QUEEN'S BENCH
DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION
COURT
BIRMINGHAM CIVIL JUSTICE CENTRE 33 BULL STREET BIRMINGHAM B4 6DS Date of hearing: 9 April 2003 Date of draft judgment: 15 April 2003 | ||
B e f o r e :
____________________
COMSITE PROJECTS
LIMITED |
Claimant | |
and |
||
ANDRITZ AG |
Defendant |
____________________
Mr Andrew Burr of Counsel (instructed by Shepherd & Wedderburn)
for the Defendant
____________________
DATE OF
HTML VERSION OF JUDGMENT: 30 APRIL 2003
BEFORE HER HONOUR JUDGE FRANCES
KIRKHAM
HTML VERSION OF JUDGMENT
Crown Copyright ©
Background
"Settlement of disputes
All disputes arising in interpretation or execution of the present contract, its annexes or in connection with documents issued by both parties to the contract, including additional agreements concerning modifications to the contract, will be settled amicably.
If no agreement can be reached or if such agreement is not observed voluntarily by one of the parties, the jurisdiction in the event of a dispute will be in Austria, Graz. Austrian law will be applied…"
Does the court have jurisdiction to deal with the Part 8 claim?
Article 23 states:
"If the parties, one or more of whom is domiciled in a Member State, have agreed that a court or the courts of a Member State are to have jurisdiction to settle any disputes which have arisen or which may arise in connection with a particular legal relationship, that court or those courts shall have jurisdiction. Such jurisdiction shall be exclusive unless the parties have agreed otherwise.
"The Subcontractor and the Contractor agree that if the services of an Adjudicator are required under the Subcontract any one of the persons nominated below (a "Nominated Adjudicator") (who are to be invited to act in the order of precedence in which they are listed), may be appointed to act as Adjudicator if they are ready and willing to act in relation to the difference or dispute to be referred. It shall be the responsibility of the party making the reference to Adjudication under Clause 44 of the Conditions of Subcontract to determine before issuing an Adjudication Notice whether any of the Nominated Adjudicators is willing to act as Adjudicator in the dispute, and if a Nominated Adjudicator agrees to act, the party issuing the Adjudication Notice shall state in such Notice the name of the Adjudicator who has agreed to act."
The nominated adjudicators are then listed.
Is the Part 8 procedure appropriate?
Does the work fall within the definition of construction operations and is the Building Services sub-contract a construction contract?
"104 Construction contracts
(1) In this Part a "construction contract" means an agreement with a person for any of the following -
(a) the carrying out of construction operations"
"105 Meaning of "construction operations"
(2) The following operations are not construction operations within the meaning of this Part –
(c) assembly installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is -
(i) nuclear processing, power generation, or water or effluent treatment,…"
Conclusion
Comsite's works under the Building Services sub-contract fall within the definition of "construction operations" set out in Section 105 of the Housing Grants, Construction and Regeneration Act 1996, and accordingly:
the Building Services sub-contract constitutes a "construction contract" as defined in Section 104 of that Act; and
Part II of that Act applies to the Building Services sub-contract; and
both Comsite and AAG have the right to refer a dispute arising under the Building Services sub-contract for adjudication under a procedure complying with Section 108 of that Act.