affected
the ability to monetise the company’s property.
2. The Court’s assessment
The Court considers that the period to be taken
into consideration began on 14 September 1998, when the applicant
instituted proceedings against company I. before the Celje District Court, and has not yet ended. The relevant period has therefore so far lasted fifteen years at
two levels of jurisdiction.
The Court reiterates that the reasonableness of
the length of proceedings must be assessed in the light of the circumstances of
the case and with reference to the following criteria: the complexity of the
case, the conduct of the applicant and the relevant authorities and what was at
stake for the applicant in the dispute (see, among many other authorities, Frydlender
v. France [GC], no. 30979/96, § 43, ECHR 2000-VII).
Applying the criteria separately to the contentious
and the following bankruptcy proceedings, the Court observes that the
contentious proceedings before the Celje District Court were not complex and no
significant delays in that stage in the proceedings can be attributed to the
applicant. But it nevertheless took the court more than three years to schedule
the first hearing, a further year to appoint an expert and altogether more
than five years and six months to deliver a judgment.
As to the bankruptcy proceedings, the Court is
willing to accept that in the present case the number of creditors and the
amount of claims lodged in the proceedings suggest that they were complex, and
numerous procedural steps had to be taken in order to realise I.’s estate,
including lodging civil claims against third parties and selling the assets through
public auctions. The Court however cannot agree with the Government that the
complexity of the proceedings can justify the overall duration of these
proceedings which are, after nine years, still pending. In this context, the
Court reiterates that it is for the State to organise its legal system in such
a way to enable its courts to comply with the requirement of Article 6 §
1 of the Convention (see, mutatis mutandis, Tusa v. Italy,
27 February 1992, § 17, Series A no. 231-D, Jama v. Slovenia,
no. 48163/08, § 36, 19 July 2012).
The Court cannot follow the Government’s argument that the bankruptcy proceedings
in which the applicant tried to enforce a judgment previously given in his
favour were of minor importance to him.
Having examined all the material submitted to
it and having regard to its case-law on the subject (see Čakš v. Slovenia,
no. 33024/02, § 19, 7 December 2006, Jama v. Slovenia, cited
above, § 36), the Court, for the
reasons set out above, considers that in the instant case the overall length of
the proceedings was excessive and failed to meet the “reasonable time”
requirement.
There has accordingly been a breach of Article 6
§ 1.
II. ALLEGED VIOLATION OF ARTICLE 13 OF THE
CONVENTION
The applicant also complained of the absence of effective
domestic remedies in respect of the excessive length of the contentious and the
bankruptcy proceedings, which falls to be examined under Article 13, which reads
as follows:
“Everyone whose rights and freedoms as set forth in [the]
Convention are violated shall have an effective remedy before a national
authority notwithstanding that the violation has been committed by persons
acting in an official capacity.”
A. Admissibility
The Court finds that this complaint is not
manifestly ill-founded within the meaning of Article 35 § 3 (a) of the
Convention and that it is not inadmissible on any other grounds. It must
therefore be declared admissible.
B. Merits
1. The parties’ arguments
The applicant argued that there had not been any
remedy available to him in order to accelerate the proceedings or to obtain
compensation for their undue length. As regards the bankruptcy proceedings, he
submitted that it was impossible to substantiate the supervisory appeals in
such types of proceedings to the extent that they would be allowed and would
lead to some progress in the proceedings. He stressed that the supervisory
appeal he had lodged with the Celje District Court had included all the
elements required by section 5 of the 2006 Act, but it was nevertheless rejected
on procedural grounds.
The Government argued that since the bankruptcy
proceedings had continued after 1 January 2007, the applicant had the remedies
provided for by the 2006 Act at his disposal, which they believed had been proven
to be effective. They maintained that the applicant could have lodged these
acceleratory remedies and that once the bankruptcy proceedings were finally resolved
he could then, provided he had properly exhausted the acceleratory remedies,
submit a claim for just satisfaction under the 2006 Act. They argued that even
though the applicant’s first supervisory appeal had been rejected, he could
have lodged a new and complete supervisory appeal immediately after the service
of the decision rejecting his first supervisory appeal. They further relied on the
domestic decisions concerning supervisory appeals of parties in bankruptcy and
compulsory dissolution proceedings which, in their opinion, confirmed that the
parties in such types of proceedings were aware of the remedies under the 2006
Act.
2. Relevant principles and previous findings of the
Court concerning the effectiveness of remedies with respect to Slovenia
The Court reiterates that Article 13 guarantees
an effective remedy before a national authority for an alleged breach of the
requirement under Article 6 § 1 to hear a case within a reasonable time (see Kudła v. Poland [GC], no.
30210/96, § 156, ECHR 2000-XI).
The Court further reiterates that remedies
available to a litigant at domestic level for raising a complaint about the
length of proceedings are “effective” within the meaning of Article 13 of the
Convention if they “[prevent] the alleged violation or its continuation, or
[provide] adequate redress for any violation that [has] already occurred” (ibid.,
§ 158). Article 13 therefore offers an alternative: a remedy is
“effective” if it can be used either to expedite a decision by the courts
dealing with the case, or to provide the litigant with adequate redress for
delays that have already occurred (ibid., § 159). The same is necessarily true
of the concept of an “effective” remedy within the meaning of Article 35 § 1
(see Mifsud v. France (dec.) [GC], no. 57220/00, ECHR 2002-VIII).
The Court notes that it has found in the case of
Lukenda v. Slovenia (no. 23032/02,
§§47-71, ECHR 2005-X) the remedies for raising a complaint about
the length of proceedings available to the applicants
before the implementation of the 2006 Act ineffective.
In the case of Grzinčič
v. Slovenia (no. 26867/02, 3 May 2007), followed by the
decision in Korenjak v. Slovenia ((dec.)
no. 463/03, 15 May 2007), the Court, basing its conclusions on an
assessment of the legislative provisions of the 2006 Act, found that the
aggregate of remedies provided for in cases involving excessively long
proceedings pending at first and second instance was effective in the sense
that the remedies were, in principle, capable of both preventing the
continuation of the alleged violation of the right to a hearing without undue
delay, and of providing adequate redress for any violation that has already
occurred (Grzinčič, cited above,
§ 98).
. In the subsequent case of Žunič (cited above), the Court
specified that it was indispensable that the proceedings, which had already
lasted a long time, were finally resolved particularly promptly following the
exhaustion of the acceleratory remedies (ibid. § 50). Moreover, it emphasised that
the national authorities should have ensured that the aggrieved party had
prompt access to the compensatory remedy once he or she had made use of the acceleratory
remedies (ibid., §53).
In the case of Jama v. Slovenia (cited
above) the Court found that in the
circumstances of that case both the acceleratory remedies and the compensatory
remedy had proven to be ineffective, since no significant progress had been
made after the applicant had availed himself of the acceleratory remedies, and
he also had not been afforded prompt access to the compensation claim with
respect to damages sustained owing to the unreasonable length of the
proceedings (ibid., §§ 47-49).
3. The present case
The Court notes that while the bankruptcy
proceedings are the continuation of the previous contentious proceedings, they
nevertheless represent a distinct stage of the proceedings with regard to the
remedies available in respect of complaints of undue delay. In this connection,
the Court points out that it has previously assessed the effectiveness of
remedies in cases against Slovenia by distinguishing between different stages
of proceedings or sets of proceedings (see Sirc v. Slovenia, no. 44580/98,
§§ 166-178, 8 April 2008; Blekić v. Slovenia (dec.),
no. 14610/02, §§ 72-85; Robert
Lesjak v. Slovenia, no. 33946/03, §§ 40-53, 21 July 2009; Beguš v. Slovenia,
no. 25634/05, §§ 27-31, 15 December 2011).
(a) Contentious proceedings (Ref. No. P 1179/98)
The Court observes that the contentious
proceedings had terminated on 2 April 2004, hence prior to the
implementation of the 2006 Act. It notes that the
objections and arguments put forward by the Government in cases involving proceedings
terminated before the implementation of the 2006 Act have been rejected in
earlier cases (see Grzinčič, cited above, §§ 75 and 76) and sees no reason to
reach a different conclusion in the present case.
(b) Bankruptcy proceedings (Ref. Nos. St 19/2004 and
St 1349/2008)
The Court observes that creditors in bankruptcy
proceedings, as was the applicant, have very limited possibilities to
participate in them, since, as a general rule, individual creditors do not act
as independent parties to the proceedings, but through an appointed committee of
creditors, if that is established. They are not summoned to hearings and do not
receive court decisions.
The Court notes that the Government have presented
four domestic decisions on supervisory appeals of parties in bankruptcy and
compulsory dissolution proceedings. All four supervisory appeals were however dismissed
as unfounded, since the parties had allegedly failed to give valid reasons as
to why they believed that the courts had been unreasonably delaying the
proceedings.
In view of the above, and in the absence of any
example put forward by the Government which would enable it to reach a
different conclusion, the Court would be reluctant to conclude in the present
case that the applicant had a realistic chance of obtaining sufficient insight into
the proceedings to be able to properly substantiate his supervisory appeal and
succeed with the acceleratory remedies, in order to later be able to obtain access
to a compensatory remedy on account of excessive length of proceedings as
provided for by the 2006 Act.
(c) Conclusion
The Court considers that with
regard to both stages of proceedings there has been a violation of Article 13
on account of the absence of any remedy under domestic law whereby the
applicant could have obtained a ruling upholding his right to have his case
heard within a reasonable time, as set forth in Article 6 § 1. In view of this
conclusion, it also rejects the Government’s objection concerning the
exhaustion of domestic remedies.
III. APPLICATION OF ARTICLE 41 OF THE CONVENTION
Article 41 of the
Convention provides:
“If the Court finds that there
has been a violation of the Convention or the Protocols thereto, and if the
internal law of the High Contracting Party concerned allows only partial
reparation to be made, the Court shall, if necessary, afford just satisfaction
to the injured party.”
A. Damage
The applicant claimed a total of between EUR 23,954
and 47,908 as damages. As regards pecuniary damages, he argued that if the
contentious proceedings had not lasted an unduly long time, bankruptcy
proceedings would not have been instituted against company I. in the meantime
and he would have been able to use enforcement proceedings to enforce the
judgment given in his favour in the contentious proceedings, whereas it now appears
that because of the bankruptcy proceedings there was nothing left in the estate
to repay him.
The Government contested the claim, arguing in
particular that the claimed amount corresponds to the Celje District Court
judgment, plus the respective default interest. In their view, the applicant was
therefore in substance claiming the reimbursement of pecuniary damages only, in
respect of which there had been no causal link between the alleged violation
and the damages sought.
In the absence of any explicit reference by the
applicant that he was claiming pecuniary damages only, the Court cannot follow
the argument of the Government.
The Court cannot speculate on any pecuniary
damages as a result of the overall length of proceedings and therefore rejects
this claim. Nevertheless, the Court considers that the applicant must have
sustained non-pecuniary damage. Ruling on equitable basis, it awards him
EUR 16,000 under that head.
B. Costs and expenses
The applicant made no claim as regards the costs
and expenses incurred before the Court. The Court therefore makes no award
under this head.
C. Default interest
The Court considers it appropriate that the
default interest rate should be based on the marginal lending rate of the
European Central Bank, to which should be added three percentage points.
FOR THESE REASONS, THE COURT UNANIMOUSLY
1. Joins to the
merits the Government’s objection
concerning the exhaustion of domestic remedies and rejects it after the
examination of the merits;
2. Declares the application admissible;
3. Holds that there has been a violation of
Article 6 § 1 of the Convention;
4. Holds that there has been a violation of
Article 13 of the Convention;
5. Holds
(a) that the respondent State is to pay the applicant, within three months from the date on which the judgment becomes final in accordance with
Article 44 § 2 of the Convention, EUR 16,000 (sixteen thousand euros),
plus any tax that may be chargeable, in respect of non-pecuniary damage;
(b) that from the expiry of the above-mentioned
three months until settlement simple interest shall be payable on the above
amount at a rate equal to the marginal lending rate of the European Central
Bank during the default period plus three percentage points;
6. Dismisses the remainder of the applicant’s
claim for just satisfaction.
Done in English, and notified in writing on 24 October 2013,
pursuant to Rule 77 §§ 2 and 3 of the Rules of Court.
Claudia
Westerdiek Mark Villiger
Registrar President