H357
Judgment
| ||||||||||||||||
Neutral Citation [2015] IEHC 357 THE HIGH COURT COMMERCIAL [2014 No. 647 JR]
[2014 No. 170 COM] IN THE MATTER OF SECTION 50 OF THE PLANNING AND DEVELOPMENT ACT 2000, AS AMENDED BETWEEN JOHN CALLAGHAN APPLICANT AND
AN BORD PLEANÁLA, IRELAND AND THE ATTORNEY GENERAL RESPONDENTS AND
ELEMENT POWER IRELAND LIMITED, ELEMENT POWER IRELAND AND NORTH MEATH WIND FARM LIMITED NOTICE PARTIES JUDGMENT of Ms. Justice Costello delivered the 11th day of June, 2015 Introduction 2. By order dated 24th November, 2014, McGovern J. entered these proceedings into the Commercial List of the High Court. By order dated 28th January, 2015, McGovern J. directed that the proceedings were to be dealt with by way of a single combined ‘telescoped’ hearing, the court firstly considering the application for leave to apply for judicial review and, if leave is granted, proceeding immediately thereafter to consider the Applicant’s substantive judicial review application. The facts 4. The applicant says that he will be directly affected by the proposed development. His house is situated 4.8km from the nearest of the proposed turbines. He says that a significant number of the proposed turbines will be directly visible from his house on the outskirts of Kells, Co. Meath. He says that the proposed wind turbines are up to 167m high and will affect the health and wellbeing of himself and his family as well as their day to day existence. The applicant says that he is an engineer and he has studied the effects of wind turbines in detail. He describes himself as a noise sensitive person with “many autistic traits”. The applicant is married and resides with his wife with their two sons, aged seven and eight years. Their younger son has been diagnosed with Pervasive Developmental Disorder and attends a special educational unit in Trim, Co. Meath. He is vulnerable to change and is sensitive to noise. The applicant states that his son is afraid of wind farms. The welfare of their children is most understandably a matter of great concern to the applicant and his wife. 5. By letter received by the Board on 30th May, 2014, EPI initiated the pre- application consultation procedure prescribed under s.37B of the Principal Act, as amended, in relation to the proposed Emlagh wind farm project in Co. Meath. Section 37B of the Principal Act, as amended, states that, in respect of certain classes of development which may comprise SID:-
8. The Inspector referred to the employment generation that could be achieved by the proposed development and noted that while there was no breakdown of the figures cited by the prospective applicant of 225 construction jobs and 60 long-term jobs, he concluded at para. 5.2.2 that:-
9. Given the scale of the proposed development, the Inspector considered that the proposed development would be consistent with the objectives of the Renewable Energy Strategy 2012-2020 published in June, 2012, albeit that the policy document was not one which came within the scope of s.37A(2)(b) as it was neither National Spatial Strategy nor Regional Planning Guidelines. The Inspector was satisfied that the proposed development met the conditions in s.37A(2)(b) in terms of contributing to the achievement of the objectives of the National Spatial Strategy or Regional Planning Guidelines. 10. At its meeting on 11th September, 2014, the Board considered the Inspector’s report, together with the documents and submissions of EPI on file and issued a Board Direction:-
The Board determined that the proposed development would comprise strategic infrastructure development, generally in accordance with the Inspector’s recommendation and conclusions. The Board was satisfied that there was no potential for transboundary impacts to occur in relation to the proposed development, having regard to its nature, scale and location in relation to Northern Ireland. The list of recommended bodies for consultation is noted.”
12. Following the SID designation, an application for planning permission was made to the Board by the Third Named Notice Party on 6th October, 2014. The applicant has made no submissions or observation on that application since it was lodged on 6th October, 2014. 13. The decision that is impugned by the applicant in these proceedings is the Board’s decision that the proposed Emlagh wind farm development is SID within the meaning of s.37A of the Principal Act, as amended. Relevant statutory provisions
(2) That condition is that, following consultations under section 37B, the Board serves on the prospective applicant a notice in writing under that section stating that, in the opinion of the Board, the proposed development would, if carried out, fall within one or more of the following paragraphs, namely— (a) the development would be of strategic economic or social importance to the State or the region in which it would be situate, (b) the development would contribute substantially to the fulfilment of any of the objectives in the National Spatial Strategy or in any regional planning guidelines in force in respect of the area or areas in which it would be situate, (c) the development would have a significant effect on the area of more than one planning authority. (3) In subsection (2) ‘prospective applicant’ means the person referred to in section 37B(1).”
(2) Such a person is referred to subsequently in this section and in sections 37C and 37D as a ‘prospective applicant’. (3) In any consultations under subsection (1), the Board may give advice to the prospective applicant regarding the proposed application and, in particular, regarding— (a) whether the proposed development would, if carried out, fall within one or more of paragraphs (a) to (c) of section 37A(2), (b) the procedures involved in making a planning application and in considering such an application, and (c) what considerations, related to proper planning and sustainable development or the environment, may, in the opinion of the Board, have a bearing on its decision in relation to the application. (4) Where, following consultations under this section, the Board is of the opinion that the proposed development would, if carried out— (a) fall within one or more of paragraphs (a) to (c) of section 37A(2), it shall serve a notice in writing on the prospective applicant stating that it is of that opinion, or (b) not fall within any of those paragraphs, it shall serve a notice in writing on the prospective applicant stating that it is of that opinion. (5) A notice under subsection (4)(b) shall include a statement that the prospective applicant’s application for permission, if it is proceeded with, must be made to the appropriate planning authority (and such an application, if it is proceeded with, shall be made to that planning authority accordingly). (6) The Board shall serve a copy of a notice under subsection (4)(a) or (b), as the case may be, on the appropriate planning authority. (7) No application for permission in respect of a development referred to in subsection (1) shall be made to a planning authority unless or until a notice is served under subsection (4)(b) in relation to the development. (8) In this section ‘appropriate planning auth ority ’ means whichever planning authority would, but for the enactment of section 3 of the Planning and Development (Strategic Infrastructure) Act 2006, be the appropriate planning authority to deal with the application referred to in subsection (1).”
(2) The holding of consultations under section 37B shall not prejudice the performance by the Board of any other of its functions under this Act or regulations under this Act and cannot be relied upon in the formal planning process or in legal proceedings. (3) The Board shall keep a record in writing of any consultations under section 37B in relation to a proposed development, including the names of those who participated in the consultations, and a copy of such record shall be placed and kept with the documents to which any planning application in respect of the proposed development relates. (4) The Board may consult with any person who may, in the opinion of the Board, have information which is relevant for the purposes of consultations under section 37B in relation to a proposed development.”
(2) On receipt of such a request the Board shall— (a) consult with the requester and such bodies as may be specified by the Minister for the purpose, and (b) comply with the request as soon as is practicable. (3) A prospective applicant shall, for the purposes of the Board’s complying with a request under this section, supply to the Board sufficient information in relation to the proposed development so as to enable the Board to assess the proposed development. (4) The provision of an opinion under this section shall not prejudice the performance by the Board of any other of its functions under this Act or regulations under this Act and cannot be relied upon in the formal planning process or in legal proceedings.”
(2) The Board may refuse to deal with any application made to it under this section where it considers that the application for permission or the environmental impact statement is inadequate or incomplete, having regard in particular to the permission regulations and any regulations made under section 177 or to any consultations held under section 37B. (3) Before a person applies for permission to the Board under this section, he or she shall— (a) publish in one or more newspapers circulating in the area or areas in which it is proposed to carry out the development a notice indicating the nature and location of the proposed development and— (i) stating that— (I) the person proposes to make an application to the Board for permission for the proposed development, (II) an environmental impact statement has been prepared in respect of the proposed development, and (III) where relevant, the proposed development is likely to have significant effects on the environment of a Member State of the European Communities or other party to the Transboundary Convention, (ii) specifying the times and places at which, and the period (not being less than 6 weeks) during which, a copy of the application and the environmental impact statement may be inspected free of charge or purchased on payment of a specified fee (which fee shall not exceed the reasonable cost of making such copy), (iii) inviting the making, during such period, of submissions and observations to the Board relating to— (I) the implications of the proposed development for proper planning and sustainable development, and (II) the likely effects on the environment of the proposed development, if carried out, and (iv) specifying the types of decision the Board may make, under section 37G, in relation to the application, (b) send a prescribed number of copies of the application and the environmental impact statement to the planning authority or authorities in whose area or areas the proposed development would be situated, (c) send a prescribed number of copies of the application and the environmental impact statement to any prescribed authorities together with a notice stating that submissions or observations may, during the period referred to in paragraph (a)(ii), be made in writing to the Board in relation to— (i) the implications of the proposed development for proper planning and sustainable development, and (ii) the likely effects on the environment of the proposed development, if carried out, and (d) where the proposed development is likely to have significant effects on the environment of a Member State of the European Communities or a state which is a party to the Transboundary Convention, send a prescribed number of copies of the application and the environmental impact statement to the prescribed authority of the relevant state or states together with a notice stating that submissions or observations may, during the period referred to in paragraph (a)(ii), be made in writing to the Board.”
(2) Without prejudice to the generality of subsection (1), the Board shall consider— (a) the environmental impact statement submitted under section 37E(1), any submissions or observations made, in response to the invitation referred to in section 37E(3), within the period referred to in that provision, the report (and the recommendations and record, if any, attached to it) submitted by a planning authority in accordance with section 37E(4), any information furnished in accordance with section 37F(1) and any other relevant information before it relating to—
(ii) the likely effects on the environment of the proposed development, (c) the provisions of the development plan or plans for the area, (d) the provisions of any special amenity area order relating to the area, (e) if the area or part of the area is a European site or an area prescribed for the purposes of section 10(2)(c), that fact, (f) if the proposed development would have an effect on a European site or an area prescribed for the purposes of section 10(2)(c), that fact, (g) the matters referred to in section 143, (h) any relevant provisions of this Act and of any regulations made under this Act. (3) The Board may, in respect of an application under section 37E for permission— (a) decide—
(ii) to make such modifications to the proposed development as it specifies in its decision and grant permission in respect of the proposed development as so modified, or (iii) to grant permission in respect of part of the proposed development (with or without specified modifications of it of the foregoing kind), (b) decide to refuse to grant the permission, and a decision to grant permission under paragraph (a)(i), (ii) or (iii) may be subject to or without conditions.”
(a) consultations under section 37B, (b) the giving of an opinion under section 37D, (c) applications for permission under section 37E, and (d) decisions under section 37G.”
(a) a planning authority, a local authority or the Board in the performance or purported performance of a function under this Act, (b) the Board in the performance or purported performance of a function transferred under Part XIV, or (c) a local authority in the performance or purported performance of a function conferred by an enactment specified in section 214 relating to the compulsory acquisition of land, otherwise than by way of an application for judicial review under Order 84 of the Rules of the Superior Courts ( S.I. No. 15 of 1986 ) (the ‘Order’).”
(a) the policies and objectives for the time being of the Government, a State authority, the Minister, planning authorities and any other body which is a public authority whose functions have, or may have, a bearing on the proper planning and sustainable development of cities, towns or other areas, whether urban or rural, (b) the national interest and any effect the performance of the Board’s functions may have on issues of strategic economic or social importance to the State, and (c) the National Spatial Strategy and any regional planning guidelines for the time being in force.”
(6) General principles for the assessment of environmental effects should be laid down with a view to supplementing and coordinating development consent procedures governing public and private projects likely to have a major effect on the environment. (7) Development consent for public and private projects which are likely to have significant effects on the environment should be granted only after an assessment of the likely significant environmental effects of those projects has been carried out. That assessment should be conducted on the basis of the appropriate information supplied by the developer, which may be supplemented by the authorities and by the public likely to be concerned by the project in question… (14) The effects of a project on the environment should be assessed in order to take account of concerns to protect human health, to contribute by means of a better environment to the quality of life, to ensure maintenance of the diversity of species and to maintain the reproductive capacity of the ecosystem as a basic resource for life... (16) Effective public participation in the taking of decisions enables the public to express, and the decision-maker to take account of, opinions and concerns which may be relevant to those decisions, thereby increasing the accountability and transparency of the decision-making process and contributing to public awareness of environmental issues and support for the decisions taken (17) Participation, including participation by associations, organisations and groups, in particular non-governmental organisations promoting environmental protection, should accordingly be fostered, including, inter alia, by promoting environmental education of the public… (19) Among the objectives of the Aarhus Convention is the desire to guarantee rights of public participation in decision-making in environmental matters in order to contribute to the protection of the right to live in an environment which is adequate for personal health and well-being.”
(c) ‘development consent’ means the decision of the competent authority or authorities which entitles the developer to proceed with the project;… (f) ‘competent authority or authorities’ means that authority or those authorities which the Member States designate as responsible for performing the duties arising from this Directive.”
“2. The environmental impact assessment may be integrated into the existing procedures for consent to projects in the Member States, or, failing this, into other procedures or into procedures to be established to comply with the aims of this Directive.”
(a) human beings, fauna and flora; (b) soil, water, air, climate and the landscape; (c) material assets and the cultural heritage; (d) the interaction between the factors referred to in points (a), (b) and (c).”
(a) the Member States consider that the information is relevant to a given stage of the consent procedure and to the specific characteristics of a particular project or type of project and of the environmental features likely to be affected; (b) the Member States consider that a developer may reasonably be required to compile this information having regard, inter alia, to current knowledge and methods of assessment. 2. Member States shall take the necessary measures to ensure that, if the developer so requests before submitting an application for development consent, the competent authority shall give an opinion on the information to be supplied by the developer in accordance with paragraph 1. The competent authority shall consult the developer and authorities referred to in Article 6(1) before it gives its opinion. The fact that the authority has given an opinion under this paragraph shall not preclude it from subsequently requiring the developer to submit further information. Member States may require the competent authorities to give such an opinion, irrespective of whether the developer so requests. 3. The information to be provided by the developer in accordance with paragraph 1 shall include at least: (a) a description of the project comprising information on the site, design and size of the project; (b) a description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects; (c) the data required to identify and assess the main effects which the project is likely to have on the environment; (d) an outline of the main alternatives studied by the developer and an indication of the main reasons for his choice, taking into account the environmental effects; (e) a non-technical summary of the information referred to in points (a) to (d). 4. Member States shall, if necessary, ensure that any authorities holding relevant information, with particular reference to Article 3, make this information available to the developer.”
(a) the request for development consent; (b) the fact that the project is subject to an environmental impact assessment procedure and, where relevant, the fact that Article 7 applies; (c) details of the competent authorities responsible for taking the decision, those from which relevant information can be obtained, those to which comments or questions can be submitted, and details of the time schedule for transmitting comments or questions; (d) the nature of possible decisions or, where there is one, the draft decision; (e) an indication of the availability of the information gathered pursuant to Article 5; (f) an indication of the times and places at which, and the means by which, the relevant information will be made available; (g) details of the arrangements for public participation made pursuant to paragraph 5 of this Article… 4. The public concerned shall be given early and effective opportunities to participate in the environmental decision- making procedures referred to in Article 2(2) and shall, for that purpose, be entitled to express comments and opinions when all options are open to the competent authority or authorities before the decision on the request for development consent is taken.”
(a) a description of the project, together with any available information on its possible transboundary impact; (b) information on the nature of the decision which may be taken. The Member State in whose territory the project is intended to be carried out shall give the other Member State a reasonable time in which to indicate whether it wishes to participate in the environmental decision-making procedures referred to in Article 2(2), and may include the information referred to in paragraph 2 of this Article.”
(a) the interpretation of the Treaties; (b) the validity and interpretation of acts of the institutions, bodies, offices or agencies of the Union; Where such a question is raised before any court or tribunal of a Member State, that court or tribunal may, if it considers that a decision on the question is necessary to enable it to give judgment, request the Court to give a ruling thereon. Where any such question is raised in a case pending before a court or tribunal of a Member State against whose decisions there is no judicial remedy under national law, that court or tribunal shall bring the matter before the Court. If such a question is raised in a case pending before a court or tribunal of a Member State with regard to a person in custody, the Court of Justice of the European Union shall act with the minimum of delay.” 31. The decision ought to be quashed on a number of grounds. At the hearing of the application, the applicant confined himself to the following grounds:-
(2) The applicant submits that the merits of the decision of the Board cannot be revisited either legally or practically. There is no appeal on the merits. Section 50 of the Principal Act, as amended, says that the validity of the decision can only be challenged by way of judicial review. That is what is occurring here and it is not a review of the merits of the decision. (3) The applicant submits that if that is not legally correct, there is in fact no practical reality to revisiting the merits of that decision. The Board has considered certain matters in determining that the proposed development, if carried out, would be of strategic economic or social importance. This involves reaching a decision in respect of certain matters which would fall within the remit the Environmental Impact Assessment (“EIA”) which it will be obliged to carry out in respect of the application for planning permission for the development. It is argued that any suggestion that it could revisit this decision would leave the Board open to an allegation of a perception of bias in the sense of prejudgment of the issue. (4) In reaching its decision under s.37A the Board failed to have regard to relevant matters which it ought to have considered and its decision is therefore irrational within the meaning of O’Keeffe v. An Bord Pleanála [1993] 1 I.R. 39. (5) The applicant also argues that the decision has both substantive and procedural effects. It has a substantive effect in domestic law therefore the applicant is entitled to fair procedures. Insofar as it has procedural effect, cumulatively, these are significant and give rise to a right to fair procedures. He has not been afforded an opportunity to be heard before the Board made its decision. Accordingly the decision should be quashed. (6) The applicant argues that the State has failed properly to transpose the Directive into Irish Law as the procedure mandated by s.37A fails to ensure that there is effective public participation in the decision-making process at a time when all options are still open to the decision-maker. 32. In relation to the domestic law, the argument is that at the pre-application consultation stage the Board has reached a decision that the development, if carried out, would be of strategic economic or social importance and that it would contribute substantially to the fulfilment of the objectives in relation to spatial strategy and regional guidelines. These are precisely matters which fall to be considered by the Board in conducting an EIA and then deciding whether to grant or to refuse permission (or to grant permission subject to conditions). The argument is that at the conclusion of the pre-application stage when the Board issues a notice under s.37B(4) it has reached a conclusion on a matter to which it is obliged to have regard at a later stage in the consent process. It does so in circumstances where the public have no entitlement to participate in the pre-application stage. It is said that this breaches the requirement to afford him fair procedures. 33. The applicant argues that he is entitled to fair procedures in relation to this application for planning permission. He relies on the Supreme Court decision in Dellway Investments Ltd. v. NAMA [2011] 4 I.R. 1. The Supreme Court addressed the issue as to when a person is entitled to a hearing and what triggers the right to fair procedures. Hardiman J. held at para. 301 that the trigger for fair procedures is that the person claiming them is a person “affected” by the decision. At para. 313 he cited with approval from Hogan & White, J.M. Kelly: The Irish Constitution (4th ed. 2003, Tottel) at para. 6.1.52:-
35. Fennelly J. held that a person whose interests are capable of being affected by a decision is entitled to fair procedures (see para. 434). At para. 460 Fennelly J. continued:-
38. The second argument advanced by the applicant is that the decision under s.37B(4) involves a decision by the Board that the development is either strategic economically or socially important to the State or region. He argues that this is a binding decision as it cannot be revisited. Section 50(2) of the Principal Act, as amended, states:-
(b) the Board in the performance or purported performance of a function [under the Act]… otherwise and by way of an application for judicial review…”
(b) The development would contribute substantially to the fulfilment of any of the objectives in the National Spatial Strategy or in any regional planning guidelines in force in respect of the area or areas in which it would be situate, (c) The development would have a significant effect on the area of more than one planning authority.” 41. Once the application for planning permission is submitted to the Board it then must conduct an EIA and is expressly mandated to have regard to matters set out in s.143 of the Principal Act, as amended. These are:-
(b) the national interest and any effect the performance of the Board’s functions may have on issues of strategic economic or social importance to the State, and (c) the national spatial strategy and any regional planning guidelines for the time being in force.” 43. The applicant’s case is that the statutory scheme requires the Board to reach a decision in relation to certain factors if it is to hold that proposed development may be SID and it does so after consultation with the developer from which the public is excluded. Then, when conducting the EIA and determining the application for planning permission it has to consider and have regard, inter alia, to certain of those factors upon which it has already reached a decision i.e. whether the development is of strategic economic or social importance. He argues, firstly, that the Board cannot itself, as a matter of law, change its decision in relation to these matters by reason of the provisions of s.50 and therefore these matters have been determined without the participation of the public. 44. Secondly, even if the Board legally could change its decision, as a matter of fact there is an unavoidable appearance of predetermination in respect of some of the matters which it must consider in deciding whether or not to grant the permission sought. In this regard the applicant relies upon the decision of the Supreme Court in Tomlinson v. Criminal Injuries Compensation Tribunal [2006] 4 IR 321. In that case the applicant applied to the respondent for compensation. The respondent, by way of a single member decision, decided that the scheme applied to the applicant and made an award but deducted the sum of stg£592,000.00 in respect of insurance paid out upon the death of the applicant’s husband. The applicant believed that the deduction was improperly made. Under the scheme there was a right of appeal to a three-member tribunal of the respondent. The applicant chose to seek judicial review of the decision instead. In opposing the application for judicial review the respondent pleaded that it was entitled to make the deduction. Denham J. pointed out that this involved the respondent addressing the substantial issue in the case i.e. the entitlement of the respondent to make the deduction. At para. 18 she held:-
46. The applicant argues that in the circumstances of the scheme mandated by the Principal Act, as amended, in relation to SIDs, it is unavoidable that there is a form of predetermination. It is argued that it is not possible to cure the perception of bias and therefore on this separate ground, the decision of the Board should be quashed. It is argued that the statutory scheme requires that the developer gets very close to the Board. This is no criticism of the performance by the Board of its functions. However, the fact that the Board reaches its decision after getting so close to the developer, due to the mandatory requirements of the statutory scheme exacerbates the bias problem, according to the applicant. 47. Separately, the applicant pointed to the fact that the prospective applicant for planning permission in fact provided very little information to the Board relating to the strategic economic and social importance allegedly attaching to the proposed development. He points to the information which he has adduced in the application for judicial review: the affidavit of Mr. Noel Meade in relation to the possible negative effects of the proposed development on the bloodstock industry and employment in the bloodstock industry in the locale of the proposed wind farm, the affidavit of Mr. Colm McCarthy, economist, in relation to the role of wind farms in the context of the State’s targets for renewable energy and the affidavit of Mr. Bernard Allen of the GAA in relation to the alleged social benefits that would accrue from the proposed development. None of this information was before the Board when it reached its decision pursuant to s.37B(4). It is argued that this amounts to a failure to have regard to relevant material and that the decision should be quashed as being irrational within the meaning of O’Keeffe v. An Bord Pleanála. 48. The applicant submitted that the decision pursuant to s.37B had procedural effects of considerable significance. The notice requirements were less onerous, for example there was no obligation to erect a site notice in respect of an application for permission to develop strategic infrastructure. The nature and extent of the plans and documents lodged by the prospective applicant can be the subject matter of discussion and agreement between the applicant and the Board. The Board is authorised by s.37G(3)(a)(ii) to make modifications to the proposed development and to grant permission in respect of the proposed development as so modified. There is no appeal to the Board. The Board may give advice and guidance in respect of the application for permission to the applicant. The Board has a wider power to grant permission that is in material contravention of the development plan than does a planning authority. It is argued that cumulatively the procedural effects are such as to entitle the applicant to fair procedures and to afford him a right to be heard in relation to the decision as to whether or not the application should be designated SID. Transposition of the Directive into Irish law 50. The applicant relies upon the decision of the European Court of Justice (“ECJ”) in the case of C-416/10 Križan and Others v. Slovenská inšpekcia životného prostredia. The case concerned a two-stage procedure for the grant of permission for a landfill development. At the first decision stage, the public was not informed of the location of the proposed landfill. The Court had to consider whether or not the procedures adopted by the Member State satisfied the requirements of the Directive. At paras. 89-90 of the judgment the Court held:-
90 Consequently, the principle of effectiveness does not preclude the possibility of rectifying, during the administrative procedure at second instance, an unjustified refusal to make available to the public concerned the urban planning decision at issue in the main proceedings during the administrative procedure at first instance, provided that all options and solutions remain possible and that rectification at that stage of the procedure still allows the public effectively to influence the outcome of the decision-making process, this being a matter for the national court to determine.” 52. Secondly, and separately, it is argued that it also means that the Board in effect is making a decision on the socio-economic aspects of an EIA. In order to comply with the requirements of the Directive this means that the Board must have all information relevant to this aspect of the decision before it, not just the information provided by the prospective applicant. It must make all of this information available to the public and it must afford the public the opportunity to participate in this aspect of the EIA. None of this occurs under the Irish procedure. It is no answer to say that it will occur subsequently in the process. The applicant rejects the argument that the Directive is not engaged until the application for planning permission is submitted. He says this is all one process and therefore the Directive applies from the beginning of the process. Furthermore, it is clear that the Directive is engaged as the decision of the Board itself actually refers to the transboundary effects of the proposed development. This decision in relation to transboundary effects derives from Article 7 of the Directive. It therefore follows that the Directive is engaged at this pre-application stage. 53. The applicant relies on the case C-201/02 R (Wells) v. Secretary of State for Transport which concerned the time at which an EIA must be carried out in the context of the consent procedure comprising several stages. The Court held that the effects which the project may have on the environment must be identified and assessed at the time of the procedure relating to the principal decision. At para. 53 the Court held:-
55. The final case relied upon by the applicant is the case of C-50/09 Commission v. Ireland. In that case the Commission alleged that Ireland had failed to transpose the Directive correctly. It identified a gap in the implementation of the Directive arising from two factors. The first was the lack of any right on the part of the Environmental Protection Agency (“EPA”) where it received an application for a licence for a project as regards pollution aspects to require an EIA. The second was the possibility that the EPA might receive an application and decide on questions of pollution before an application was made to a planning authority which alone could require the developer to make an environmental impact statement (“EIS”). The Court pointed out that Ireland had neither established nor even alleged that it was legally impossible for a developer to obtain a decision from the EPA where he had not also applied to the planning authority for permission. It held:-
57. The applicant argues that the Directive is engaged at this pre-consultation stage. The consultation between the Board and the developer is far wider than the consultation that occurs under s.37D or s.135 of the Principal Act, as amended. The Board is entitled to give advice under s.37B(3), including advice on what considerations, related to proper planning and sustainable development or the environment may, in the opinion of the Board, have a bearing on its decision in relation to the application for planning permission. This is to be contrasted with the more limited role of the Board in s.37D which permits the Board to give an opinion in writing on what information will be required to be contained in the EIS in relation to the development. This, it is said, is unobjectionable and reflects the requirements of the Directive. The applicant says that there is an overlap between the matters considered by the Board in determining whether or not the proposed development constituted SID and matters which are required to be considered in the course of an EIA. It is said that the Directive requirement for participation by the public at the earliest possible stage in the procedure is not met when the decision-maker has already reached a conclusion on some of the matters it has to consider as part of the EIA. It is the applicant’s argument that as a result the State has failed properly to transpose the Directive. Sections 37A and 37B are mandatory procedures which fail to satisfy the public participation requirements of the Directive. It is insufficient to argue that the public may participate at a later stage in the process prior to the making of the decision. 58. Finally, the applicant urged that the Court may wish to consider whether or not it is necessary to refer the matter of the transposition of the Directive into Irish law for an opinion to the Court of Justice of the European Union (“CJEU”). I consider this aspect of the matter below. Discussion Leave 60. It has long been established that the test to be applied is that annunciated by Carroll J. and subsequently approved by the Supreme Court in McNamara v. An Bord Pleanála (No.1) [1995] 2 I.L.R.M. 125 at p. 130:-
The decision 62. Section 37B(4) requires the Board to form an opinion as to whether the proposed development if carried out will fall or will not fall within one or more of:-
(b) the development would contribute substantially to the fulfilment of any of the objectives in the National Spatial Strategy or in any regional planning guidelines in force in respect of the area or areas in which it would be situate, (c) the development would have a significant effect on the area of more than one planning authority.” 63. Once it has made its decision it notifies the applicant pursuant to s.37B(4). The applicant then submits its application for planning permission either to the Board, if it has designated the application to be SID, or to the appropriate planning authority, if it has not. The Board or the planning authority is the competent authority for the purpose of the Directive and must carry out an EIA. Assuming that the Board has designated the proposed application to be SID, the Board and the applicant must follow the procedures mandated in ss.37D-H. In particular the Board is obliged by law to have regard to all of the additional information provided to it as part of the Article 3 assessment and s.171A of the Principal Act, as amended. This includes input from the statutory bodies, all submissions and observations of the public, submissions from the planning authority for the relevant area and the EIS provided by the applicant for planning permission. Once it has completed the EIA, the Board must then make a decision on the consent application. 64. When making a decision pursuant to s.37G the Board is deciding whether or not to grant or refuse permission or whether to make modifications to the proposed development or to grant permission in respect of part of the proposed development or to grant permission in respect of part of the proposed development (with or without specified modifications). This is a different decision for a different purpose based on far more extensive information that it is obliged to consider than the SID designation decision. The Board is viewing the entire application and assessing whether or not in the exercise of its planning expertise the proposed development (with or without modifications) complies with requirements of the proper planning and sustainable development of the area and is a development to which planning permission should be granted. 65. The difference between the two decisions is clear. It is perfectly possible that a proposed development could be considered to be of strategic economic or social importance if carried out but, due to its location for example, the Board might, in the exercise of its expert judgment, decide that it should refuse planning permission. It could do so on the grounds that the particular project in that location would not accord with proper planning and sustainable development. It may be that the application is premature, given the state of existing infrastructure which might be inadequate to meet the requirements of the proposed development or it might be inappropriate given the density of the housing in the immediate environs. There could be any number of reasons why the Board could validly form the opinion that a proposed application was of strategic economic or social importance but, upon considering all of the matters and information before it both during the EIA and thereafter, that the negative factors including those relating to the strategic economic or social importance aspects of the application outweighed the benefits presented by the applicant in its pre-application to the Board pursuant to s.37B. I therefore cannot accept the applicant’s central submission that the designation of the proposed application as SID in any way predetermines the outcome or any part of the outcome of either the EIA or the application for planning permission. This accords with the reasoning of Finlay Geoghegan J. in Kelly v. An Bord Pleanála [2014] IEHC 400 in relation to the effect of an EIA. She stated at para. 33:-
66. In this case, as a matter of law, the Board is obliged to consider all matters set out in s.37G. This includes the EIS, any submissions or observations made to it relating to the implications of the proposed development for proper planning and sustainable development and the likely effects on the environment of the proposed development and the other matters set out in s.37G(2). As pointed out by the applicant, this refers to the matters set out in s.143 of the Principal Act, as amended, which includes the national interest and any effect the performance of the Board’s functions may have on issues of strategic economic or social importance to the State and the National Spatial Strategy and any regional planning guidelines for the time being in force. In this instance the prospective applicant submitted as part of its s.37B submission to the Board that the proposed development would, if carried out, create 225 construction jobs and 60 long term jobs. However it is perfectly possible that submissions and observations made by third parties including the public and other interested parties might be submitted which could show that other jobs might be lost. In this regard the affidavit of Mr. Meade is relevant. To take a hypothetical case, if a prospective applicant indicates that a proposed development has the potential to create 200 jobs and, inter alia, on that basis the Board forms the opinion that the proposed development would if carried out be of strategic economic or social importance, it is possible that observations or submissions to the effect that the proposed development might result in the loss of 500 jobs could be sent to the Board. The Board could not ignore these hypothetical submissions and it must therefore in exercising its expertise and reaching a decision pursuant to s.37G weigh up the submissions made by the applicant for planning permission and the other information submitted to it as part of the planning process. It cannot be said that the Board has prejudged the issue and definitively concluded that the proposed development is of strategic economic or social importance. It must make its concluded decision on the basis of the fuller information which will be available to it when it comes to make the consent decision. 67. I reject the argument that, as a matter of law, the Board cannot revisit the s.37B(4) opinion. Firstly, as a matter of law, it is obliged to reconsider the material it considered in forming the opinion when determining the consent decision. Secondly, on a strict construction of the section, the s.37B opinion is that: an opinion of the Board that the proposed development would, if carried out fall within one of the categories set out in s.37A(2). It is an opinion not a concluded decision. 68. Thirdly, s.50 of the Principal Act, as amended, states that a person shall not question the validity of any decision made or other act done by the Board in the performance or purported performance of a function under the Act otherwise than by way of an application for judicial review under O.84 of the Rules of the Superior Courts. In deciding whether or not to grant or refuse planning permission or to grant planning permission subject to modifications pursuant to s.37G, the Board would not be questioning the validity of its s.37B(4) decision in any way. The Board would be looking at the same material and any other material submitted by the developer, other agencies, the EPA and the public to reach a fundamentally different decision. The decision is whether or not to grant planning permission. This must be made on the basis that it accords with proper planning and sustainable development in the area. It is not a decision as to whether or not a proposed development would, if carried out, be of strategic economic or social importance to the State. 69. As a matter of law the Board is entitled to look again at the material that was submitted by the applicant for planning permission at the pre-application stage in conjunction with all the additional information then available to the Board to reach a different decision in relation to the social and/or economic aspects of the proposed development as it is in the context of a different decision. Fair procedures 70. Put in this way the answer becomes clear. In order to preserve and protect the applicant’s right to participate in and affect the outcome of the planning application process, it is not necessary that the applicant be entitled to be heard at the pre-application stage set out in s.37B. This is because the pre-application decision is not legally a predetermination of anything to be decided by the Board pursuant to s.37G. The rights are triggered when the application for planning permission is submitted and the statutory scheme clearly protects those rights from that point in time. 71. The fact that the Board consults with or advises a developer at the pre-application stage without the involvement of the public does not alter this and of itself does not trigger the applicant’s rights to fair procedures as set out in Dellway. 72. In my judgment, the decision pursuant to s.37B does not trigger the rights contended for as the decision does not have the substantive effect contended by the applicant. 73. The decision of the Board pursuant to s.37B has procedural effects. If it reaches a decision that the proposed development does not fall within the SID criterion then the Board serves a notice in writing on the prospective applicant stating this opinion and the subsequent application for planning permission is made to the appropriate planning authority. If, on the other hand, the Board forms the opinion that the matter falls within one or more of subparas. (a) to (c) of s.37A(2) then the notice served by the Board requires the prospective developer to submit the application for planning permission directly to the Board. In the latter case, there are resulting procedural differences from the planning application that is first considered by a planning authority. Most significantly, there is no appeal to the Board. There are different provisions in relation to material contravention of the development plan; different requirements in relation to notice of the proposed development; the nature and extent of the plans and documents the applicant for planning permission is required to lodge are different; and the Board is entitled to consult with the applicant to a greater extent and to modify the plans. This is a synopsis of the more significant effects referred to by the applicant. He argues that taken together they have a significant impact upon his interests and therefore he should be entitled to fair procedures before the decision is taken which results in these procedural effects. 74. Whether or not the procedural effects of the decision are such as to trigger a right to fair procedures as set out in Dellway is a matter of degree. In considering this issue it is important to bear in mind the interest or right of the applicant which is required to be protected. In this instance it is the right to participate effectively in the planning process. In my opinion the procedural effects of the decision do not impair or curtail the applicant’s right to participate in the process in a manner such as to trigger not only his but all and any member of the public’s right to fair procedures. Indeed he does not make the case that he has actually been hindered in any way from participating in the planning process by reason of the procedural effects of the decision of the Board he seeks to quash. His case is advanced on a theoretical basis only as he has elected not to make any submission or objection to the Board and there is evidence on affidavit that he was aware of the planning application and could presumably therefore have voiced his concerns to the Board within the time allowed for submissions if he wished. Predetermination 76. The debate in Tomlinson took place in the context of the Court’s exercise of its discretion where there were alternative remedies of appeal and judicial review. In the circumstances the Supreme Court held that the more appropriate remedy was judicial review and remitted the matter to the High Court for judicial review. This authority is not of assistance in considering whether there is a perception of bias in the form of predetermination of necessity in all cases dealt with under the statutory procedure provided for in ss.37A-H of the Principal Act, as amended. The applicant’s argument is one of principle rather than fact specific. Therefore this is what he must establish to succeed on this point. 77. In my opinion the cases of Dublin and County Broadcasting Limited v. Independent Radio and Television Commission (Unreported, High Court, Murphy J., 12th May, 1989) and Spin Communications Ltd. v. Independent Radio and Television Commission [2000] IEHC 128 are of more relevance. The test there established is that the question of bias must be determined on the basis of what a right-minded person would think of the real likelihood of prejudice and not on the basis of a suspicion which might dwell in the mind of a person who is ill-informed and who did not seek to direct his mind properly to the facts. Applying this test, it cannot be said that such a reasonable, well informed person would reach the conclusion that the Board was biased and had predetermined the planning consent application on the basis of its s.37B opinion. 78. In this case, the Board’s decision pursuant to s.37B(4) is not determinative of the socio-economic aspects of the application for planning permission and the decision it has to make pursuant to s.37G. The Board will revisit some of the material which it considered in the context of the s.37B decision when reaching the different decision required of it pursuant to s.37G. In addition, of course, at this stage the applicant and others will have had full opportunity to present such information or arguments to the Board in relation to this aspect and other aspects of the application for planning permission as they see fit. This applies in all applications under the scheme. These matters must be considered by the Board when exercising its discretion in respect of the application for planning permission. In these circumstances I do not accept that it can fairly be argued that every case which goes before the Board pursuant to the statutory scheme must appear tainted by bias and predetermination. As the applicant’s case is based on the statutory scheme and not on any particular facts, I am not persuaded by this argument. 79. Furthermore, the logic of the applicant’s argument is that, regardless of opinion of the Board on the s37B issue, the statutory scheme would inevitably and automatically disqualify the Board from any further involvement in the planning process once it has made any determination pursuant to s.37B(4). If it makes a decision that the matter is not SID, and thus the planning application should be submitted to the planning authority, the arguments advanced by the applicant here would apply equally to a developer who wished to appeal a decision of a planning authority to the Board. In those circumstances, it could equally be argued that the Board had predetermined that the matter was not of strategic economic or social importance to the State and therefore had predetermined an issue which it had to consider on appeal. The applicant may say that is the consequence of a flawed legislative scheme and does not in itself invalidate his arguments; in my opinion it is more suggestive of the fallacy of the premise upon which the argument is based. I do not accept that this is a form of predetermination. It follows that the SID designation process does not trigger the rights to fair procedures contended for by the applicant. Irrational Directive 82. In view of the fact that I have concluded that as a matter of national law, the Board is not precluded from revisiting the s.37B decision in relation to the socio-economic aspects of an EIA when conducting the EIA pursuant to ss. 37D-G, it follows that there is no obligation on the Board at the pre-application stage to comply fully with the requirements of the Directive in relation to the conduct of an EIA. Therefore the arguments predicated on the fact that the pre-application assessment under s.37B does not satisfy the requirements of the Directive is not a ground for saying that the Directive has not properly been transposed into national law. Simply because the national procedure commences with a pre-application procedure, it does not follow that the procedure required by the Directive to exist in national law has to commence at this point. It is clear from Križan that the public participation right mandated by the Directive must afford the public merely an effective participation in the procedure when all options and solutions are possible. In R(Wells) it was held that the EIA must in principle be carried out as soon as it is possible to identify and assess all the effects which the project may have on the environment. This cannot be done before the application for planning permission has been submitted even if the public was entitled to participate at the pre-application stage. These cases do not lead to the conclusion that the Directive must be interpreted as precluding a member state from engaging with any issues which touch upon or concern the EIA at a stage in the statutory scheme from which the public is excluded as was argued by the applicant. 83. In fact in the case of C-431/92 Commission v. Germany it was held by the ECJ that the public participation provisions of the Directive apply from the date when the application for consent is formally lodged and not sooner. On the facts the ECJ rejected an argument that the preliminary consultations preceding the formal application for consent were a significant part of the consent procedure and therefore the Directive would have applied to the preliminary consultation. The Court held as follows:-
31 That argument cannot be accepted. 32 Informal contacts and meetings between the competent authority and the developer, even relating to the content a proposal to lodge an application for consent for a project, cannot be treated for the purposes of applying the directive as a definite indication of the date on which the procedure was initiated. The date when the application for consent was formally lodged thus constitutes the sole criterion which may be used. Such criterion accords with the principle of legal certainty and is designed to safeguard the effectiveness of the directive. The Court moreover followed this approach in Bund Naturschutz, cited above (paragraph 16). 33 The consent procedure for the project at issue must accordingly be regarded as having been initiated after the deadline of 3 July 1998, with the result that the project was required to undergo an assessment of its effects on the environment in accordance with a directive.” 85. The applicant argued that because the decision of 11th September, 2014, specifically referred to Article 7 that it necessarily followed that the public participation requirements of the Directive were engaged at this stage. In my opinion this argument also must be rejected. Article 7 requires that where a member state is aware that a project is likely to have significant effects on the environment in another member state, the Member State in whose territory the project is intended to be carried out is to send to the affected Member State:-
(a) a description of the project, together with any available information on its possible transboundary impact; (b) information on the nature of the decision which may be taken.” Preliminary reference to the CJEU
(a) the interpretation of the Treaties; (b) the validity and interpretation of acts of the institutions, bodies, offices or agencies of the Union; Where such a question is raised before any court or tribunal of a Member State, that court or tribunal may, if it considers that a decision on the question is necessary to enable it to give judgment, request the Court to give a ruling thereon. Where any such question is raised in a case pending before a court or tribunal of a Member State against whose decisions there is no judicial remedy under national law, that court or tribunal shall bring the matter before the Court. If such a question is raised in a case pending before a court or tribunal of a Member State with regard to a person in custody, the Court of Justice of the European Union shall act with the minimum of delay.”
(ii) are the provisions of Article 6(2), 6(3), 6(4) and 7(1) of the EIA Directive to be interpreted as meaning that the environmental impact assessment has commenced and the public concerned should be informed and/or consulted where a body, which is a competent authority for the purposes of the EIA Directive, in a process mandated by domestic law, makes a determination in respect of a proposed development which has the effect of giving to that competent authority jurisdiction to determine development consent and where, during the said process, the said body assesses and makes determinations in respect of whether the project is likely to have significant effects on the environment in another Member State and assesses and makes determinations in respect of matters which are required as part of an environmental impact assessment and which must, as a matter of domestic law, be considered when making its decision on development consent?”
67. I am not satisfied that the Court has jurisdiction pursuant to Article 267 to now request a preliminary ruling from the CJEU on the interpretation of Article 14 of the Framework Directive and Article 10 of the Landfill Directive as it does not appear to me that a ruling on the interpretation of those provisions is necessary…” Section 3 of the Environment (Miscellaneous Provisions) Act 2011
(a) Order 99 of the Rules of the Superior Courts ( S.I. No. 15 of 1986 ), (b) Order 66 of the Circuit Court Rules ( S.I. No. 510 of 2001 ), or (c) Order 51 of the District Court Rules ( S.I. No. 93 of 1997 ), and subject to subsections (2), (3) and (4), in proceedings to which this section applies, each party (including any notice party) shall bear its own costs. (2) The costs of the proceedings, or a portion of such costs, as are appropriate, may be awarded to the applicant, or as the case may be, the plaintiff, to the extent that he or she succeeds in obtaining relief and any of those costs shall be borne by the respondent, or as the case may be, defendant or any notice party, to the extent that the acts or omissions of the respondent, or as the case may be, defendant or any notice party, contributed to the applicant, or as the case may be, plaintiff obtaining relief. (3) A court may award costs against a party in proceedings to which this section applies if the court considers it appropriate to do so— (a) where the court considers that a claim or counter-claim by the party is frivolous or vexatious, (b) by reason of the manner in which the party has conducted the proceedings, or (c) where the party is in contempt of the court. (4) Subsection (1) does not affect the court’s entitlement to award costs in favour of a party in a matter of exceptional public importance and where in the special circumstances of the case it is in the interests of justice to do so. (5) In this section a reference to “court” shall be construed as, in relation to particular proceedings to which this section applies, a reference to the District Court, the Circuit Court, the High Court or the Supreme Court, as may be appropriate. 4.—(1) Section 3 applies to civil proceedings, other than proceedings referred to in subsection (3), instituted by a person— (a) for the purpose of ensuring compliance with, or the enforcement of, a statutory requirement or condition or other requirement attached to a licence, permit, permission, lease or consent specified in subsection (4), or (b) in respect of the contravention of, or the failure to comply with such licence, permit, permission, lease or consent, and where the failure to ensure such compliance with, or enforcement of, such statutory requirement, condition or other requirement referred to in paragraph (a), or such contravention or failure to comply referred to in paragraph (b), has caused, is causing, or is likely to cause, damage to the environment. (2) Without prejudice to the generality of subsection (1), damage to the environment includes damage to all or any of the following: (a) air and the atmosphere; (b) water, including coastal and marine areas; (c) soil; (d) land; (e) landscapes and natural sites; (f) biological diversity, including any component of such diversity, and genetically modified organisms; (g) health and safety of persons and conditions of human life; (h) cultural sites and built environment; (i) the interaction between all or any of the matters specified in paragraphs (a) to (h). (3) Section 3 shall not apply— (a) to proceedings, or any part of proceedings, referred to in subsection (1) for which damages, arising from damage to persons or property, are sought, or (b) to proceedings instituted by a statutory body or a Minister of the Government. (4) For the purposes of subsection (1), this section applies to— (a) a licence, or a revised licence, granted under section 83 of the Environmental Protection Agency Act 1992, (b) a licence granted pursuant to section 32 of the Act of 1987, (c) a licence granted under section 4 or 16 of the Local Government (Water Pollution) Act 1977, (d) a licence granted under section 63, or a water services licence granted under section 81, of the Water Services Act 2007, (e) a waste collection permit granted pursuant to section 34, or a waste licence granted pursuant to section 40, of the Act of 1996, (f) a licence granted pursuant to section 23(6), 26 or 29 of the Wildlife Act 1976, (g) a permit granted pursuant to section 5 of the Dumping at Sea Act 1996, (h) a licence granted under section 40, or a general felling licence granted under section 49, of the Forestry Act 1946, (i) a licence granted pursuant to section 30 of the Radiological Protection Act 1991, (j) a lease made under section 2, or a licence granted under section 3 of the Foreshore Act 1933, (k) a prospecting licence granted under section 8, a State acquired minerals licence granted under section 22 or an ancillary rights licence granted under section 40, of the Minerals Development Act 1940, (l) an exploration licence granted under section 8, a petroleum prospecting licence granted under section 9, a reserved area licence granted under section 19, or a working facilities permit granted under section 26, of the Petroleum and Other Minerals Development Act 1960, (m) a consent pursuant to section 40 of the Gas Act 1976, (n) a permission or approval granted pursuant to the Planning and Development Act 2000. (5) In this section— “damage”, in relation to the environment, includes any adverse effect on any matter specified in paragraphs (a) to (i) of subsection (2); “statutory body” means any of the following: (a) a body established by or under statute; (b) a county council within the meaning of the Local Government Act 2001; (c) a city council within the meaning of the Local Government Act 2001. (6) In this section a reference to a licence, revised licence, permit, permission, approval, lease or consent is a reference to such licence, permit, lease or consent and any conditions or other requirements attached to it and to any renewal or revision of such licence, permit, permission, approval, lease or consent… 7.—(1) A party to proceedings to which section 3 applies may at any time before, or during the course of, the proceedings apply to the court for a determination that section 3 applies to those proceedings. (2) Where an application is made under subsection (1), the court may make a determination that section 3 applies to those proceedings. (3) Without prejudice to subsection (1), the parties to proceedings referred to in subsection (1), may, at any time, agree that section 3 applies to those proceedings. (4) Before proceedings referred to in section 3 are instituted, the persons who would be the parties to those proceedings if those proceedings were instituted, may, before the institution of those proceedings and without prejudice to subsection (1), agree that section 3 applies to those proceedings. (5) An application under subsection (1) shall be by motion on notice to the parties concerned. 93. It is absolutely clear that a determination, pursuant to s.7, that s.3 of the Act of 2011 applies to the proceedings cannot be made unless there is a causative link between the failure to ensure compliance with, or the enforcement of, a statutory requirement and damage to the environment. The damage to the environment may have been caused, continuing or it may be something that is likely to be caused in the future. Section 4(2) of the Act of 2011 provides that damage to the environment includes damage to all or any of the matters set out. It includes (e) landscapes and natural sites and (g) health and safety of persons and conditions of human life. When asked to identify the damage to the environment upon which the applicant relied, counsel referred to the development which the notice parties hoped to carry out and asked rhetorically “how can it be said that there will not be damage to landscapes?” His case is thus based on the nature of the proposed development and the damage identified at s.4(2)(e). 94. It must be borne in mind that these proceedings relate to matters which occurred (or which did not occur) before any application for planning permission was lodged. There is no wind farm in existence therefore obviously there is no damage actually caused or being caused to the environment within the meaning of s.4. Therefore the issue is whether or not the failure asserted by the applicant to afford him his constitutional entitlement to fair procedures at the pre-application SID designation stage is likely to cause damage to the environment. 95. The entire purpose of applying for planning permission and of conducting EIAs is to assess developments and to determine their environmental effects and to regulate them, inter alia, for the purpose of avoiding damage to the environment. If the Court were to grant the applicant the determination pursuant to s.7 that he seeks, it would be predicated upon an assumption that this entire process would not be carried out properly in due course. Clearly, the Court cannot proceed on that basis. Simply put, this application does not fall within the parameters of s.4 and therefore s.3 of the Act of 2011 cannot apply to the proceedings. I refuse the determination sought. Conclusions 1 The Environmental Impact Assessment Directive 85/337/EEC and its three amendments have been codified by Directive 2011/92/EU
|