The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 No. 3104

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 No. 3104

Statutory Instruments

2012 No. 3104

Highways, England

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012

Made

10th December 2012

Coming into force

1st March 2013

The Secretary of State for Transport having approved the Royal Borough of Kingston upon Thames Permit Scheme under section 34(2) of the Traffic Management Act 2004(1) makes this Order in exercise of the powers conferred by sections 34(4) and (5) and 39(2) of that Act.

Citation and commencement

1. This Order may be cited as the Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 and comes into force on 1st March 2013.

Interpretation

2. In this Order-

"the Royal Borough of Kingston upon Thames Permit Scheme" means the permit scheme set out in the Schedule in terms commonly known as the "London Permit Scheme" which was prepared and submitted to the Secretary of State by the Royal Borough of Kingston upon Thames and has been approved by the Secretary of State; and

"specified streets" has the meaning given by regulation 8 of the Traffic Management Permit Scheme (England) Regulations 2007(2).

Commencement of Permit Scheme

3. The Royal Borough of Kingston upon Thames Permit Scheme comes into effect on 1st March 2013.

Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007

4. Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 shall apply to the specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

Signed by authority of the Secretary of State for Transport

Norman Baker

Parliamentary Under Secretary of State

Department for Transport

10th December 2012

Article 2

SCHEDULETHE ROYAL BOROUGH OF KINGSTON UPON THAMESPERMIT SCHEME

EXPLANATORY NOTE

(This note is not part of the Order)

This Order gives effect to the Royal Borough of Kingston upon Thames Permit Scheme.

The Royal Borough of Kingston upon Thames Permit Scheme is designed to control the carrying out of works in specified streets in Kingston upon Thames by imposing an obligation to obtain a permit from the Royal Borough of Kingston upon Thames before undertaking the works.

Article 3 gives effect to the permit scheme, which will come into effect on 1st March 2013. The permit scheme referred to in this article is set out in the Schedule to the Order.

Article 4 applies Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 (which makes provision for the disapplication and modification of enactments in relation to specified works in specified streets) to the specified works and specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

A copy of the Royal Borough of Kingston upon Thames Permit Scheme is deposited and can be inspected at the offices of the Royal Borough of Kingston upon Thames, Main Reception, Guildhall 2, High Street, Kingston upon Thames, KT1 1EU and is available to inspect on the Borough's website www.kingston.gov.uk.

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 No. 3104

Statutory Instruments

2012 No. 3104

Highways, England

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012

Made

10th December 2012

Coming into force

1st March 2013

The Secretary of State for Transport having approved the Royal Borough of Kingston upon Thames Permit Scheme under section 34(2) of the Traffic Management Act 2004(1) makes this Order in exercise of the powers conferred by sections 34(4) and (5) and 39(2) of that Act.

Citation and commencement

1. This Order may be cited as the Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 and comes into force on 1st March 2013.

Interpretation

2. In this Order-

"the Royal Borough of Kingston upon Thames Permit Scheme" means the permit scheme set out in the Schedule in terms commonly known as the "London Permit Scheme" which was prepared and submitted to the Secretary of State by the Royal Borough of Kingston upon Thames and has been approved by the Secretary of State; and

"specified streets" has the meaning given by regulation 8 of the Traffic Management Permit Scheme (England) Regulations 2007(2).

Commencement of Permit Scheme

3. The Royal Borough of Kingston upon Thames Permit Scheme comes into effect on 1st March 2013.

Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007

4. Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 shall apply to the specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

Signed by authority of the Secretary of State for Transport

Norman Baker

Parliamentary Under Secretary of State

Department for Transport

10th December 2012

Article 2

SCHEDULETHE ROYAL BOROUGH OF KINGSTON UPON THAMESPERMIT SCHEME

EXPLANATORY NOTE

(This note is not part of the Order)

This Order gives effect to the Royal Borough of Kingston upon Thames Permit Scheme.

The Royal Borough of Kingston upon Thames Permit Scheme is designed to control the carrying out of works in specified streets in Kingston upon Thames by imposing an obligation to obtain a permit from the Royal Borough of Kingston upon Thames before undertaking the works.

Article 3 gives effect to the permit scheme, which will come into effect on 1st March 2013. The permit scheme referred to in this article is set out in the Schedule to the Order.

Article 4 applies Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 (which makes provision for the disapplication and modification of enactments in relation to specified works in specified streets) to the specified works and specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

A copy of the Royal Borough of Kingston upon Thames Permit Scheme is deposited and can be inspected at the offices of the Royal Borough of Kingston upon Thames, Main Reception, Guildhall 2, High Street, Kingston upon Thames, KT1 1EU and is available to inspect on the Borough's website www.kingston.gov.uk.

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 No. 3104

Statutory Instruments

2012 No. 3104

Highways, England

The Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012

Made

10th December 2012

Coming into force

1st March 2013

The Secretary of State for Transport having approved the Royal Borough of Kingston upon Thames Permit Scheme under section 34(2) of the Traffic Management Act 2004(1) makes this Order in exercise of the powers conferred by sections 34(4) and (5) and 39(2) of that Act.

Citation and commencement

1. This Order may be cited as the Traffic Management (Royal Borough of Kingston upon Thames) Permit Scheme Order 2012 and comes into force on 1st March 2013.

Interpretation

2. In this Order-

"the Royal Borough of Kingston upon Thames Permit Scheme" means the permit scheme set out in the Schedule in terms commonly known as the "London Permit Scheme" which was prepared and submitted to the Secretary of State by the Royal Borough of Kingston upon Thames and has been approved by the Secretary of State; and

"specified streets" has the meaning given by regulation 8 of the Traffic Management Permit Scheme (England) Regulations 2007(2).

Commencement of Permit Scheme

3. The Royal Borough of Kingston upon Thames Permit Scheme comes into effect on 1st March 2013.

Application of Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007

4. Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 shall apply to the specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

Signed by authority of the Secretary of State for Transport

Norman Baker

Parliamentary Under Secretary of State

Department for Transport

10th December 2012

Article 2

SCHEDULETHE ROYAL BOROUGH OF KINGSTON UPON THAMESPERMIT SCHEME

EXPLANATORY NOTE

(This note is not part of the Order)

This Order gives effect to the Royal Borough of Kingston upon Thames Permit Scheme.

The Royal Borough of Kingston upon Thames Permit Scheme is designed to control the carrying out of works in specified streets in Kingston upon Thames by imposing an obligation to obtain a permit from the Royal Borough of Kingston upon Thames before undertaking the works.

Article 3 gives effect to the permit scheme, which will come into effect on 1st March 2013. The permit scheme referred to in this article is set out in the Schedule to the Order.

Article 4 applies Part 8 of the Traffic Management Permit Scheme (England) Regulations 2007 (which makes provision for the disapplication and modification of enactments in relation to specified works in specified streets) to the specified works and specified streets within the Royal Borough of Kingston upon Thames Permit Scheme.

A copy of the Royal Borough of Kingston upon Thames Permit Scheme is deposited and can be inspected at the offices of the Royal Borough of Kingston upon Thames, Main Reception, Guildhall 2, High Street, Kingston upon Thames, KT1 1EU and is available to inspect on the Borough's website www.kingston.gov.uk.