Page: 709↓
(On Appeal from the Court of Appeal in England.)
(Before
Subject_Ship — Charter-party — Construction — Custom of the Port of Hull — Demurrage.
The appellant claimed demurrage under a charter-party, clause 3 of which provided that the cargo was “to be loaded and discharged with customary steamship dispatch as fast as steamer can receive and deliver during the ordinary working hours of the respective
Page: 710↓
ports, but according to the custom of the respective ports. … Should the steamer be detained beyond the time stipulated as above for loading or discharging, demurrage shall be paid at £25 per day.” He maintained that by the custom of the port there was an absolute obligation upon the respondents to provide immediately upon arrival a berth for the ship and facilities for unloading. Held that unless the charter plainly defines the period of time within which delivery of the cargo is to be accomplished such phrases as “with all dispatch” or “as fast as the steamer can deliver” only import an obligation to use all dispatch reasonable under the circumstances of the case.
Decision of the Court of Appeal affirmed.
Appeal from an order of the Court of Appeal reversing an order of the Divisional Court which set aside a judgment of the County Court Judge of Yorkshire.
The proceedings in the Divisional Court, sub nom. the “Lizzie,” are reported 23 Com. C. 332, and in the Court of Appeal, [1919] P. 22.
The s.s. “Lizzie” was chartered to carry wood from Sweden to Hull. By clause 3 of the charter-party the cargo was “to be loaded and discharged with customary steamship dispatch as fast as the steamer can receive and deliver during the ordinary working hours of the respective ports, but according to the custom of the respective ports. … Should the steamer be detained beyond the time stipulated as above for loading or discharging, demurrage shall be paid at the rate of £25 per day and pro rata for any part thereof.”
The ship was fully loaded at Nyhamn under several bills of lading assigned to the respondents separately shortly before the ship arrived at Hull. On 29th September 1915 the ship reached the Humber, but owing to the congestion of the port it was 7th October before she could start discharging. The discharge was completed on 18th October. By the custom of the port of Hull, embodied in a printed statement drawn up in 1899 by a committee of shipowners and timber merchants, it is the duty of the receiver of a cargo of wood at Hull to provide upon her arrival a clear quay space the full length of the vessel and (or) a sufficient and continuous supply of bogies and (or) open lighters alongside. Relying on this custom the appellant asserted that had it been complied with the cargo would have been discharged by 7th October. He therefore claimed 11 days' demurrage. The County Court Judge held that the incorporation of this custom in the charter-party imposed no greater obligation upon the respondents than to use (as he held they had used) their best endeavour to find accommodation. He therefore found in favour of the respondents. The Divisional Court ( Horridge and Hill, JJ.) reversed this decision on the ground that the custom imposed upon the respondents an absolute duty to provide accommodation.
The Court of Appeal reversed that judgment, by Swinfen Eady, M.R., and Warrington, L.J., on the ground that the evidence failed to establish any uniform custom as alleged; by Duke, L. J., on the ground that the custom did not apply to a case where the bills of exchange were held by several receivers.
At delivering judgment—
Since this House decided Hulthen v. Stewart ( [1903] AC 389) it must be taken to be the law that charter-parties fall into two classes. There are some that prescribe a definite time—generally measured by a certain number of days—within which the discharge is to be taken by the charterers. The obligation is in that case an unqualified one, and if the time fixed is exceeded demurrage is payable irrespective of the circumstances, but the charter-party may merely stipulate that the discharge is to be taken “with all dispatch” or “as fast as the vessel can deliver according to the custom of the port,” or may embody language which, as in these expressions, does not either name a period of time or necessarily imply one of an altogether inelastic character. In such a case the liability of the charterer is treated as being only an obligation to take delivery with the utmost dispatch practicable, excluding affection by circumstances not under the control of the charterer. If a liability not qualified in this fashion is to be imposed, the language employed must be definite on the point and free from ambiguity.
The charter-party under construction belongs to the second of these classes. Neither by its terms nor by the custom of the port of Hull as proved at the trial before the learned County Court Judge is a definite and unqualified period of time prescribed within the meaning of the rule of construction as stated. It makes no difference to the general character of the obligation that there is a special clause in the charter-party providing for strikes and epidemics.
This consideration disposes of the argument of the appellants and makes it unnecessary to consider any other point raised.
I think that the appeal ought to be dismissed with costs.
The first point to settle is What was the extent of the admission made at the trial? I hold without hesitation that the defendants through their counsel admitted that there was a custom at Hull in connection with the discharge of wood cargoes, and
Page: 711↓
I think the question is really quite concluded by authority. The only difficulty that has arisen is from the rather uncertain doctrine which was laid down in some of the decided cases, and especially from Wright v. New Zealand Shipping Company ( 1879, 4 Ex. Div. 165). I do not think I should serve any useful purpose by examining and stating the somewhat numerous authorities. I will go at once to the cases in your Lordships' House which in my opinion settle the law. The most recent is Hulthen v. Stewart ( [1903] 3 A.C. 389). That case, as this, contained the obligation for customary discharge according to the custom of the port, which there was also the port of Hull. Indeed, the document there construed was a White Sea wood charter, commonly called Merblanc, which is a sister of the charter in the present case, commonly called Scanfin. The cause of delay was the crowded state of the port. The argument put forward that the normal period of discharge could be expressed in terms of days and then constituted an absolute obligation, was rejected, its having been found as a fact that the charterers had done all that they reasonably could to discharge the vessel and the existence of a strike clause being held to make no difference. The general proposition was laid down by Lord Macnaghten as follows—“It is, 1 think, established that in order to make a charterer unconditionally liable it is not enough to stipulate that the cargo is to be discharged ‘with all dispatch,’ or ‘as fast as the steamer can deliver,’ or to use expressions of that sort. In order to impose such a liability the language used must be in plain and unambiguous terms, define and specify the period of time within which delivery of the cargo is to be accomplished.”
It was just possible here to say that the impediment there was unconnected with the special duty undertaken by the charterers under the custom—namely, to provide bogies. The passage which exactly deals with such a case will be found in the words of Lord Selborne in Postlethwaite v. Freeland ( 5 A.C. 599), where he quotes the words of Lord Blackburn, in Ford v. Cotesworth ( 1868 L.R., 4 Q.B. 127)—“If by the terms of the charter-party the charterer has agreed to discharge it within a fixed period of time that is an absolute and unconditional engagement for the non-performance of which he is answerable, whatever may be the nature of the impediments which prevent him from performing it and which cause the ship to be detained in his service beyond the time stipulated. If, on the other hand, there is no fixed time, the law implies an agreement on his part to discharge the cargo within a reasonable time—that is, as was said by Blackburn, J., in Ford v. Cotesworth, ‘a reasonable time under the circumstances.’ Difficult questions may sometimes arise as to the circumstances which ought to be taken into consideration in determining what time is reasonable. If as in the present case an obligation indefinite as to time is qualified or partially defined by express or implied reference to the custom or practice of a particular port, every impediment arising from or out of that custom or practice which the charterer could not have overcome by the use of any reasonable diligence ought, I think, to be taken into consideration.”
Now that passage from Ford v. Cotesworth was approved and quoted by A. L. Smith, L.J., in Lyle Shipping Company v. Cardiff Corporation ( [19001 2 Q.B. 638), as well as by Lord Selborne in Postlethwaite v. Freeland in this House, and Lord Blackburn in the same case, while naturally adhering to his own view in Ford v. Cotesworth, does, in explaining Ashcroft v. Crow Orchard Company ( 1874 L.R., 9 Q.B. 540), give the only ground on which Wright's case can be supported, namely, the view that on the facts the charterer failed through what he calls a self-imposed inability. That is really viewing the expression “overcome by the use of reasonable diligence,” from, so to speak, the other side, and makes the whole of the cases, if that view of the fact in Wright is taken, consistent. If that view of the facts is not possible, then Wright as an authority must disappear, for we have the dictum in Ford v. Cotesworth approved both by the Court of Appeal and by this House, and the same thing said by Lord Macnaghten again in this House in Hulthen.
It follows that the unreported judgment of the case ( Beatley v. Bryson, Jameson, & Company) decided by Matthew, J., and the
Page: 712↓
For these reasons I am of of opinion that the result reached by the Court of Appeal was right, although I cannot tread the path which they took to reach it.
The appeal should be dismissed.
No such conflict or inconsistency as this exists between the provisions of the bill of lading and the charter-party in the present case. It is untouched by this authority, and the present respondents are therefore bound by the terms of the charter-party. The nature and extent of the duties imposed upon charterers touching the discharge of the cargo from the ships they have chartered are well established.
If by the terms of the charter-party the charterers have agreed to discharge the chartered ship within a fixed period of time that is an absolute and unconditional engagement for the non-performance of which they are answerable, whatever be the nature of the impediments which prevented them from performing it and thereby causing the ship to be detained in their service beyond the time stipulated. If no time be fixed expressly or impliedly by the charter-party the law implies an agreement by the charterer to discharge the cargo within a reasonable time, having regard to all the circumstances of the case as they actually existed, including the custom or practice of the port, the facilities available thereat, and any impediments arising therefrom, which the charterer could not have overcome by reasonable diligence— Postlethwaite v. Freeland, 1880, 5 A.C. 599; Hick v. Raymond and Reid, [1893] AC 22; and Hulthen v. Stewart, [1903] AC 389.
In the last of these three cases the charter-party provided that the cargo was to be “discharged with customary steamship dispatch as fast as the steamer can deliver during the ordinary working hours” of the port of discharge, “but according to the custom” of the port, “Sundays, general or local holidays unless used excepted.” These are very precise and peremptory words, much better calculated to impose an absolute and unconditional obligation than are the words upon which, in my view, the question for decision in the present case turns. Lord Macnaghten held in Hulthen v. Stewart that the meaning of the above-mentioned words was not tantamount to fixing a certain definite number of days or hours as the period within which the discharge of the vessel was to be accomplished. That what the words pointed to was, he said, “the discharge of the cargo with the utmost dispatch practicable, having regard to the custom of the port, the facilities for delivery possessed by the particular vessel, under contract of affreightment, and all other circumstances in existence at the time, not being circumstances brought about by the person whose duty it is to take delivery or circumstances within his control.” The learned Judge who tried the case, Phillimore, J., as he then was, had found as a fact that the respondents had done all they reasonably could to discharge the vessel. In the present case the trial judge has found that the respondents were not responsible for ordering the ship into dock, and that the delay in the discharge of the ship was not due in whole or in part to circumstances over which the defendants or the charterers had control. Having regard to this finding, I think the first question for decision in this case resolves itself into this—Do the words of the written statement of the custom and practice concerning the discharge of steamships laden with wood cargoes existing at the port of Kingston-upon-Hull impose upon the charterers of the ‘Lizzie,’ and also upon the respondents who are bound by the terms of the charter-party, an obligation to discharge this ship as absolute and unconditional in character as if a definite number of days had been fixed for her discharge? It has been contended that they do impose such an obligation
Page: 713↓
I think that contention is unsound. It is not thus that absolute unconditional obligations can be spelt out and imposed. Adopting the words of Lord Macnaghten in the judgment which I have already quoted, I may say that in order to impose the liability contended for the language used “must in plain and unambiguous terms define and specify the period within which delivery of the cargo is to be accomplished.” The language relied upon in this case is not of this character.
I therefore think that the appeal upon this point fails, and that being so it is unnecessary to deal with the second point, namely, the possibility of holding the consignees as liable as one consignee would be. I think the appeal should be dismissed with costs.
Appeal dismissed.
Counsel for the Appellant— Compston. K.C.— Hardy. Agents— Botterell & Roche, Solicitors, for Andrew M. Jackson & Company, Hull.
Counsel for the Respondents— Mackinnon, K.C.— W. H. Owen. Agents— Trinder, Capron, & Company, Solicitors.